COUNCIL DELIVERY PLAN 2025-26 (QUARTER 3 UPDATE)

Noted Executive 2 papers

AI summaryNorth Herts Cabinet noted progress on the 2025-26 Council Delivery Plan and approved new and revised project milestones. Three projects are complete, two carry amber delivery status, four carry red risk, and three performance indicators are rated red.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIncluding new Museum Collection Facility project
MoneyNo direct financial implications, per the report
What happens nextYear-end monitoring reportMost new KPIs to be reported there
Who it affectsCouncil projects, KPIs and risksMonitored through the Council Delivery Plan

What was decided

Cabinet noted progress against Council projects and performance indicators and approved new milestones and changes to milestones. Report 2.1

A new item relating to the Museum Collection Facility project and its associated risks was added to the Council Delivery Plan. Report P4, 8.2

Revised milestone dates were approved for the Churchgate project (soft market testing at UKREiiF in May 2026, with committee reports now expected in June 2026) and the Digital Transformation project, including a new go live date of 12 March 2026 for the Safety Advisory Group platform. Report 8.3, P22

Why

Quarterly Council Delivery Plan monitoring reports let Cabinet and Overview and Scrutiny Committee track progress against key projects and understand new issues, risks or opportunities. Report 3.1

No alternative options were considered; it was previously agreed that Cabinet would receive quarterly updates, with Overview and Scrutiny providing additional oversight. Report 4.1, 4.2

What happens next

A Professional Technical Services contractor for the Museum Collection Facility is due to be appointed by the end of March 2026, with renovation currently estimated to complete in Summer 2027. Report 8.2

Officers will continue work to set up new KPIs aligned to Council Plan objectives on the Ideagen system, with most to be included in the year-end monitoring report for 2025-26. Report 8.9

Actions are in hand to return Careline installation and call answering performance to target, including technician recruitment, scheduling discipline, temporary recruitment, and closer coordination with services before large outbound communications. Report P25, P26

Options considered

  • Chosen: Receive a quarterly update on the Council Delivery Plan. Previously agreed approach providing Cabinet and Overview and Scrutiny with monitoring oversight Report 4.1, 4.2

Implications

  • Legal: No specific legal implications arise from the report; a robust and measurable delivery plan supports the Council's best value duty under Section 3 of the Local Government Act. Report 9.3, 9.4
  • Financial: No direct financial implications; project efficiencies and investments are tracked through the budget and quarterly finance reports. Report 10.1
  • Equalities: No direct equalities implications arise from the report. Report 12.2
  • Risk: Seven of 17 risks are rated high (red), including Churchgate, Decarbonisation Phase 2, Local Plan Review, Museum Collection Facility, and three corporate risks; Financial Sustainability has moved from red to amber. Report P4, 8.8
  • Staffing: There is an ongoing need to align Council and Service objectives with available people resources; Careline performance is affected by technician capacity and recruitment. Report 14.1, P25

Who and where

  • Overview and Scrutiny Committee members reviewing delivery progress Report 3.1, 5.3, 8.11
  • Careline service users waiting for installations Report P25
  • Callers to the Customer Service Centre Report P26
  • Residents affected by the Council's major projects including Churchgate, decarbonisation of Council buildings, the Local Plan Review, and the new Museum Collection Facility Report P4, 8.2, 8.3

Timeline

  • 26 February 2026: Full Council approved the 2026-27 budget, completing the Engaging the community on our finances project Report P4
  • 2025-26 Quarter 3 (to early March 2026): Period covered by the update Report P1, 8.1
  • By the end of March 2026: Professional Technical Services contractor due to be appointed for the Museum Collection Facility Report 8.2
  • 12 March 2026: New Safety Advisory Group platform go live Report 8.3, P22
  • 31 March 2026: Target for completing waste process TechnologyOne automations Report 8.3, P22
  • May 2026: Churchgate soft market testing phase at UKREiiF Report 8.3, P22
  • June 2026: Reports on Churchgate expected to be presented to relevant committees Report 8.3, P22
  • Summer 2027: Current estimate for completion of the Museum Collection Facility renovation, followed by relocation of the museum collection Report 8.2

Plain English for the jargon

  • CDP: Council Delivery Plan, the document that brings together projects, risks and performance indicators
  • KPI: Key Performance Indicator, a measure used to track overall Council performance
  • RPMG: Risk and Performance Management Group, internal group that reviewed the draft Q3 update
  • O&S: Overview and Scrutiny Committee
  • FAR: Finance, Audit and Risk Committee
  • SAG: Safety Advisory Group, with a new digital platform going live in March 2026
  • UKREiiF: UK Real Estate Investment and Infrastructure Forum, venue for the Churchgate soft market testing in May 2026
  • Ideagen: The Council's performance and risk management system holding the live Council Delivery Plan data
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 7 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 2025-26. This is a Quarter 3 update but generally reflects progress up to the point that the report was prepared (early March 2026). The report includes:

• For the projects identified by Cabinet, it details milestones and progress against them. • The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. • Latest data for the Council’s key performance indicators (KPIs).

Points to note:

• A new item relating to the Museum Collection Facility project and associated risks has been added to the Council Delivery Plan. • Three projects are complete and associated risks have been managed to the target level. Two of these were reported in the Quarter 2 Update (King George V Skate Park and Waste and Street Cleansing Contract) and the other one was completed following approval of the 2026-27 budget at Full Council on 26 February 2026 (Engaging the community on our finances). • Two projects have an amber delivery status (Churchgate, and Digital Transformation). • Four projects have a high risk (red) status (Churchgate, Decarbonisation of Council Buildings - Phase 2, Local Plan Review, and Museum Collection Facility). • Three of the four over-arching Corporate Risks also have a red status, with the other one (Financial Sustainability) now assessed as a medium (amber) risk. • There are three KPIs that have a red status (two relating to Careline installations and one relating to CSC calls answered in 45 seconds).

This report also provides an update on developing agreed new KPIs that align with Council Plan objectives and the proposed timing for these to be included in future Council Delivery Plan monitoring reports. 2. RECOMMENDATIONS

2.1That Cabinet notes progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approves new milestones and changes to milestones.

Reasons for recommendations

3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.

4.2Therefore, no alternative options were considered for this report.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.

5.2A draft of the Quarter 3 update was provided to the Risk and Performance Management Group (RPMG) in February 2026. The Group has a standing invite to the Executive Member for Resources (who has responsibility for performance monitoring), the Chair of Overview and Scrutiny Committee (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S, FAR, and Cabinet are also encouraged to attend if they can. RPMG were asked to comment on the Q3 update. There were no specific issues raised by the Group.

5.3The Overview and Scrutiny Committee were asked to provide comments on the current progress of the CDP, including recommendations to Cabinet.

5.4New KPIs that link to actions in the Council Plan were previously discussed by the internal informal Political Liaison Board of the Executive and Leadership Team in August 2025, followed by a further discussion at Political Liaison Board in December 2025. They were then considered by O&S and Cabinet in January 2026.

6. FORWARD PLAN

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Delivery Plan 2025-26 Q3 Monitoring ReportAppendix A 33 pages Download
PDF
COUNCIL DELIVERY PLAN 2025-26 (QUARTER 3 UPDATE)Report 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. COUNCIL DELIVERY PLAN 2025-26 (QUARTER 3 UPDATE)This decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (q3 update)Approved
  4. Council delivery plan 2025-26 (quarter 2 update)Noted
  5. Council delivery plan 2025-26 (quarter 2 update)Approved
  6. Council delivery plan 2025/26 (quarter 1 update)Noted

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies