(1) That the forecast expenditure of £15.857million in 2018/19 on the capital programme be noted and the adjustments detailed in table 3 which resulted in a net decrease on the working estimate of £0.958million be approved; (2) That the adjustments to the capital programme for 2018/19 onwards as a result of the revised timetable of schemes detailed in table 2, decreasing the estimated spend in future years 2019/20 by £1.340million be approved; (3) That the position of the availability of capital resources, as detailed in table 4, and the requirement to keep the capital programme under review for affordability be noted. REASONS FOR DECISIONS: (1) Cabinet is required to approve revisions to the capital programme; (2) Cabinet is required to ensure that the capital programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1To update Cabinet on progress with delivering the capital programme for 2018/19, as at the end of June 2018, and indicating its impact upon the approved capital programme for 2019/20 - 2021/22. The current estimate is a decrease in spend in 2018/19 of £2.298million from that reported in the Capital Programme Outturn report for 2017/18, and a decrease in spend in future years of £1.340 million. The most significant individual changes are the withdrawal of the Royston Leisure Centre project in 2018/19 and the removal of Disabled Facilities Grants which are now administered by Hertfordshire County Council.
Recommendations
2.1That Cabinet notes the forecast expenditure of £15.857million in 2018/19 on the capital programme, paragraph 8.2 refers, and approves the adjustments detailed in table 3 which resulted in a net decrease on the working estimate of £0.958million.
2.2That Cabinet approves the adjustments to the capital programme for 2018/19 onwards as a result of the revised timetable of schemes detailed in table 2, decreasing the estimated spend in future years 2019/20 by £1.340million.
2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4, and the requirement to keep the capital programme under review for affordability.
Reasons for recommendations
3.1Cabinet is required to approve revisions to the capital programme.
3.2Cabinet is required to ensure that the capital programme is fully funded. 4. ALTERNATIVE OPTIONS CONSIDERED
4.1Options for capital investment are considered as part of the Corporate Business Planning process.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.
6. FORWARD PLAN
6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 5th June 2018.
Background
7.1In February 2018, Council approved the capital programme for 2018/19 to 2021/22. This was subsequently amended by reprogramming from 2017/18.
7.2The Medium Term Financial Strategy for 2018 to 2023 confirmed that the Council will seek opportunities to utilise capital funding (including set aside receipts) for invest to save schemes and proposals that generate higher rates of return than standard treasury investments. This is one way the Council will allocate resources to support organisational transformation that will reduce revenue expenditure.
8. RELEVANT CONSIDERATIONS
Capital Programme 2018/19
8.1Summaries of the capital programme by Council priority and service are shown in appendix A together with the overall funding analysis and projected availability of capital funding balances (set aside and capital receipts). The full programme is detailed in Appendix B and shows the revised costs to date, together with the expected spend from 2018/19 to 2021/2 and the funding source for each capital scheme.
8.2Capital expenditure for 2018/19 is estimated to be £15.857million. This is a reduction of £2.298million on that forecast in the 2017/18 Capital Programme Outturn report (reported to Cabinet on 19th June 2018). The decrease in spend in 2018/19 is largely due to the withdrawal of the Royston Leisure Centre project and re-profiling of spend into future years. Table 1 below details changes to capital programme. Table 1- Current Capital Estimates 2018/19 2019/20 2020/21 to £M £M 2021/22 £M Original Estimates approved by 12.511 1.828 2.737 Full Council February 2018 Changes approved by Cabinet in 5.644 0 0 2017/18 Capital Outturn report Revised Capital estimates at start 18.155 1.828 2.737 of 2017/18 Changes at Q1 detailed in this -2.298 0.150 -1.490 report Current Capital Estimates 15.857 1.978 1.247
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.