CAB 54/17 The Leader of the Council introduced the report, asking Cabinet to approve a finance package of just over £1m and negotiate terms of an on-lending facility necessary to secure the redevelopment of and additional housing led regeneration projects. Presenting the detail of the proposals, the Cabinet Member for Regeneration and Housing reported that this represented the next steps in the redevelopment of this area, which was a key city centre gateway. The Cabinet Member noted the positive response from the public to these proposals, and the importance of realising this project to revitalise this area of the city. Cabinet Members spoke in favour of the proposals, welcoming the scheme and the much needed investment it would bring to this area. Thanks were also given to the members and officers involved in developing and negotiating these proposals to ensure the project could go ahead. To approve a finance package of £1,050,700 and negotiate terms of an on-lending facility necessary to secure the redevelopment of 123-129 Commercial Street and additional housing led regeneration projects. Leader of the Council, Strategic Director – Place, Head of Finance, Head of Law and Regulation, Cabinet Member for Regeneration and Housing Implemented By: Head of Regeneration, Investment and Housing Implementation Timetable: Immediate To approve a finance package of £1,050,700 and negotiate terms of an on-lending facility necessary to secure the redevelopment of 123-129 Commercial Street and additional housing led regeneration projects.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject 123-129 Commercial Street Purpose To advise the Cabinet of current proposals in relation to the delivery of this scheme and to seek approval of the financial considerations arising
Author Matt Tribbeck, Regeneration Manager
Ward Stow Hill
Summary The redevelopment of 123-129 Commercial Street is the flagship project of Newport’s Vibrant and Viable Places programme. Welsh Government has ring-fenced the remaining £3.097m of Newport’s Vibrant and Viable Places funding into a fourth year of the programme to allow the development to proceed. This funding forms part of a package which seeks to deliver further housing-led regeneration projects within the city alongside the redevelopment of 123-129 Commercial Street. The Council would need to make a financial commitment to the scheme in order to secure the development and bring this £10m investment into Newport City Centre.
Proposal To approve a finance package of £1,050,700 and negotiate terms of an on-lending facility necessary to secure the redevelopment of 123-129 Commercial Street and additional housing led regeneration projects.
Action by Keir Duffin, Head of Regeneration, Investment & Housing
Timetable Immediate This report was prepared after consultation with:
Leader of the Council Strategic Director - Place Head of Finance (Chief Finance Officer) Head of Law and Regulation (Monitoring Officer) Cabinet Member for Regeneration and Housing
Signed Background
.1 This project will redevelop an obsolete block of city centre properties acquired by the Pobl Group in accordance with agreed aims and objectives of the Vibrant and Viable Places (VVP) programme. 123-129 Commercial Street includes the entrance to the Park Square Car Park and the redevelopment will therefore transform a key city centre gateway as well as delivering much- needed new affordable homes for older people.
.2 Additional funding has been understood to be required for some time due to a number of inflationary factors. The proposed development sits in a difficult urban location and the complexity of the scheme intersects with an ambition to deliver a statement development synonymous with the renewed sense of confidence around the city centre. On-site constraints and market conditions, notably the buoyancy of the local construction industry, have also played a role towards inflating costs. Any dilution of the redevelopment will run contrary to the Planning consent for the scheme and restrict the regeneration impact achieved, which limits the potential to value-engineer the scheme costs down.
.3 The main source of funding for the development remains the Welsh Government, via a combination of VVP funding secured against the scheme and a requested allocation of Social Housing Grant (SHG). Detailed work has continued to both further improve the financial viability and explore synchronicities between this development and additional housing-led opportunities within the city centre that could be incorporated within the funding envelope of 123-129 Commercial Street. In order to satisfy Welsh Government’s Social Housing Grant conditions, there is a requirement to lever in additional affordable housing units. This responsibility is being undertaken by Pobl and will not incur further cost to the project or NCC.
Financial Summary
Capital Costs Position July 2017 (123-129 Package Option (123-129 only) and additional 18 units) Acquisitions £791,700 £791,700 Main Works £9,250,000 £11,331,384 On-costs £502,085 (@5%) £689,409 (@6%) NCC On-lending Saving (£200,000) (£200,000) (to be negotiated) Under croft Car Park Income (£100,000) (£100,000) Total Scheme Cost £10,243,785 £12,512,493 Funding VVP £3,855,000 £3,855,000 SHG £2,602,085 £2,602,085 NCC Contribution £1,050,700 £1,050,700 Pobl Private Finance £2,736,000 £5,004,709 Total Scheme Cost £10,243,785 £12,512,494
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.