CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Cabinet, Tuesday 26 September 2017 at 7.30pm

FIRST QUARTER REVENUE MONITORING 2017/18

Noted Executive 1 paper

Cabinet noted this item on Tuesday 26 September 2017. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

(1) That the report be noted; (2) That the changes to the 2017/18 General Fund Budget, as identified in Table 2 and Paragraph 8.2 of the report, and involving an increase in net expenditure of £208,000, be approved; and (3) That the changes to the 2018/19 General Fund Budget, as identified in Table 2 and Paragraph 8.2 of the report, and involving an increase in net expenditure of £158,000, be noted, and that these be incorporated into the draft Revenue Budget for 2018/19. REASON FOR DECISION: To monitor and request appropriate action of Directorates who do not meet the budget targets set as part of the Corporate Business Planning process; and to ensure that changes to the Council’s balances are monitored and approved. (1) That the report be noted; (2) That the changes to the 2017/18 General Fund Budget, as identified in Table 2 and Paragraph 8.2 of the report, and involving an increase in net expenditure of £208,000, be approved; and (3) That the changes to the 2018/19 General Fund Budget, as identified in Table 2 and Paragraph 8.2 of the report, and involving an increase in net expenditure of £158,000, be noted, and that these be incorporated into the draft Revenue Budget for 2018/19. REASON FOR DECISION: To monitor and request appropriate action of Directorates who do not meet the budget targets set as part of the Corporate Business Planning process; and to ensure that changes to the Council’s balances are monitored and approved.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The purpose of this report is to inform Cabinet of the summary position on revenue income and expenditure forecasts for 2017/18, as at the end of the first quarter (30 June 2017). The forecast variance is an increase of £208k on the net working budget of £17.022m for 2017/18, with an ongoing impact in future years of £158k. There are a number of significant variances within these totals, which are detailed and explained in table 2. The report also provides an update on;

- the progress with the planned delivery of efficiencies (paragraph 8.3) - the use of budget approved to be carried forward from 2016/17 (paragraph 8.4) - performance against the four key corporate ‘financial health’ indicators (para 8.5) - the overall forecast funding position for the Council and factors that may affect this (paras 8.6 – 8.13)

Recommendations

2.1That Cabinet note this report.

2.2That Cabinet approves the changes to the 2017/18 General Fund budget, as identified in table 2 and paragraph 8.2, a £208k increase in net expenditure.

2.3That Cabinet notes the changes to the 2018/19 General Fund budget, as identified in table 2 and paragraph 8.2, a £158k increase in net expenditure. These will be incorporated in to the draft revenue budget for 2018/19.

Reasons for recommendations

3.1Members are able to monitor and request appropriate action of Services who do not meet the budget targets set as part of the Corporate Business Planning process.

3.2Changes to the Council’s balances are monitored and approved.

CABINET (26.9.17) 4. ALTERNATIVE OPTIONS CONSIDERED

4.1Budget holders have considered the options to manage within the existing budget but consider the variances reported here necessary and appropriate.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the budget monitoring is not required. Members will be aware that there is wider consultation on budget estimates during the corporate business planning process each year.

6. FORWARD PLAN

6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 27th June 2017.

Background

7.1Council approved the revenue budget in February 2017 of £16.545 million. As at quarter 1 the working budget has increased to £17.022 million. Table 1 below details the approved changes to this budget to get to the current working budget:

Table 1 - Current Working Budget

£k Original approved budget for 2017/18 16,545 Proposed Crematorium at Wilbury Hills Cemetery - Interim Report On 50 Business Case – approved by Cabinet 28th March 2017 Quarter 3 2016/17 Revenue Monitoring report - 2017/18 budget 199 changes approved by Cabinet (March 2017) 2016/17 Revenue Outturn Report - 2017/18 budget changes approved 228 by Cabinet (June 2017) Current Working Budget 17,022

8. RELEVANT CONSIDERATIONS

REVENUE INCOME AND EXPENDITURE FORECASTS

8.1Service Managers are responsible for monitoring their expenditure and income against their working budget. Table 2 below highlights those areas where there are forecast to be differences. An explanation is provided for each of the most significant variances, which are generally more than £25k. The final column details if there is expected to be an impact on next year’s (2018/19) budget:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FIRST QUARTER REVENUE MONITORING 2017/18Report 401 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. FIRST QUARTER REVENUE MONITORING 2017/18This decision
  2. First quarter revenue budget monitoring 2026/27Noted
  3. First quarter capital budget monitoring review 2026/27Noted
  4. First quarter treasury management review 2026/27Noted
  5. First quarter revenue budget monitoring 2026/27Approved
  6. First quarter capital budget monitoring review 2026/27Approved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies