Resolved
I. To approve the additions to the Capital Programme requested in the report. II. To note the capital expenditure forecast position as at July 2016. III. To note and approve the allocation of in-year capital receipts.
Cabinet approved this item on Monday 12 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
I. To approve the additions to the Capital Programme requested in the report. II. To note the capital expenditure forecast position as at July 2016. III. To note and approve the allocation of in-year capital receipts.
Report Cabinet Part 1
Date: 12th September 2016
Item No:
Subject Capital Programme Monitoring and Additions July 2016 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.
To update Cabinet on current spending against the Capital Programme schemes highlighting the forecast outturn position for the programme as at July 2016.
Author Senior Finance Business Partner (Capital)
Ward All Wards
Summary The report requests that new schemes be added to the programme. The report also updates Cabinet on the capital expenditure forecast position and the current position regarding capital receipts.
Proposal To approve the additions to the Capital Programme requested in the report.
To note the capital expenditure forecast position as at July 2016.
To note and approve the allocation of in-year capital receipts.
Action by Assistant Head of Finance
Timetable Immediate This report was prepared after consultation with:
Heads of Service Accountancy teams for relevant service areas Relevant Service Area Project Managers NORSE Property Services
Signed Background In February 2014, the Council approved a four year Capital Programme to cover the financial years 2014/15 to 2017/18 totalling £80.551 million. We are now in the third year of the four-year programme, and over time changes have been made to the programme to revise the total budget to £116.138 million. The table below summarises the changes made to date:
Report 2014/15 2015/16 2016/17 2017/18 Total £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 Actual Actual Budget Budget Capital Programme Outturn 27,197 25,783 42,137 18,198 113,315 Report 15/16 This Report 27,197 25,783 46,823 18,198 118,001
The changes to the capital programme identified in this report have increased the overall size of the remaining two year programme by £4,686k. The resulting changes to the funding of the capital programme are: Increase in external grant – £2,167k Increase in S106 and other contributions – £2,079k Increase in direct revenue contributions – £258k Use of capital receipts – £55k Increase in unsupported borrowing – £127k
As 2017/18 will be the final year of the existing four-year programme, proposals in line with the Council’s strategic and corporate priorities will now need to be considered by directorates and bids for projects formulated and submitted for inclusion in the Capital Programme from 2018/19 onwards. It is proposed that the Council now move to a rolling four-year programme rather than a ‘fixed’ format, for consistency with financial planning for revenue budgets and to allow borrowing implications to be forecast into the medium term at all times. This is also generally accepted best practice amongst other Local Authorities.
Cabinet will note the content of the separate Education Capital Programme report presented at this meeting and be aware that the budget position summarised above is likely to be subject to significant change depending on the decisions to be made to address the current capital budget issues with the Education Capital Programme and is subject to approval of additional funding from Welsh Government.
Changes to the approved Capital Programme
New schemes are listed in Appendix A and are requested to be added to the capital programme. Appendix B of this report shows the revised 2016/17 programme, including the proposed schemes. A summary of the key programme changes are outlined in the following paragraphs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Monitoring and AdditionsReport | 659 KB | DownloadRead as text |
Follow Cabinet at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. | Approved | Open |
| 8 Jul 2026 | Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... | Approved | Open |
| 8 Jul 2026 | Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. | Approved | Open |
| 8 Jul 2026 | Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... | Agreed | Open |
| 17 Jun 2026 | Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.