THIRD QUARTER CAPITAL BUDGET MONITORING REVIEW 2025/26
NotedExecutive2 papers
AI summaryNorth Hertfordshire Cabinet notes £23.350M capital spend forecast for 2025/26 and approves £3.011M of scheme rephasing into 2026/27, including switching the Priory Gardens Bandstand project from renovation to rebuild.
Written from the decision and the officer reportPDF Pro
OutcomeNotedForecast spend and budget revisions approved
Money£23.350M forecast 2025/26Plus £3.011M added to 2026/27
What happens nextCapital programme kept under reviewDue to limited capital resources
Who it affectsCouncil capital programmeMany schemes rephased into 2026/27
What was decided
Cabinet noted forecast capital expenditure of £23.350M in 2025/26, a decrease of £3.066M on the Q2 forecast. Report 2.1
Cabinet approved rephasing £3.011M of capital spend from 2025/26 into 2026/27 and later years. Report 2.2, 8.4
Cabinet approved changing the Priory Gardens Bandstand project from renovation to rebuild, with an extra £0.025M added to the 2026/27 budget. Report 2.3, 8.4
Why
Cabinet must approve adjustments to the capital programme and ensure it remains fully funded. Report 3.1, 9.1, 9.3
Many schemes have slipped because of procurement changes, design work, recruitment gaps or external decisions, including the Public Sector Decarbonisation Fund Phase 2 and Oughtonhead Common Weir. Report 8.4
The Council's Capital Financing Requirement has turned positive, meaning it will need to borrow and charge a minimum revenue provision to the General Fund from 2026/27. Report 8.8
What happens next
Officers will continue to seek third-party grants and S106 contributions to reduce pressure on capital receipts. Report 8.7
The capital programme will remain under close review for affordability, with possible further borrowing considered for 2026/27 onwards. Report 8.8
Individual projects worth £50k or more, or affecting more than two wards, will have an equality analysis carried out before they proceed. Report 12.2
The money
£23.350M Forecast capital expenditure in 2025/26 Report 2.1
£3.066M Decrease in 2025/26 spend versus the Q2 forecast Report 1.2
£3.011M Increase in estimated spend added to 2026/27 Report 2.2, 1.2
£0.025M Extra 2026/27 budget for Priory Gardens Bandstand rebuild Report 2.3
£0.732M Rephased from Public Sector Decarbonisation Fund Phase 2 Report 1.2, 8.4
£0.315M Rephased from Oughtonhead Common Weir Report 1.2, 8.4
£0.229M Underspend on Fibre Waste Bins Report 1.2, P23
£0.160M Increase in S106 funded project spend in 2025/26 Report 1.2, P22
£127.0M Value of capital assets owned by the Council Report 8.1
£4.6M Potential total cost overrun over the ten-year programme against a budgeted £59.298M
Options considered
Chosen: Approve rephasing of £3.011M into 2026/27. Reflects revised scheme timetables identified in Q3 monitoring Report 2.2, 8.4
Chosen: Switch Priory Gardens Bandstand from renovation to rebuild with £0.025M extra. The bandstand needs replacing rather than renovating Report 2.3, 8.4
Rejected: Reject the adjustments and keep the original budget profile Report 2.2, 2.3
Implications
Financial: The Capital Financing Requirement has moved from negative £0.59M to positive, so the Council will need to borrow and will charge a minimum revenue provision to the General Fund from 2026/27. Report 8.8
Financial: Using capital receipts reduces investment income; £1.0M of capital currently earns around £40k a year in interest.
Financial: Over the ten-year programme, total spend could be around £4.6M higher than the budgeted £59.298M once the Council's tolerance limits are applied.
Legal: Cabinet has authority under its terms of reference to monitor and adjust capital expenditure, but significant additions to budget must be approved by Full Council. Report 9.1, 9.2
Legal: The Council has a duty under Section 151 of the Local Government Act 1972 and Section 28 of the Local Government Act 2003 to maintain a balanced budget and review it periodically. Report 9.3, 9.4
Risk: Project-level risks are managed by individual project managers and reported through the Council's risk management software. Report 11.2
Equalities: No direct equalities implications arise from the report; equality analysis will follow for any new investment of £50k or more, or affecting more than two wards. Report 12.2
Other: No direct environmental, social value or human resource implications from the report itself, though some rephased schemes may have environmental impacts to assess later. Report 13.1, 14.1, 15.1
Who and where
North Hertfordshire District Council as landowner and asset owner of £127.0M of capital assets Report 8.1
Council tax payers and the General Fund, which will bear a minimum revenue provision charge from 2026/27 Report 8.8
Users of rephased schemes, including the Public Sector Decarbonisation Fund Phase 2, Oughtonhead Common Weir, cycle and transport projects, and the Priory Gardens Bandstand Report 8.4
Community groups receiving S106 and Shared Prosperity Fund grants Report P22
Timeline
20th January 2025: Q2 capital report considered by Cabinet
February 2025: Full Council approved the Integrated Capital and Treasury Strategy for 2025/26 to 2034/35 Report 7.1
End of December 2025: Cut-off date for the Q3 monitoring position Report 1.1
19th December 2025: Key Executive decision first notified in the Forward Plan Report 6.1
26th February 2026: Full Council approved changes including the Investment Strategy 2026-36 Report P16
2026/27: Rephased schemes including Public Sector Decarbonisation Phase 2, Oughtonhead Common Weir, transport and green infrastructure projects scheduled to be delivered Report 8.4
From 2026/27: Minimum revenue provision charge begins to be applied to the General Fund Report 8.8
Plain English for the jargon
Capital programme: The Council's planned spending on assets such as buildings, equipment and infrastructure
Capital Financing Requirement (CFR): A measure of the Council's outstanding capital borrowing and financing liabilities
Minimum Revenue Provision (MRP): The amount the Council must set aside each year from revenue to repay capital debt
S106: Section 106 planning obligations, where developers contribute funds for local infrastructure or community use
Rephasing / reprofiling: Moving planned spending from one financial year to a later one
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46
Resolved
That Cabinet: (1) Noted the forecast expenditure of £23.350M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) Approved the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend by £3.011M. (3) Approved a change of scope to the Priory Gardens Bandstand project from renovation to rebuild and an increase of the budget in 2026/27 by £0.025M. (4) Noted the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. REASON FOR DECISIONS: Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded. That Cabinet: (1) Noted the forecast expenditure of £23.350M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) Approved the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend by £3.011M. (3) Approved a change of scope to the Priory Gardens Bandstand project from renovation to rebuild and an increase of the budget in 2026/27 by £0.025M. (4) Noted the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. REASON FOR DECISIONS: Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1To update Cabinet on progress with delivering the capital programme for 2025/26, as at the end of December 2025.
1.2To update Cabinet on the impact upon the approved capital programme for 2025/26 – 2035/36. The current estimate is a decrease in spend in 2025/26 of £3.066M and an increase in spend in 2026/27 £3.011M. The most significant individual changes to the forecast spend in 2025/26 for reprofiling into 2026/27: £0.732M Public Sector Decarbonisation Fund Phase 2, £0.315M Oughtonhead Common Weir, £0.278M Cycle Strategy Implementation, £0.250M Transport Plans Implementation, £0.185M Green Infrastructure Implementation, £0.155M Museum and Commercial Storage, £0.146M Parking Machines Replacement. The most significant underspend in 2025/26 is £0.229M Fibre Waste Bins, while there is an increase in forecast expenditure in 2025/26 of £0.160M for S106 funded projects.
Recommendations
2.1That Cabinet notes the forecast expenditure of £23.350M in 2025/26 on the capital programme, paragraph 8.3 refers.
2.2That Cabinet approves the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend by £3.011M.
2.3That Cabinet approves a change of scope to the Priory Gardens Bandstand project from renovation to rebuild and an increase of the budget in 2026/27 by £0.025M.
2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. 3. REASONS FOR RECOMMENDATIONS
3.1Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
Alternative options considered
4.1Options for capital investment are considered as part of the Corporate Business Planning process.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.
6. FORWARD PLAN
6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 19th December 2025.
Background
7.1In February 2025, Council approved the Integrated Capital and Treasury Strategy for 2025/26 to 2034/35. The reports for Capital and Treasury have been split for the quarterly monitoring updates.
8. RELEVANT CONSIDERATIONS
8.1The Council has £127.0M of capital assets that it currently owns. The Investment Strategy set out the reasons for owning assets that are not for service delivery, including an assessment of Security, Liquidity, Yield and Fair Value. There have been no significant changes in relation to these since the last quarter. Capital Programme 2025/26 8.2 The full capital programme is detailed in Appendix A and shows the revised costs to date, together with the expected spend from 2025/26 to 2035/36 and the funding source for each capital scheme. 8.3 Capital expenditure for 2025/26 is estimated to be £23.350M. This is a decrease of £3.066M on the forecast in the 2nd quarter report (reported to Cabinet on 20th January 2025). Table 1 below details changes to capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.