AI summaryNorth Herts Finance, Audit and Risk Committee approved the council's 2026/27 Internal Audit Plan, covering 260 purchased audit days across general, IT, project assurance and follow-up work.
Money260 audit days purchasedAllocation across general, IT, strategic, grants, contingency
What happens nextQuarterly plan progress reportsFour updates to committee in 2026/27
Who it affectsCouncil services and residentsAudits cover housing, cyber, waste, reorganisation
What was decided
The committee approved the proposed North Herts Council Internal Audit Plan for 2026/27. Report P2
The committee noted the SIAS Internal Audit Strategy and Service Plan and invited comments. Report P2
The decision aims to give members and management independent, risk-based assurance on the council's governance, risk management and control arrangements. Report P10
Why
SIAS planning is required to conform with the Global Internal Audit Standards (UK public sector), which took effect from 1 April 2025. Report 1.2, 1.3
The plan is built from horizon scanning, the audit universe, risk assessment and discussions with senior managers, with topical requirements covering cyber and third-party risk. Report 2.3, 1.6, 2.8
Local authorities face rising demand, macro-economic pressure, cyber risk, workforce challenges, growth expectations and local government reorganisation, all shaping audit priorities. Report P57, P58, P59, P60, P61, P62
What happens next
Progress against the plan and any proposed changes will be reported to the committee four times in 2026/27. Report 3.1
An updated SIAS Internal Audit Charter will be brought to the June 2026 committee for member approval. Report 1.8
Any significant plan changes, postponements or cancellations will need approval from the Director (Resources) and be brought back to the committee for noting.
The money
260 days Total purchased internal audit days for 2026/27 Report 2.13, P73
148 days General internal audits (57%) Report P72
24 days IT audits (9%) Report P72
38 days Strategic support including audit committee and CAE opinion (15%) Report P72, P74
20 days Carry forward to complete 2025/26 projects (7%) Report P72, P166
12 days Recommendation follow-ups (5%) Report P72
8 days Grants or charity certification (3%) Report P72
5 days Consultancy, assurance mapping and contingency (2% each) Report P72
£3.2 million Capital funding awarded to Anderson House scheme under SHAP Report P172
£1.2 million Revenue funding over three years for Anderson House scheme Report P172
£388.3k Affordable housing commuted sums allocated by NHC Cabinet to OneYMCA for Anderson House Report P172
£17m Payments cited from a joint report on Peterborough City Council's homelessness accommodation, used as a benchmark for a planned audit Report P105
Options considered
Chosen: Approve the proposed 2026/27 Internal Audit Plan. Conforms with GIAS requirements and provides risk-based assurance Report P2, P14
Chosen: Note the SIAS Internal Audit Strategy and Service Plan. Strategy reviewed by SIAS Board in December 2025 Report 1.3
Rejected: Defer or decline audits in the plan. Plan is designed to be dynamic with reallocation possible from reserve list Report P175
Implications
Risk: The Chief Audit Executive must give an annual opinion on the council's internal control, governance and risk management framework, supported by enough completed audit work. Report 1.7, 2.17
Legal: Audits of the Renters Rights Act 2025, asset disposals, and emergency homelessness accommodation payments test compliance with new statutory duties and procurement law. Report P105, P119, P132
Staffing: Nine SIAS team members are studying towards professional qualifications; the service also uses an internal audit delivery partner for resilience and specialist skills. Report 2.20, 2.21
Equalities: Recommendation follow-ups include reviewing the Gender Pay Gap Action Plan and improving mandatory training completion rates. Report P147
Climate: Embedded audit coverage continues on the leisure centre and council buildings decarbonisation projects, linked to the council's 2030 carbon neutral target. Report P108, P110
Financial: Audits of asset disposals and new finance systems reflect the financial sustainability corporate risk and government guidance on decisions before local government reorganisation. Report P119, P202
Other: Audit time is allocated for local government reorganisation assurance, with unused days to be reallocated to the reserve list once the Secretary of State's decision is known. Report P124, P126
Who and where
Council members and senior managers receiving assurance Report P10, 3.1
Council residents and service users across North Hertfordshire Report P127
Herts Careline service users (over 13,000 residents supported in partnership with Hertfordshire County Council) Report P127
Private rented sector landlords and tenants affected by Renters Rights Act 2025 enforcement Report P132
Anderson House tenants and OneYMCA partner Report P172
SIAS partner councils and the Shared Internal Audit Service team Report 2.19, 2.20
Timeline
1 April 2025: GIAS (UK public sector) standards became effective Report 1.2
December 2025: SIAS Board reviewed the Internal Audit Strategy Report 1.3
12 January 2026: Nominations Agreement signed between OneYMCA and North Herts Council for Anderson House Report P173
5 February 2026: Cybersecurity Topical Requirement effective; government consultation on local government reorganisation commenced Report 1.6, P124
June 2026: Updated SIAS Internal Audit Charter to be brought to the committee for approval Report 1.8
15 September 2026: Third-Party Topical Requirement effective Report 1.6
2026/27: Internal audit plan delivery year, with quarterly progress reports to the Finance, Audit and Risk Committee Report 3.1
By 31 March 2028: Decarbonisation of Council Buildings Phase 2 works scheduled to complete Report P110
Plain English for the jargon
SIAS: Shared Internal Audit Service, the partnership that delivers internal audit to North Herts Council and other partners.
GIAS (UK public sector): Global Internal Audit Standards as applied to UK public sector bodies, effective from 1 April 2025.
CAE: Chief Audit Executive, the senior officer responsible for the internal audit function.
AGS: Annual Governance Statement, the council's annual statement on its governance arrangements.
Assurance map: A structured way of identifying and presenting the sources of assurance over how risks are being managed.
Three Lines (of Defence) model: A framework distinguishing operational management, risk and compliance oversight, and independent assurance as separate lines of defence.
Topical Requirement: A mandatory component of the International Professional Practices Framework covering specific risk areas such as cybersecurity.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68
Resolved
That the Commitee (1) Approved the proposed North Herts Council Internal Audit Plan for 2026/27 (2) Noted the SIAS Internal Audit Strategy & Service Plan and invited to provide any comments REASON FOR DECISION: To strengthen the Council’s ability to create, protect, and sustain value by providing Members and management with independent, risk-based, and objective assurance, advice, insight, and foresight. That the Committee (1) Approved the proposed North Herts Council Internal Audit Plan for 2026/27 (2) Noted the SIAS Internal Audit Strategy & Service Plan and invited to provide any comments REASON FOR DECISION: To strengthen the Council’s ability to create, protect, and sustain value by providing Members and management with independent, risk-based, and objective assurance, advice, insight, and foresight.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Report to Finance, Audit and Risk Committee, 47 pages
INTERNAL AUDIT PLAN REPORT 2026/27 NORTH HERTS COUNCIL FINANCE, AUDIT AND RISK COMMITTEE 25 MARCH 2025
RECOMMENDATION Members are recommended to approve the proposed North Herts Council Internal Audit Plan for 2026/27 Members are requested to note the SIAS Internal Audit Strategy & Service Plan and invited to provide any comments Contents
1. Introduction and Background
2. Audit Planning Process 2.1 Planning Principles 2.2 Approach to Planning 2.10 Planning Context 2.13 Internal Audit Plan 2026/27
Appendices A Proposed North Herts Council Audit Plan 2026/27
B Audit Start Dates Agreed with Management
C Risk Register Mapping to Internal Audit Plan
D Glossary of Terms
E SIAS Internal Audit Strategy 2026/27 1. Introduction and Background 1.1 The purpose of internal audit is to strengthen the Council’s ability to create, protect, and sustain value by providing Members and management with independent, risk-based, and objective assurance, advice, insight, and foresight.
1.2The Global Internal Audit Standards (GIAS), Application Note: Global Internal Audit Standards in the UK Public Sector and CIPFA Code of Practice for the Governance of Internal Audit in UK Local Government, taken together, form the basis of UK public sector internal audit standards, which became effective from 1 April 2025. The Application Note states that a professional, independent, and objective internal audit service is one of the key elements of good governance, as recognised throughout the UK public sector.
1.3The SIAS Board reviewed the SIAS Internal Audit Strategy in December 2025, and this strategy outlines how SIAS will achieve the purpose of internal audit and ensure ongoing compliance with the GIAS (UK public sector). The following report outlines the key principles related to Audit Planning and Resourcing, with the Internal Audit Strategy itself attached as an appendix. The GIAS (UK public sector) includes setting out how SIAS must approach internal audit planning. The specific requirements that SIAS must adhere to are set out below:
Standard Description Domain III Board and Senior Management Support 6.3 It is an essential condition for Senior Management and the Audit Committee to approve the internal audit plan. Domain III Board Interaction 8.1 The Chief Audit Executive (CAE) must provide the Audit Committee with the information needed to conduct its oversight responsibilities. This includes the internal audit plan and subsequent significant revisions. Domain III Resources 8.2 The CAE, Audit Committee and Senior Management must collaborate to ensure that internal audit has sufficient resources to fulfil the internal audit mandate and achieve the internal audit plan. This should be at least annually, and cover numbers and capability, as well as the impact and remedy of insufficient resources on the internal audit mandate and plan (if applicable). Domain III Quality 8.3 Amongst the essential conditions in this Standard is a requirement for the Audit Committee to review and approve the internal audit functions performance objectives at least annually. This includes its conformance with the Standards, laws and regulations, ability to meet the internal audit mandate, and progress towards completion of the internal audit plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.