The Cabinet was informed that the changes to the capital programme identified in the report by the Head of Finance had decreased the overall size of the remaining three year programme by £5,633k. The changes were summarised and set out in detail in the report. This included: New external grant funded schemes at £1,620,000; An increase in S106 and other contributions at £80,000; The use of earmarked reserve at £46,000; A Budget increase, where previously omitted, to existing borrowing funded schemes at £520,000; Reduction of schemes/ removal of budget – £4,980,000; A Re-profiling of the budget into the four year programme starting 2018/19 – £2,919,000; Details of the expenditure position as at December 2015 were set out in the report. These details showed the forecast outturn position for the 2015/16 programme was estimated to be £25,557,000. An update was also provided on the headline / high value schemes in the programme. The current position on capital receipts was set out in the report. The value of receipts earmarked for use as match funding for the 21 st Century Schools Programme Band A had reached its target of £7.5m. Cabinet Members were pleased to see the improved position in relation to slippage which had been a matter of concern in the past. Members expressed the importance of contractors meeting timescales. This was the subject of discussions with Norse.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject Capital Programme Monitoring and Additions January 2016 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.
To submit the re-profiled Capital Programme budgets to Cabinet for approval.
To update Cabinet on current spending against the revised Capital Programme schemes highlighting the forecast outturn position for the programme as at January 2016.
Author Senior Finance Business Partner (Capital)
Ward All Wards
Summary The report requests that new schemes be added to the programme, and updates Cabinet on the budget re-profiling undertaken.
The report also updates Cabinet on the capital expenditure forecast position and the current position regarding capital receipts.
Proposals To approve the additions to the Capital Programme requested in the report. To approve the re-profiled capital budgets and note the capital expenditure forecast position as at January 2016.
To note and approve the allocation of in-year capital receipts.
Action by Assistant Head of Finance
Timetable Immediate This report was prepared after consultation with:
Heads of Service Directors Accountancy teams for relevant service areas Relevant Service Area Project Managers NORSE Property Services Background In February 2014, the Council approved a four year Capital Programme to cover the financial years 2014/15 to 2017/18 totalling £80.551 million. We are now in the second year of the four-year programme, and over time changes have been made to the programme to revise the total budget to £110.577 million. The most recent changes are based on the reprofiling exercise that has been undertaken during the past three months, as well as the addition of new capital schemes. The table below shows the changes made to date:
Report 2014/15 2015/16 2016/17 2017/18 Total £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Capital Programme Outturn 52,160 16,083 28,629 20,063 116,935 Report 14/15 (budgets) Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 (revised for slippage) July 2015 Additions Report 27,197 42,198 27,813 20,063 117,271 October 2015 Monitoring Report 27,197 41,153 27,797 20,063 116,210 This Report 27,197 26,095 39,087 18,198 110,577
Changes to the approved Capital Programme The changes to the capital programme identified in this report have decreased the overall size of the remaining three year programme by £5,633k. The revised capital programme is shown in Appendix A, with the overall changes summarised below:
New external grant funded schemes – £1,620k Schools Challenge Cymru (£159k) – Welsh Government have approved this allocation for 2015/16, with the schools benefitting from an improved teaching and learning environment being Llanwern High, Lliswerry High, and St Julians School. Flying Start (£124k) – additional funding awarded by WG to be used for small projects at six LSOAs. Energy Efficiency (£402k) – remaining grant money available from WG to enable NCC to administer grant awards to qualifying social housing tenants to fund improvements to efficiency via insulation works, boiler replacements and overcladding works. Substance Misuse Action Fund (£935k) – NCC acts as an agent, administering this grant on behalf of WG, who provide full funding for applicable schemes annually. The approved schemes for 2015/16 have been confirmed.
Increase in S106 and other contributions – £80k Street Lighting (£80k) – additional funding has been secured by Streetscene from an external developer, which is being used to supplement the existing annual sums allocation for this year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.