That the Committee noted the report. REASON FOR DECISION: The report is following the request of the committee for an update on the progress of the Commercial Directorate work programme and is for information only. That the Committee noted the report. REASON FOR DECISION: The report is following the request of the committee for an update on the progress of the Commercial Directorate work programme and is for information only.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Report to Overview and Scrutiny Committee, 2 pages
Appendix A
Appendix A - Service Action Plan
Enterprise Please note - updates are shown in italics.
Action Corporate Objective Target/Aim/Outcome Planned Start Date Due Date Current Progress
2022/23 Museum and Town Hall In the two financial years prior to the pandemic, the town hall generated £54k in 2018/19 and £69k in 2019/20 in hall and room lettings. HTH remains on course to exceed these income levels by the end of 2021/22, which would signify an extremely strong recovery from the pandemic and further evidence of the business growing. Fitness class income continues to perform strongly, also ahead of 2018/19 and 2020/21. Bar takings have For the level of hires of Hitchin Town Hall, and the level of recovered ground on the income target as the year has progressed and income to have recovered to the point of parity with pre looking at the events to come, this income stream is expected to finish the Covid Recovery Hitchin Town Hall Brighter future together Ongoing pandemic levels (assumes the current pandemic situation year strongly with a particularly healthy Christmas period . Cafe and continues to improve). catering income, linked to lower visitor figures, and staffing shortages linked with the transition to incorporate the Bancroft site, continues to lag behind target. Overall, income remains approximately 15% behind target, however we know there are a number of highly profitable events which have occured very recently which are yet to filter through into the accounts. Officers continue to witness a stronger than expected recovery at the venue from the Covid pandemic, which is encouraging.
Prior to the pandemic, the museum was on course to attract over 35,000 visitors in its first full year of operation. This equates to roughly 3000 visitors per month which fluctuates with seasonal variation and which exhibitions are on. By the mid way point of 2022, the museum had For the level of visitors to North Herts Museum to have welcomed 15461 general visitors, excluding schools and out of hours Covid Recovery North Herts recovered to a point of parity with pre pandemic levels. groups. This signifies a continuing trend towards matching pre pandemic Brighter future together Ongoing 01/03/23 Museum (Assumes the current pandemic situation continues to visitor numbers. Gift Shop performance and margins continue to track improve). alongside targets and the current exhibition has resulted in a number of favourable commission based sales of artwork, all of which is welcomed against slightly lower visitor numbers for the year to date. Officers feel the recovery continues to be stronger than expected from the pandemic, though there is still ground to recover. The Council have appointed a new Procurement Officer in the summer, who has been able to add valuable input to this project. Based on advice received, officers were strongly encouraged to revisit the framework approach and are now finalising details for the adoption of the SCAPE framework to guide the project and source a principal contractor. We Procurement of the necessary developers and consultants to envisage now moving forward with awarding this contract in early 2023. be undertaken and completed. North Herts Museum collection 01/03/2023 Whilst the beginning of construction is now thought to be more likely in Burymead Redevelopment Brighter future together to have been successfully temporarily relocated and for 01/09/22 Revised to Summer 2023 rather than Spring 2023, officers now have much more construction work to be underway at the Burymead site on the 01/06/2023 confidence in the direction of travel with this project and that risks have new museum storage facility. been minimised and value for money maximised through the current approach. As mentioned in a previous update, the museum collection will need to be relocated by this point and we have had initial discussions and outline quotations for transportation and storage options during the construction period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.