25/02998/FP LAND BETWEEN SHANGRI-LA AND TODDS CORNER, STEVENAGE ROAD, TODDS GREEN, HERTFORDSHIRE, SG1 2JE
AgreedPlanning2 papers
AI summaryNorth Herts Planning Control Committee grants permission for four detached dwellings on Stevenage Road, Todds Green, subject to a Natural England great crested newt assessment and a list of planning conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFour detached dwellings with landscaping and parking
MoneyNone statedNo financial sums in the papers
What happens nextSubject to Natural EnglandImpact Assessment and Conservation Payment Certificate required first
Who it affectsTodds Green residents and highwaysVehicular access off Stevenage Road to be widened
What was decided
Application 25/02998/FP was granted planning permission for four detached dwellings, landscaping, parking and widening of the existing vehicular access off Stevenage Road. Report P1
The grant is conditional on receiving the Impact Assessment and Conservation Payment Certificate from Natural England under the Great Crested Newt District Level Licensing, with no objection from the North Herts Ecologist. Report P2
An extension of time to the statutory determination date is required to allow the Natural England process to complete, and the standard conditions and informatives in the report apply. Report P3, P4
Why
The application is for a residential development of four detached dwellings and the officer recommendation is approval subject to the stated conditions and informatives. Report P1, P4
Conditions cover materials, highways works, a Construction Traffic Management Plan, ecological enhancements including swift bricks, contaminated land investigation, and landscaping. Report P7, P8, P9, P10, P11, P12, P13, P14, P15
A Biodiversity Gain Plan will be required before development begins as the statutory exemptions do not apply. Report P5
What happens next
The applicant must apply to Natural England for the Great Crested Newt District Level Licensing and obtain the Impact Assessment and Conservation Payment Certificate, with the agreement of the North Herts Ecologist. Report P2
The statutory determination date must be extended to allow the Natural England process to be completed before permission is issued. Report P3
Once granted, development must begin within three years and comply with the full list of planning conditions, including the biodiversity gain plan, materials, highways, ecology, contamination, and landscaping conditions. Report P5, P6, P7, P8, P9, P10, P11, P12, P13, P14, P15
Options considered
Chosen: Grant planning permission subject to Natural England assessment and conditions. Officer recommendation in the Development and Conservation Manager's report Report P1, P4
Implications
Environment and climate: Great Crested Newt District Level Licensing required, an Ecological Enhancement Plan with bird, bat, bee boxes and swift bricks must be approved, and the development must follow the submitted Ecological Impact Assessment mitigation. Report P2, P10, P11, P12
Environment and climate: A Biodiversity Gain Plan must be approved by the council before development can begin, as no statutory exemption applies. Report P5
Risk: Phased contamination investigation and remediation are required, with a validation report before any dwelling is occupied, and a duty to report any unexpected contamination found during works. Report P13, P14
Other: Before first occupation, the widened vehicular access, visibility splays, footway connections, signage and lighting relocation must be completed to the Highway Authority's design guide, and surface water must be kept off the highway. Report P8
Other: A Construction Traffic Management Plan must be agreed with the Highway Authority before any development takes place, with construction noise restricted to the stated hours. Report P9, P16
Other: External materials must be approved before development starts, and landscaping must be completed in the first planting season with replacements for any losses within five years. Report P7, P15
Who and where
The applicant proposing four detached dwellings on the site Report P1
North Herts Ecologist, who must raise no objection after the Natural England assessment Report P2
Hertfordshire County Council as Highway Authority, consulted on access and construction traffic Report P8, P9
Natural England, which must process the GCN District Level Licensing application Report P2
Todds Green area residents and users of Stevenage Road, affected by construction, the widened access and the relocated signage and lighting Report P8, P9, P16
Timeline
2026-02-24: Planning Control Committee resolves to grant permission, subject to conditions and Natural England process
Before any development: Materials details, Construction Traffic Management Plan, Ecological Enhancement Plan, contamination desk study and Biodiversity Gain Plan must be submitted and approved Report P5, P7, P9, P10, P13
Before first occupation of any dwelling: Highways access works, footways, signage and lighting relocation must be completed, and a contamination validation report must be approved Report P8, P13
Within 3 years of the date of permission: The development must have begun Report P6
Plain English for the jargon
GCN District Level Licensing: Great Crested Newt District Level Licensing, a Natural England scheme allowing developers to pay for newt mitigation rather than carry out site-by-site surveys.
IACPC: Impact Assessment and Conservation Payment Certificate, issued under the GCN District Level Licensing to confirm a development's mitigation contribution has been paid.
BNG / Biodiversity Gain Plan: A plan required under the biodiversity gain condition in the Town and Country Planning Act 1990, showing how a development will deliver a required percentage of biodiversity net gain.
EEP (Ecological Enhancement Plan): A plan setting out new wildlife features such as integrated bird, bat and bee boxes, and swift bricks where building heights allow.
CTMP (Construction Traffic Management Plan): A plan setting out how construction vehicles will be managed, agreed with the local planning authority in consultation with the Highway Authority.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item136
Resolved
That application 25/02998/FP be GRANTED planning permission subject to: A) The receipt of the Impact Assessment and Conservation Payment Certificate (IACPC) following an application to Natural England under the GCN District Level Licensing (DLL) and a response of no objection from the North Herts Ecologist; and B) The agreement to an extension of time to the statutory determination date to allow time for (A) to occur; and C) The conditions and informatives as set out in the report of the Development and Conservation Manager.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Location: Land Between Shangri-La And Todds Corner Stevenage Road Todds Green Hertfordshire SG1 2JE
Applicant: [name removed]: Erection of four detached dwellings including landscaping, parking and widening of existing vehicular access off Stevenage Road.
Ref. No: 25/02998/FP
Officer: Alex Howard
Land between Shangri-La and Todds Corner CR
Date of expiry of statutory period: 31st January 2026
Extension of statutory period: 28th February 2026. The final consultation/publicity period expired on 4th January 2026.
Reason for Delay: To present at an available meeting.
Reason for Referral to Committee: This application has been called in by Cllr McDonnell, in support of the objections raised by the Parish Council.
1.0Site History
1.125/00949/FP - Erection of two detached dwellings with private gardens including landscaping, parking, and widening of existing vehicular access off Stevenage Road. Conditional Permission
2.0Policies
2.1North Hertfordshire District Local Plan (The Local Plan) 2011 – 2031
Policy SP1: Sustainable Development in North Hertfordshire Policy SP2: Settlement Hierarchy and Spatial Distribution Policy SP5: Countryside and Green Belt Policy SP6: Sustainable Transport Policy SP8: Housing Policy SP9: Design and Sustainability Policy SP11: Natural Resources and Sustainability Policy SP12: Green Infrastructure, Landscape and Biodiversity Policy SP13: Historic Environment Policy T1: Assessment of Transport Matters Policy T2: Parking Policy D1: Sustainable Design Policy D3: Protecting Living Conditions Policy NE1: Landscape Policy NE2: Green Infrastructure Policy NE4: Biodiversity and geological sites Policy NE12: Renewable and Low Carbon Energy Development Policy HE1: Designated Heritage Assets
2.2National Planning Policy Framework (NPPF) (December 2024) Section 2: Achieving sustainable development Section 4: Decision making Section 5: Delivering a sufficient supply of homes Section 8: Promoting healthy and safe communities Section 9: Promoting sustainable transport Section 11: Making effective use of land Section 12: Achieving well-designed places Section 14: Meeting the challenge of climate change, flooding, and coastal change Section 15: Conserving and enhancing the natural environment Section 16: Conserving and enhancing the historic environment
2.3Wymondley Neighbourhood Plan 2016
Policy NHE2 Biodiversity Policy NHE3 Wildlife and Ecology Policy NHE4 Green Infrastructure Policy Policy NHE8 Landscaping Schemes Policy NHE9 Historic Character and Heritage Assets Policy GB1 Green Belt Policy FR1 Flood Risk Policy FR2 Flood Risk Management Policy TM1 Roads
2.4Vehicle Parking at New Development SPD
Sustainability SPD
3.0Representations
3.1Site Notice and Neighbour Consultation – Comments received from Todds Corner, 4 Adstone Road and 12 Gilders (neutral) stating the following:
- Concern that the proposal, including the access road close to the northern boundary, would cause unacceptable harm to amenity, through being overbearing. Further concerns with development creep post application. - The proposal would erode the existing character and pattern of development, urbanising the area. - The two front dwellings are set back from the highway and the established building line, which is inconsistent. - A scheme of 4 dwellings cannot be considered limited infilling in the village, so it would conflict with the NPPF. - Concern that permitting this scheme would set an undesirable precedent for future similar development. - Request that the scheme incorporates at least four British Standard BS42021:2022 integrated Swift bricks, which could be secured by condition. 3.2 Hertfordshire Highways – No objection subject to two conditions and informatives.
3.3Wymondley Parish Council – Objects to the proposal on a number of grounds (summary):
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.