Capital Programme Monitoring and Additions

Approved Executive 1 paper

Cabinet approved this item on Monday 12 September 2016. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

I. To approve the additions to the Capital Programme requested in the report. II. To note the capital expenditure forecast position as at July 2016. III. To note and approve the allocation of in-year capital receipts.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 12th September 2016

Item No:

Subject Capital Programme Monitoring and Additions July 2016 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.

To update Cabinet on current spending against the Capital Programme schemes highlighting the forecast outturn position for the programme as at July 2016.

Author Senior Finance Business Partner (Capital)

Ward All Wards

Summary The report requests that new schemes be added to the programme. The report also updates Cabinet on the capital expenditure forecast position and the current position regarding capital receipts.

Proposal To approve the additions to the Capital Programme requested in the report.

To note the capital expenditure forecast position as at July 2016.

To note and approve the allocation of in-year capital receipts.

Action by Assistant Head of Finance

Timetable Immediate This report was prepared after consultation with:

 Heads of Service  Accountancy teams for relevant service areas  Relevant Service Area Project Managers  NORSE Property Services

Signed Background  In February 2014, the Council approved a four year Capital Programme to cover the financial years 2014/15 to 2017/18 totalling £80.551 million. We are now in the third year of the four-year programme, and over time changes have been made to the programme to revise the total budget to £116.138 million. The table below summarises the changes made to date:

Report 2014/15 2015/16 2016/17 2017/18 Total £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 Actual Actual Budget Budget Capital Programme Outturn 27,197 25,783 42,137 18,198 113,315 Report 15/16 This Report 27,197 25,783 46,823 18,198 118,001

 The changes to the capital programme identified in this report have increased the overall size of the remaining two year programme by £4,686k. The resulting changes to the funding of the capital programme are:  Increase in external grant – £2,167k  Increase in S106 and other contributions – £2,079k  Increase in direct revenue contributions – £258k  Use of capital receipts – £55k  Increase in unsupported borrowing – £127k

 As 2017/18 will be the final year of the existing four-year programme, proposals in line with the Council’s strategic and corporate priorities will now need to be considered by directorates and bids for projects formulated and submitted for inclusion in the Capital Programme from 2018/19 onwards. It is proposed that the Council now move to a rolling four-year programme rather than a ‘fixed’ format, for consistency with financial planning for revenue budgets and to allow borrowing implications to be forecast into the medium term at all times. This is also generally accepted best practice amongst other Local Authorities.

 Cabinet will note the content of the separate Education Capital Programme report presented at this meeting and be aware that the budget position summarised above is likely to be subject to significant change depending on the decisions to be made to address the current capital budget issues with the Education Capital Programme and is subject to approval of additional funding from Welsh Government.

Changes to the approved Capital Programme

 New schemes are listed in Appendix A and are requested to be added to the capital programme. Appendix B of this report shows the revised 2016/17 programme, including the proposed schemes. A summary of the key programme changes are outlined in the following paragraphs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring and AdditionsReport 659 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, apologies
RP
Councillor Robert PooleCommittee Member, present
JR
Councillor John RichardsCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, apologies

On this subject at Newport

Search all
  1. Capital Programme Monitoring and AdditionsThis decision
  2. Capital Programme Monitoring and Additions Report - 2025/26 OutturnApproved
  3. Capital Programme Monitoring and Additions Report - October 2025Approved
  4. Capital Programme Monitoring and Additions - JulyApproved
  5. Capital Programme Monitoring and Additions OutturnApproved
  6. Capital Programme Monitoring and Additions Report - November 2024Approved

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies