RECOMMENDED TO CABINET: (1) That the reduction in the score for the “Increased Homelessness and use of B & B” risk from a 7 to a 5 be approved; (2) That the reduction in the score for the “Office Accommodation” risk from a 7 to a 5 be approved; (3) That a reduction in the likelihood score for the “Sale of Materials” sub-risk to a 2 – Medium – be approved; and (4) That the Annual Report on Risk and Opportunities Management 2016/17, as set out at Appendix B to the report, be supported and referred to Council for approval. REASON FOR DECISION: To comply with the Risk and Opportunities Management Strategy, which stipulates that an Annual Risk Management report is taken to Council.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1To provide the Committee with an update on the management of the Corporate risks
Recommendations
2.1That the Committee notes and refers the changes in the Corporate risks to Cabinet.
2.2That the Annual Report on Risk Management 2016/17 (attached at Appendix B) is referred to Cabinet for onward referral to Council.
Reasons for recommendations
3.1The responsibility for ensuring the management of the risks referred to in Section 2 of this report is that of Cabinet.
3.2This Committee has responsibility to monitor the effective development and operation of risk management.
Alternative options considered
4.1There are no alternative options that are applicable
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation has been undertaken with SMT and the Risk Management Group (this includes Councillor T Hone as Risk Management Member ’champion’) and these recommendations were supported. Lead Officers discuss these risks with the relevant Executive Member.
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan. FAR COMMITTEE (12.6.17) 7. BACKGROUND
7.1At the March meeting of the Finance, Audit and Risk Committee the increase in the likelihood of the “Shared Procurement Opportunity” sub-risk that falls under the umbrella of the overarching “Waste & Street Cleansing Contract Renewal” risk and the addition of “Cyber Risks” as a new Corporate risk were approved and referred on to Cabinet.
8. RELEVANT CONSIDERATIONS
8.1The Risks summarised in Table 1 have been reviewed and agreed by SMT. Members are able to view the current risk descriptions on Covalent, the Council’s performance and risk management software. The changes to the assessment of the current Corporate risks & opportunities are outlined in sections 8.2, 8.3 and 8.4.
4 7 9 Income Generation Local Plan Projects Managing the Council’s Sustainable Finances 3 Development (2 x Sub North Hertfordshire High Risks) Museum and Hitchin Town Hall Project
2 5 8 Increased Cyber Risks Homelessness and Use of Waste and Street Likelihood
B&B (Reduced from 7) Cleansing Contract 2 Office Accommodation Renewal (8 x Sub Risks) Medium (Reduced from 7) Workforce Planning
1 3 6
1 Low
1 2 3 Low Medium High
Impact
FAR COMMITTEE (12.6.17) 8.2 Increased homelessness and use of B&B In March 2017, officers reviewed this risk again and reduced the likelihood risk score to “Medium” (2). Use of B&B accommodation has consistently reduced over the last year and at the time of the review, there were no homeless households being accommodated in B&B. The current level of homelessness within the district is being managed using available temporary accommodation units. However, officers noted that this is a challenging issue and that demand can be unpredictable. Therefore, the risk will be subject to quarterly reviews. This proposed change will move the Homelessness risk from a 7 to a 5 on the Matrix
8.3Office Accommodation Willmott Dixon commenced work on site on 6 March 2017.They are currently undertaking asbestos removal and demolition works and are on schedule. Some unforeseen issues have been identified during the works and these are being assessed. Any solutions required will be financed from existing budgets. In view of the progress made and the Council's commitment to complete the refurbishment, Officers have reduced the Likelihood risk score to "2- Medium. This proposed change will move the Office Accommodation risk from a 7 to a 5 on the Matrix.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.