QUARTERLY UPDATE ON THE COUNCIL DELIVERY PLAN

Decided Scrutiny 2 papers

Overview and Scrutiny Committee decided this item on Tuesday 6 December 2022. Below is the council's own wording, with the papers it was decided on.

Item166

Resolved

(1) That Overview and Scrutiny Committee commented on the Council Delivery Plan Quarter 2 monitoring report. (2) That Overview and Scrutiny Committee determined any project that they want to receive more detail on as part of the next monitoring report. RECOMMENDED TO CABINET: (1) That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. (2) That Cabinet notes the completion of the Local Plan milestones for this year. REASONS FOR DECISIONS AND REFERALS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 4 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 22-23 at the end of Quarter 2, which includes:

• Progress against the completion of Council projects and milestones • Requests to change milestone dates • Commentary on progress made and any new issues, risks, or opportunities

Recommendations

2.1That Overview and Scrutiny Committee comment on the Council Delivery Plan Quarter 2 monitoring report, including the recommendations made to Cabinet i.e.:

• That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. • That Cabinet notes the completion of the Local Plan milestones for this year.

2.2That Overview and Scrutiny Committee determine any project that they want to receive more detail on as part of the next monitoring report.

Reasons for recommendations

3.1The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities.

4. ALTERNATIVE OPTIONS CONSIDERED 4.1. In developing the CDP it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Service Directors and Service Managers have provided updates on progress and will have made Executive Members (and Deputies) aware of progress made.

5.2A draft of the Quarter 2 update was provided to Risk Management Group (RMG) in November. The Group has a standing invite to the Executive Member for Finance and IT (has responsibility for performance monitoring), the Deputy Executive Member for Finance and IT, the Chair of Overview and Scrutiny (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they are able to. RMG were asked to comment on the content and format of the CDP Q1 update.

5.3The CDP is reviewed by Overview and Scrutiny Committee and they are asked to provide comments and recommendations to Cabinet.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision first notified on the Forward Plan on the 7 June 2022.

Background

7.1The CDP brings together projects, risks and performance indicators together in one document. It was adopted by Cabinet in March 2022, which included the projects to be included within the CDP.

8. RELEVANT CONSIDERATIONS

8.1Appendix A provides an update on the progress made in delivering the Council Delivery Plan. Whilst it is labelled as a Quarter 2 update, it generally reflects the latest position at the time that the report was written (mid-November).

8.2Cabinet are asked to approve the following:

• The proposed change to current milestone dates for Town Centre Recovery, Resident/ Public EV charging in our car parks, Cycling Networks, Town Centre Strategies, Finalise Pay on Exit Parking Review, and Replacement of Royston Town Hall Annexe with reasons detailed in Appendix A.

• The progress made to date against each project and resulting impacts on future milestones, as detailed in the commentary against each project in Appendix A. Future updates will provide monitoring against any revised milestones. 8.3 The intention is that the CDP reports provide an overview, as providing all the details on project milestones would lead to a report that was too long. Requests can be made (especially by O&S) to look at individual projects in more detail. Any such request would be incorporated in to the next monitoring report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CDP 16.11.22.pdfAppendix A 22 pages Download
PDF
QUARTERLY UPDATE ON THE COUNCIL DELIVERY PLANReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. QUARTERLY UPDATE ON THE COUNCIL DELIVERY PLANThis decision
  2. Quarterly update on the council delivery planNoted

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies