That Cabinet (1) Agreed that the Council will stop providing the monthly property compliance tasks (as detailed in paragraph 8.1) to community groups/ buildings (as detailed in paragraph 8.3). (2) Agreed that the Council should continue to fund low value repairs in such a way so that community groups/ buildings do not lose out from changes to the way that the compliance contract is expected to operate from February 2023. REASON FOR DECISIONS: The decision helps the Council keep under control the cost of providing property compliance contract. It also leads to reduced vehicle travel and associated environmental benefits. It also reflects that the Council will focus its support (and resources) on providing those property compliance services that require specialist knowledge and training. That Cabinet (1) Agreed that the Council will stop providing the monthly property compliance tasks (as detailed in paragraph 8.1) to community groups/ buildings (as detailed in paragraph 8.3). (2) Agreed that the Council should continue to fund low value repairs in such a way so that community groups/ buildings do not lose out from changes to the way that the compliance contract is expected to operate from February 2023. REASON FOR DECISIONS: The decision helps the Council keep under control the cost of providing property compliance contract. It also leads to reduced vehicle travel and associated environmental benefits. It also reflects that the Council will focus its support (and resources) on providing those property compliance services that require specialist knowledge and training.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
The Council leases a number of buildings to community groups. These are mainly buildings referred to as Community Centres, but also includes a bowls club, pavilion and a day centre (referred to as Community Buildings in this report). Under the lease the community group are required to take on various property checking and compliance tasks. However, the Council has continued to provide almost all of these tasks through a property compliance contract. Some of these tasks are carried out on a monthly basis and do not require any specialist knowledge or training to carry them out. This report recommends that the Council stops providing these specific elements of the compliance service, and therefore the community groups (either their staff or volunteers) would need to take them on. As well as helping to keep under control the cost of providing the service, it would also lead to reduced vehicle travel, and the associated environmental benefits. The Council would still continue to provide those tasks that require specialist knowledge or training.
Recommendations
2.1That Cabinet agrees that the Council will stop providing the monthly property compliance tasks (as detailed in paragraph 8.1) to community groups/ buildings (as detailed in paragraph 8.3).
2.2That Cabinet agrees that the Council should continue to fund low value repairs in such a way so that community groups/ buildings do not lose out from changes to the way that the compliance contract is expected to operate from February 2023.
Reasons for recommendations
3.1The decision helps the Council keep under control the cost of providing property compliance contract. It also leads to reduced vehicle travel and associated environmental benefits. It also reflects that the Council will focus its support (and resources) on providing those property compliance services that require specialist knowledge and training. 4. ALTERNATIVE OPTIONS CONSIDERED
4.1It would be possible to retain services as they are, but that would come with an additional financial and environmental cost.
4.2The Council could seek to withdraw all property compliance support. This is rejected due to the cost and complexity involved for each community group obtaining these services individually.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1The community groups have been consulted on these proposals. This started with an e- mail in July seeking any feedback or questions. This e-mail was copied to Local Ward Councillors. This has been followed up with responses to any questions raised and also clarification e-mails.
5.2Due to the timing some of the Area Committees (i.e. there was not a meeting in advance of this Cabinet meeting), feedback has been sought via e-mail to the Chair of the Area Committee. As Baldock and District do not have a Chair, the e-mail was sent to all Members of the Area Committee.
5.3The feedback from the community groups is detailed in section 8. At the time of writing the report, none of the Area Committees have provided a response. Some of the Ward Councillors have supported their Community Centres, but to date there have not been any specific separate responses from Ward Councillors.
6. FORWARD PLAN
6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 6th September 2022.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.