Cabinet decided this item on Monday 12 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
text
Report Cabinet Part 1
Date: 12 September 2016
Item No: Insert item number here
Subject City Deal – Update and consideration of Memorandum of Understanding Purpose To provide an update to cabinet about the ongoing city deal process and seek agreement to sign the updated Memorandum of Understanding between the 10 authorities which will guide the process.
Author Will Godfrey – Chief Executive
Ward All
Summary In March of this year, the council signed the outline city deal, which is an agreement between the 10 authorities of the Cardiff Capital City Region (CCCR), UK Government and Welsh Government. The deal outlines how all parties can work together to improve economic outcomes across the city region. It also outlines the creation of an Infrastructure Investment Fund of £1.229bn which, if certain conditions are met, could be invested over a 20 year period to deliver projects aimed at improving economic outcomes.
There is still a long way to go and the council will need to consider carefully whether the investment will deliver value for money and outcomes which meet the needs of our communities. However it is important at this point to continue our involvement in the process and work with other partners to secure the best deal possible.
Any final proposal will require sign off by council and it is anticipated this will take place before the end of the 2016/17 financial year.
Proposal Cabinet is asked to:
1. Endorse the work to date on the city deal and support the ongoing work to its conclusion. 2. Agree the attached Memorandum of Understanding between the 10 authorities and authorise the Chief Executive to sign on behalf of the council.
Action by Chief Executive
Timetable Immediate This report was prepared after consultation with: Leader of the Council Background Newport City Council has been working with the other 9 authorities making up the South East Wales region to secure a city deal which could potentially bring investment worth £1.229bn over the next 20 years to improve economic outcomes for the communities across the region.
A city deal is a mechanism designed by UK Govt, which began in 2012, as a means of ensuring better regional working to secure infrastructure investment. A commitment was given by the Chancellor of the Exchequer in November 2014 to consider developing a city deal for the Cardiff region and discussions began in earnest in the summer of 2015. Cabinet received a report in June 2015 to outline the commitment needed from the council, including the agreement to contribute £50,000 to a joint fund to finance the necessary work to secure agreement on a city deal. At this point Welsh Government joined the discussions.
An informal structure was created by the 10 authorities to co-ordinate the work, with each authority represented by the Leader of the Council. Officer working groups were also created to ensure all the authorities worked together to develop an initial proposal.
Essentially there are three phases to a city deal:
Phase 1 – development of initial proposal which outlines the headline commitments from all parties and the overall aims from the deal. This phase is concluded with the signing of a “Heads of Terms” document between the parties – local authorities, UK Govt and Welsh Govt.
Phase 2 – translates the Heads of Terms into more detailed agreement. This needs to outline financial commitments from all parties and also provide more clarity about the projects which will be funded through the city deal money. This phase concludes with each authority signing (or not) an assurance framework which essentially is a document outlining the rules to secure release of the city deal money.
Phase 3 – delivery of the city deal projects and evaluation of the economic impact.
We reached the end of phase 1 in March 2016 when all parties – local authorities, UK Govt and Welsh Govt signed the “Heads of Terms”. The deal document is attached at appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
City Deal: Update and Memorandum of UnderstandingReport | 592 KB | DownloadRead as text |
Follow Cabinet at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. | Approved | Open |
| 8 Jul 2026 | Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... | Approved | Open |
| 8 Jul 2026 | Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. | Approved | Open |
| 8 Jul 2026 | Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... | Agreed | Open |
| 17 Jun 2026 | Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.