That Cabinet (1) Noted the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. (2) Noted the completion of the Local Plan milestones for this year. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities. That Cabinet (1) Noted the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. (2) Noted the completion of the Local Plan milestones for this year. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
This report presents progress on delivering the Council Delivery Plan for 22-23 at the end of Quarter 2, which includes:
• Progress against the completion of Council projects and milestones • Requests to change milestone dates • Commentary on progress made and any new issues, risks, or opportunities
Recommendations
2.1That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. 2.2. That Cabinet notes the completion of the Local Plan milestones for this year.
Reasons for recommendations
3.1The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities.
Alternative options considered
4.1In developing the CDP it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS 5.1. Service Directors and Service Managers have provided updates on progress and will have made Executive Members (and Deputies) aware of progress made.
5.2A draft of the Quarter 2 update was provided to Risk Management Group (RMG) in November. The Group has a standing invite to the Executive Member for Finance and IT (has responsibility for performance monitoring), the Deputy Executive Member for Finance and IT, the Chair of Overview and Scrutiny (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they are able to. RMG were asked to comment on the content and format of the CDP Q2 update.
5.3The CDP is reviewed by Overview and Scrutiny Committee and they are asked to provide comments and recommendations to Cabinet.
6. FORWARD PLAN
6.1This report contains a recommendation on a key Executive decision first notified on the Forward Plan on the 7 June 2022.
Background
7.1The CDP brings together projects, risks and performance indicators together in one document. It was adopted by Cabinet in March 2022, which included the projects to be included within the CDP.
8. RELEVANT CONSIDERATIONS
8.1Appendix A provides an update on the progress made in delivering the Council Delivery Plan. Whilst it is labelled as a Quarter 2 update, it generally reflects the latest position at the time that the report was written (mid-November).
8.2Cabinet are asked to approve the following:
• The proposed change to current milestone dates for Town Centre Recovery, Resident/ Public EV charging in our car parks, Cycling Networks, Town Centre Strategies, Finalise Pay on Exit Parking Review, and Replacement of Royston Town Hall Annexe with reasons detailed in Appendix A.
• The progress made to date against each project and resulting impacts on future milestones, as detailed in the commentary against each project in Appendix A. Future updates will provide monitoring against any revised milestones.
8.3The intention is that the CDP reports provide an overview, as providing all the details on project milestones would lead to a report that was too long. Requests can be made (especially by O&S) to look at individual projects in more detail. Any such request would be incorporated in to the next monitoring report.
9. LEGAL IMPLICATIONS 9.1 The constitution determines the role of Cabinet as including: “To take decisions on resources and priorities, together with other stakeholders and partners in the local community, to deliver and implement the budget and policies decided by the Full Council. To monitor performance and risk in respect of the delivery of those policies and priorities” (paragraph 5.6.3) .
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.