That the Information Note on Planning Obligations Funding (Section 106 and Unilateral Undertakings) be noted. REASON FOR DECISION: To respond to a request made by the Committee. That the Information Note on Planning Obligations Funding (Section 106 and Unilateral Undertakings) be noted. REASON FOR DECISION: To respond to a request made by the Committee.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1Planning obligation funding is available for capital projects, as long as they meet the conditions of why the funding was provided. There may be a need to return funding that is not used within the terms of the funding within a specified period. The Council always seeks to avoid this.
1.2Where possible, the funding will be used to reduce the amount that the Council has to contribute towards projects from its own resources. Some projects may only come about as a result of the planning obligation income received. The Council must consider whether it has to contribute any capital funding and any ongoing revenue costs that may result before going ahead with these.
1.3The time period for spending planning obligation funding is usually quite long i.e. 10 years for section 106 agreements and unrestricted for unilateral undertakings. This means that the balances held are quite high, but these are kept under regular review to ensure optimal usage and avoid having to pay back amounts to developers
2. STEPS TO DATE
2.1Annual reports are provided to Area Committees on the planning obligation totals for their area. This information note provides a general overview of the balances held.
3. INFORMATION TO NOTE
3.1The Council introduced a Planning Obligations supplementary planning document (SPD) in 2006 giving a formula for developers to use to calculate what their planning contribution costs might be. Planning obligation payments should reflect the additional demand placed on infrastructure, services and public facilities by new development. For simpler developments the planning contribution may be through a unilateral undertaking. For more complex developments there will need to be an agreement between the developer and the Council, i.e. a section 106 agreement.
3.2Planning obligation payments are for facilities and infrastructure and therefore can only be used for capital expenditure. The agreement in relation to the planning obligation is likely to stipulate what the funding will be used for and also set a time period for doing so. Unilateral undertakings do not have a time period for when they need to be used. Where the funding is not used in accordance with the agreed purpose then it may have to be returned to the developer. FAR COMMITTEE (12.6.17) 3.3 The Community Infrastructure levy (CIL) regulations came into force in April 2010. It is unlikely that the Council will adopt a Community Infrastructure Charging Schedule until after 2018 following the adoption of a Local Plan.
3.4Developer Contributions can be a source of funding for the Council’s capital programme. Wherever possible the contributions will be used towards existing planned projects to reduce the amount that has to be funded from other Council resources (e.g. set-aside and capital receipts). For some balances specific projects may be identified to make use of the available funding. There should always be a consideration of whether the Council has to provide additional capital funding and the ongoing revenue costs that arise from any new facilities or infrastructure.
3.5Contributions that the Council is holding (i.e. received but not yet spent) are invested in the same way as any cash balances that the Council holds. The interest from these balances supports General Fund expenditure.
3.6Table 1 below shows a summary of the planning obligation balances by year and by type:
Table 1, Planning Obligation amounts by year and by type (£000)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.