(1) That the forecast expenditure of £15.139million in 2017/18 on the Capital programme, as set out in Paragraph 8.2 of the report, be noted, and the changes detailed in Table 3 of the report, which resulted in a net decrease of the working estimate of £0.217million, be approved; (2) That the changes to the Capital Programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in Table 2 of the report, increasing the estimated spend in 2018/19 by £5.234million (re-profiled from 2017/18), be noted, and that these be incorporated into the draft Capital Programme for 2018/19 onwards; and (3) That the position of the availability of capital resources, as detailed in Table 4 of the report, and the requirement to keep the Capital Programme under review for affordability, be noted. REASON FOR DECISION: To approve revisions to the Capital Programme, and to ensure that the Capital Programme is fully funded. (1) That the forecast expenditure of £15.139million in 2017/18 on the Capital programme, as set out in Paragraph 8.2 of the report, be noted, and the changes detailed in Table 3 of the report, which resulted in a net decrease of the working estimate of £0.217million, be approved; (2) That the changes to the Capital Programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in Table 2 of the report, increasing the estimated spend in 2018/19 by £5.234million (re-profiled from 2017/18), be noted, and that these be incorporated into the draft Capital Programme for 2018/19 onwards; and (3) That the position of the availability of capital resources, as detailed in Table 4 of the report, and the requirement to keep the Capital Programme under review for affordability, be noted. REASON FOR DECISION: To approve revisions to the Capital Programme, and to ensure that the Capital Programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1To update Cabinet on progress with delivering the capital programme for 2017/18, as at the end of June 2017, indicating its impact upon the approved capital programme for 2018/19 - 2020/21. The current estimate is a decrease in spend in 2017/18 from that reported in the Capital Programme Outturn report for 2016/17 of £5.451million, and an increase in spend in future years of £5.234 million. The most significant individual change is that the Council was not granted permission from DCLG to make a Capitalised Pension Fund Contribution.
Recommendations
2.1That Cabinet notes the forecast expenditure of £15.139million in 2017/18 on the capital programme, paragraph 8.2 refers, and approves the changes detailed in table 3 which resulted in a net decrease on the working estimate of £0.217million.
2.2That Cabinet notes the changes to the capital programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2018/19 by £5.234million (re-profiled from 2017/18). These will be incorporated in to the draft capital programme for 2018/19 onwards.
2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4, and the requirement to keep the capital programme under review for affordability.
Reasons for recommendations
3.1Cabinet is required to approve revisions to the capital programme.
3.2Cabinet is required to ensure that the capital programme is fully funded.
Alternative options considered
4.1Options for capital investment are considered as part of the Corporate Business Planning process.
CABINET (26.9.17) 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.
6. FORWARD PLAN
6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 27th June 2017.
Background
7.1In February 2017, Council approved the capital programme for 2017/18 to 2020/21. This was subsequently amended by reprogramming from 2016/17.
7.2The Medium Term Financial Strategy for 2017 to 2022 confirmed that the Council will seek opportunities to utilise capital funding (including set aside receipts) for invest to save schemes and proposals that generate higher rates of return than standard treasury investments. This is one way the Council will allocate resources to support organisational transformation that will reduce revenue expenditure.
8. RELEVANT CONSIDERATIONS
Capital Programme 2017/18
8.1Summaries of the capital programme by Council priority and service are shown in appendix A together with the overall funding analysis and projected availability of capital funding balances (set aside and capital receipts). The full programme is detailed in Appendix B and shows the revised costs to date, together with the expected spend from 2017/18 to 2020/21 and the funding source for each capital scheme.
8.2Capital expenditure for 2017/18 is estimated to be £15.139million. This is a reduction of £5.451million on that forecast in the 2016/17 Capital Programme Outturn report (reported to Cabinet on 13th June 2017). The decrease in spend in 2017/18 is largely due to re-profiling spend into future years. Table 1 below details changes to capital programme.
Table 1- Current Capital Estimates 2017/18 2018/19 2019/20 to £M £M 2020/21 £M Original Estimates approved by 8.465 4.788 3.197 Full Council February 2017 Changes approved by Cabinet in 12.125 -0.365 0.025 2016/17 Capital Outturn report Revised Capital estimates at start 20.590 4.423 3.222 of 2017/18 Changes detailed in this report -5.451 5.234 0
Current Capital Estimates at Q1 15.139 9.657 3.222
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.