AI summaryNorth Herts Finance, Audit and Risk Committee noted the final 2025/26 SIAS progress report, with 82% of audit plan days delivered against an 86% target. Two high priority recommendations remain open and largely implemented; no audit plan amendments were agreed.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFinal 2025/26 SIAS update received by the Committee
MoneyNot stated
What happens nextAnnual Assurance OpinionDue at first Audit Committee of 2026/27
Who it affectsInternal audit assuranceCouncil governance and risk management
What was decided
The Committee noted the SIAS Progress Report for the period to 13 March 2026, including six final internal audit reports issued since the last update in January 2026. Report 2.2
The Committee noted the implementation status of high priority recommendations: one Estates finding and one Business Continuity Planning finding remain open and largely implemented. Report 2.4, 2.5
The Committee noted that no amendments to the 2025/26 Annual Audit Plan were agreed, though the EV Charging audit will be carried forward into 2026/27. Report 2.10, 2.15
Why
The Council must review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. Report 1.4
It is considered good practice for progress reports to include proposed amendments to the agreed annual audit plan. Report 1.4
SIAS must bring to Members' attention the implementation status of high priority recommendations; it is the responsibility of officers to implement them by the agreed date. Report 2.3
What happens next
Estates rent review policy and procedure documentation to be completed by a revised target date of 31 March 2026. Report 2.4, P86
The Cyber Resilience Plan will be subject to further review and update following a wider test exercise involving staff and Councillors. Report P95, P96
Performance against the remaining annual targets, including Public Sector Internal Audit Standards conformance, will be reported in the Head of Assurance's 2025/26 Annual Report. Report 2.18, P48, P50
Options considered
Chosen: Carry forward EV Charging audit into the 2026/27 Internal Audit Plan. Audit remains at planning stage at year end Report 2.15
Rejected: Agree audit plan amendments during 2025/26. No amendments had been agreed with management at the date of the report Report 2.10
Implications
Risk: Two high priority recommendations remain open, both reported as largely implemented, with the Estates policy work still in draft. Report 2.4, 2.5, P86, P96
Staffing: Delivery has been affected by the resignation of an Assistant Client Audit Manager, in-year trainee recruitment and capacity pressures linked to Local Government Reorganisation. Report P42
Other: Performance on Annual Internal Audit Plan delivery is 82% against an 86% target, and project delivery to draft report is 62% against a 90% target. Report P35, P37
Other: One new high priority recommendation was raised in the Purchasing Cards audit; the management response is reported as complete so no further follow-up will be reported. Report 2.7
Who and where
Finance, Audit and Risk Committee members Report 1.2, 1.4
Council officers responsible for implementing audit recommendations Report 2.3
Council staff subject to ongoing internal audits Report 2.16
IT and Communications teams involved in cyber resilience testing Report P95
Timeline
12 March 2025: Finance, Audit and Risk Committee approved the 2025/26 Internal Audit Plan Report 1.2
9 March 2026: Simulated desktop incident exercise held with Leadership Team, IT and Communications Report P95
13 March 2026: Progress measured as at this date: 82% of plan days delivered Report 2.1, P35
31 March 2026: Revised target date for completion of Estates policy and procedure work Report 2.4, P86
2026/27: EV Charging audit to be carried forward into the new plan Report 2.15
Plain English for the jargon
SIAS: Shared Internal Audit Service, the provider of internal audit to the Council
FAR Committee: Finance, Audit and Risk Committee of North Hertfordshire District Council
CAE: Chief Audit Executive, the head of internal audit
BDO: SIAS's external co-sourced audit partner
LGR: Local Government Reorganisation
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67
Resolved
That the Committee notes: (1) The SIAS Progress Report for the period to 13 March 2026. (2) The implementation status of the reported high priority recommendations. (3) The plan amendments to the 2025/26 Annual Audit Plan. REASON FOR DECISION: This report details progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Internal Audit Plan for 2025/26 as of 13 March 2026. That the Committee noted: (1) The SIAS Progress Report for the period to 13 March 2026. (2) The implementation status of the reported high priority recommendations. (3) The plan amendments to the 2025/26 Annual Audit Plan. REASON FOR DECISION: This report details progress made by the Shared Internal Audit ... view the full minutes text for item 67.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Report to Finance, Audit and Risk Committee, 17 pages
Appendices
A Progress against the 2025/26 Audit Plan
B 2025/26 Audit Plan Start Dates Agreed with Management
C Assurance and Finding Definitions 2025/26
D Implementation Status of High Priority Recommendations
Page 2 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Internal Audit Plan for 2025/26 as at 13 March 2026. b) In-Year Audit Plan review and proposed plan amendments. c) An update on performance indicators as at 13 March 2026. d) The implementation status of high priority internal audit recommendations.
Background
1.2The 2025/26 Internal Audit Plan was approved by the Finance, Audit and Risk Committee (the FAR Committee) on 12 March 2025.
1.3The Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the final update report for 2025/26 on the delivery of the Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 13 March 2026, 82% of the 2025/26 Audit Plan days had been delivered.
2.2There have been six final internal audit reports issued as part of the approved 2025/26 Internal Audit Plan since the last progress update to FAR Committee in January 2026:
Audit Title Assurance Recommendations Opinion
UK Shared Prosperity Fund 5 Low Priority and 2 Reasonable Advisory Actions
1 Medium and 2 Low Local Authorities as Charity Reasonable Priority; 2 Advisory Trustees Actions
1 High, 1 Medium and 1 Purchasing Cards Reasonable Low
Assurance Mapping N/A 1 Medium
High Priority Recommendations
2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.
2.4One high priority finding and recommendation made in the Estates audit, with an original implementation date of 31 December 2024, remains open and is reported as largely implemented. The service has advised that remaining actions should be completed by a revised target date of 31 March 2026.
2.5One high priority finding and recommendation made in the Business Continuity Planning audit with an original implementation date of 30 April 2023, remains open and is reported as largely implemented. The service has advised that remaining actions are subject to further review and update following recent test exercises and walkthroughs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.