THIRD QUARTER CAPITAL MONITORING 2017/18

Noted Finance 3 papers

Finance, Audit and Risk Committee noted this item on Wednesday 21 March 2018. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

That the Third Quarter Capital Monitoring report for 2017/18 be noted. REASON FOR DECISION: To provide an opportunity for the Committee to comment as appropriate on the Third Quarter Capital Programme Monitoring report for 2017/18. That the Third Quarter Capital Monitoring report for 2017/18 be noted. REASON FOR DECISION: To provide an opportunity for the Committee to comment as appropriate on the Third Quarter Capital Programme Monitoring report for 2017/18.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Finance, Audit and Risk Committee

Executive summary

1.1To update Cabinet on progress with delivering the capital programme for 2017/18, as at the end of December 2017, and indicating its impact upon the approved capital programme for 2018/19 - 2021/22. The current estimate is a decrease in spend in 2017/18 of £4.167million from that reported when the Capital Programme for 2018/19- 2021/22 was approved by Council in February 2018, and an increase in spend in future years of £4.139 million. The most significant individual changes are the inclusion of the purchase of kitchen caddies to support the new weekly collection of food waste service from May 2018 and the re-profiling of the capital expenditure allocations for new waste vehicles and housing investment into 2018/19.

Recommendations

2.1That Cabinet notes the forecast expenditure of £10.903million in 2017/18 on the capital programme, paragraph 8.2 refers, and approves the changes detailed in table 3 which resulted in a net decrease on the working estimate of £0.028million.

2.2That Cabinet approves the changes to the capital programme for 2018/19 onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2018/19 by £4.139million (re-profiled from 2017/18).

2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4, and the requirement to keep the capital programme under review for affordability.

Reasons for recommendations

3.1Cabinet is required to approve revisions to the capital programme.

3.2Cabinet is required to ensure that the capital programme is fully funded.

FAR COMMITTEE (21.3.18) 4. ALTERNATIVE OPTIONS CONSIDERED

4.1Options for capital investment are considered as part of the Corporate Business Planning process.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.

6. FORWARD PLAN

6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 2nd February 2018.

Background

7.1In February 2017, Council approved the capital programme for 2017/18 to 2020/21. This was subsequently amended by reprogramming from 2016/17 and re-profiling at the first quarter and second quarter.

7.2The Medium Term Financial Strategy for 2017 to 2022 confirmed that the Council will seek opportunities to utilise capital funding (including set aside receipts) for invest to save schemes and proposals that generate higher rates of return than standard treasury investments. This is one way the Council will allocate resources to support organisational transformation that will reduce revenue expenditure.

8. RELEVANT CONSIDERATIONS

Capital Programme 2017/18

8.1Summaries of the capital programme by Council priority and service are shown in appendix A together with the overall funding analysis and projected availability of capital funding balances (set aside and capital receipts). The full programme is detailed in Appendix B and shows the revised costs to date, together with the expected spend from 2017/18 to 2021/22 and the funding source for each capital scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Summary 2017/18 onwardsAppendix A 187 KB Download
PDF
Capital Programme Detail including Funding 2017/18 onwardsAppendix B 595 KB Download
PDF
THIRD QUARTER CAPITAL MONITORING 2017/18Report 274 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. THIRD QUARTER CAPITAL MONITORING 2017/18This decision
  2. Third quarter treasury management review 2025/26Noted
  3. Third quarter capital budget monitoring review 2025/26Noted
  4. Third quarter revenue budget monitoring 2025/26Noted
  5. Third quarter revenue budget monitoring 2025/26Approved
  6. Third quarter capital budget monitoring review 2025/26Approved

More from North Hertfordshire Finance, Audit and Risk Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Apologies for absenceThat Councillor Stewart Willoughby be elected as Chair for this meeting of the Finance, Audit and Risk Committee. Apo... Decided Open
9 Sep 2026 Minutes - 10 june 2026That the Minutes of the Meeting of the Committee held on 10 June 2026, as amended, be approved as a true record of th... Approved Open
9 Sep 2026 Notification of other businessThere was no other business notified. Decided Open
9 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
9 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open