CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newport City Council
Cabinet, Monday 12 January 2026 at 4.00pm

Mid-Year Reviews Service Area Plans 2025-26

Noted Executive 1 paper

AI summaryNewport City Council Cabinet noted mid-year reviews of 11 service area plans for 2025/26, finding most objectives and measures on track, with eight of 41 objectives amber and nine of 113 measures red.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted mid-year progress of 11 service areas against plans
MoneyNo direct costsReport carries no direct financial cost
What happens nextEnd of year reports June/July 2026Service areas to continue monitoring through 2025/26
Who it affectsAll wards, all service areasCouncil-wide service plan performance review

What was decided

Cabinet noted the contents of the mid-year assessment report covering 1 April to 30 September 2025. Report P9, P15

The assessment covers 11 service areas, 41 objectives and 113 performance measures linked to the Corporate Plan 2022-27 and four Well-being Objectives. Report P6, P7, P13

Performance is largely on track, with 53 measures green (47%), 12 amber (11%), 9 red (8%) and 39 for information (34%), and only 8 of 41 objectives rated amber. Report P7, P21

Why

The report is a routine mid-year check on progress against service plans and supports the Council's duties under the Well-being of Future Generations Act and the Local Government and Elections (Wales) Act. Report P14, P15

Scrutiny committees reviewed each service area's assessment in November and December 2025 and their feedback will feed into the end-of-year review and 2026/27 service plans. Report P8, P16, P37

Finance and Housing & Communities hold the highest numbers of red and amber measures, including council tax collection, e-billing uptake, customer contact waiting times, audit coverage and homelessness outcomes. Report P21, P53, P54, P55

What happens next

Service areas will continue to monitor performance for the rest of 2025/26, with updates to Cabinet Members and an Executive Board end-of-year review. Report P24

End-of-year reports will be presented in June or July 2026 (dates to be confirmed) and will feed the Council's overall self-assessment against the Corporate Plan. Report P24

Scrutiny committee recommendations, including a Pupil Attendance Report for February 2026, a city-wide bin review update and a note on South Distributor Road street lighting, will be progressed. Report P38, P39

The money

  • £58,216,304 Council Tax collected by mid-year (51.82% of £112,339,136 due) Report P54

Options considered

  • Chosen: Note the report and continue to monitor service area performance in 2025/26. Preferred option; the report provides the routine mid-year update and monitoring will continue. Report P30, P31, P32
  • Rejected: Reject the report or ask for further information. No reason given; the alternative was not preferred. Report P30

Implications

  • Risk: Risk that the Council cannot achieve the objectives and outcomes of the Corporate Plan, mitigated by quarterly performance reviews and mid-year and end-of-year performance reviews. Report P28
  • Equalities: No Equality Impact Assessment was completed because the report is for information only. Report P40
  • Climate: Progress against the Council's Climate Change Plan is reported in the body of the report; the report itself is for information. Report P45
  • Legal: There are no legal implications arising directly from the report, which is for noting and comment. Report P35
  • Financial: There are no direct financial impacts; many underlying service objectives have financial impacts which were reported in detail to Scrutiny committees. Report P26, P33, P34
  • Other: The report supports compliance with the Well-being of Future Generations (Wales) Act 2015 and the Local Government and Elections (Wales) Act. Report P14, P41

Who and where

  • All 11 council service areas, covering Environment and Public Protection, Housing and Communities, Environment and Sustainability, Infrastructure, Regeneration and Economic Development, Adult Services, Children Services, Prevention and Inclusion, Education, Finance, Law and Standards, and People Policy and Transformation. Report P13, P18, P19, P20
  • Residents of Newport across all wards, as service areas covering housing, social care, education, waste, highways and leisure are included. Report P5, P23, P55
  • Cabinet Members and the Executive Board who receive regular performance updates. Report P10, P24

Timeline

  • 1st April to 30th September 2025: First six months of 2025/26 covered by the mid-year assessment. Report P6, P15
  • 24th November and 8th December 2025: Place and Corporate Performance Scrutiny Committee reviewed the mid-year reports. Report P39
  • 2nd December and 9th December 2025: People Scrutiny Committee reviewed the mid-year reports. Report P38
  • 5 January 2026: Report dated for the Cabinet meeting. Report P48
  • 12 January 2026: Cabinet meeting where the report was noted. Report P2
  • February 2026: Pupil Attendance Report to be presented to Scrutiny; partnership board to consider Youth Justice first-time entrants data. Report P38, P51
  • June / July 2026 (dates to be confirmed): End-of-year 2025/26 service area reports to be presented. Report P24
  • Mid-2026: Refurbishment of a further two-bedded children disabilities home due for completion. Report P23

Plain English for the jargon

  • RAG (Red / Amber / Green): A status scale used to rate how far a service area or performance measure is meeting its target, with green on target, amber within tolerance and red off target.
  • Service Area Plan: An annual plan for a council service area setting out its objectives, performance measures, risks and workforce development to support the Corporate Plan.
  • Well-being Objectives: The four statutory objectives of Newport's Corporate Plan 2022-27: Economy, Education and Skills; Environment and Infrastructure; Quality Social Care and Community Services; and an Inclusive, Fair and Sustainable Council.
  • Well-being of Future Generations (Wales) Act 2015: Welsh law requiring public bodies to consider the long-term impact of their decisions on future generations, using the sustainable development principle and five ways of working.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Cabinet noted the contents of this report.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 12 January 2026

Subject Mid-Year Assessment Report 2025/26 Purpose For Cabinet to agree the Mid-year Assessment Report of service area progress against their Service Plans 2025/26

Author Chief Executive Director of Transformation and Corporate

Ward All

Summary The Council’s 11 service areas have developed service area plans which set out how they will contribute towards the delivery of the Council’s Corporate Plan 2022-27 and its four Well-being Objectives. This report provides a summary on the progress which service areas have made in the first six months of 2025/26 (1st April to 30th September 2025).

The Mid-year assessment shows that service areas are making good progress in the delivery of their objectives and actions with only eight out of 41 objectives reporting Amber progress. Within each objective there are 113 performance measures reported: • 9 (8%) Red performance measures • 12 (11%) Amber performance measures • 53 (47%) Green performance measures • 39 (34%) Performance measures for information

Each service area presented their Mid-year assessment to the Place and Corporate and People Scrutiny Committees in November and December 2025. The feedback and comments raised by the scrutiny committees will be considered for future service plan development, scrutiny committee review and reporting of the Council’s annual report 2025/26.

Proposal To note and comment on the contents of this report.

Action by Executive Board Corporate Management Team

Timetable Immediate

This report was prepared after consultation with:

▪ Executive Board ▪ Corporate Management Team ▪ Place & Corporate Scrutiny Committee ▪ People Scrutiny Committee Background Service area plans 2025/26 have been developed to support the delivery of the Council’s Corporate Plan and its four Well-being Objectives of Economy, Education and Skills; Environment and Infrastructure; Quality Social Care and Community Services; and an Inclusive, Fair and Sustainable Council. Each of the 11 service area plans outlines their key priorities relating to: • Objectives to support the delivery of the Corporate Plan, strategic priorities and continuous improvement. • Performance Measures • Risks (Corporate and Service level) • Workforce Development

This also contributes towards the Council’s compliance with the Well-being of Future Generations Act and the Local Government and Elections (Wales) Act.

Service Plan Mid-Year Assessment 2025/26 This report provides an overview of the progress the 11 Service Areas have made between 1st April and 30th September 2025 in the delivery of: • Service Area Objectives and Actions including workforce planning actions. • Performance measures.

Each service area presented their mid-year assessment to the People Scrutiny Committee and Place & Corporate Scrutiny Committee in November / December 2025. The feedback and recommendations from the committees is outlined in the Scrutiny Committee section of the report. These will be considered as part of the preparation of the End of Year / Annual Review of performance as well as supporting the development of service area plans for 2026/27.

The table below provides a summary of the assessment against the progress of Service Area objectives and their actions. Based upon the actions reported, eight objectives reported an ‘Amber’ status with the remaining objectives assessed as a ’Green’ at the end of Quarter 2.

Service Plan Objectives Mid-Year Assessment (Red / Amber / Green). Directorate Service Area See definition in Appendix 1 Objective 1 Objective 2 Objective 3 Objective 4 Objective 5 Environment & Public Protection Housing & Environment & Communities Sustainability Infrastructure Regeneration & Economic Development Adult Services Children Social Services Services Prevention & Inclusion Education Service

Transformation Finance & Corporate Law & Standards People, Policy & Transformation *Note – Grey boxes denote no objective.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mid-Year Reviews Service Area Plans 2025-26Plan 229 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
DB
Councillor Dimitri BatrouniChair, present
DD
Councillor Deb DaviesCommittee Member, present
MS
Councillor Mark SpencerCommittee Member, present
ES
Councillor Emma Stowell-CortenCommittee Member, present
LL
Councillor Laura LaceyCommittee Member, present
JH
Councillor Jason HughesCommittee Member, present
JC
Councillor James ClarkeCommittee Member, present
YF
Councillor Yvonne ForseyCommittee Member, present
SA
Councillor Saeed AdanCommittee Member, present
RH
Councillor Rhian HowellsCommittee Member, present

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies