CAB 53/17 The Leader of the Council presented the standard update on the capital budget, monitoring the programme of spending and asking Cabinet to approve any additions since the last monitor. It was reported that the forecast outturn was looking similar to previous years, carrying a small underspend. Further monitors would be reported through the year to ensure this position was maintained. To approve the additions to the Capital Programme requested in the report. To note the capital expenditure forecast position as at July 2017. To note the balance of and approve the allocation of in-year capital receipts. Heads of Service, Accountancy Teams for relevant service areas, relevant service area project managers. Implemented By: Assistant Head of Finance Implementation Timetable: Immediate To approve the additions to the Capital Programme requested in the report. To note the capital expenditure forecast position as at July 2017. To note the balance of and approve the allocation of in-year capital receipts.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject Capital Programme Monitoring and Additions July 2017 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.
To update Cabinet on current spending against the Capital Programme schemes highlighting the forecast outturn position for the programme as at July 2017.
Author Senior Finance Business Partner (Capital)
Ward All Wards
Summary The report requests that new schemes be added to the programme. The report also updates Cabinet on the current capital expenditure position as at the end of July 2017 along with the forecast outturn for 2017/18. The net effect of the forecasts provided shows an overall Authority-wide underspend variance of £3,631k against the budget of £43,312k. This includes forecast slippage of budget into 2018/19 to the value of £1,789k, giving a true forecast underspend of £1,842k.
Whilst not currently forecast as an overspend, the Gypsy/ Traveller Site project is currently being reviewed in order to reduce initial costings as there is a risk that an overspend position could be reported in future reports if not addressed.
The report also updates Cabinet on the current position regarding capital receipts. To date £770k has been received in-year, which is a significant step towards the total £1,000k estimated to be achieved by the end of this financial year.
Proposal To approve the additions to the Capital Programme requested in the report.
To note the capital expenditure forecast position as at July 2017.
To note the balance of and approve the allocation of in-year capital receipts.
Action by Assistant Head of Finance
Timetable Immediate This report was prepared after consultation with:
Heads of Service Accountancy teams for relevant service areas Relevant Service Area Project Managers NORSE Property Services
Signed Background 2017/18 is the final year of the current four-year capital programme originally approved by Council in February 2014 at an overall cost of £80.551 million. Over time, a number of changes have been made to the programme due to emerging developments, re-evaluation of priorities and the availability of specific funding sources; these changes have been reported to and approved by Cabinet on a quarterly basis over the past three years. The total budget for the period as a whole now stands at £128.685 million. The table below summarises the changes made to date:
2014/15 2015/16 2016/17 2017/18 Total Report £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 Actual Actual Budget Budget Capital Programme Outturn 27,197 25,783 42,137 18,198 113,315 Report 15/16 Actual Actual Actual Budget Capital Programme Outturn 27,197 25,783 32,393 39,456 124,829 Report 16/17 This Report 27,197 25,783 32,393 43,312 128,685
Changes to the approved Capital Programme The changes to the capital programme identified in this report have increased the overall size of the current year programme by £3,856k (and the 2018/19 committed programme by £600k) since reported in June 2017. These should have no net revenue impact on the budget as all the revenue financing costs for the extra borrowing is covered by existing service area/ school budgets. The capital budget changes and their associated funding are listed in Appendix A and are requested to be approved by Cabinet, whilst Appendix B shows the revised capital programme for 2017/18 including the proposed changes. These changes are summarised in the paragraphs below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.