North Kesteven District Council
Executive Board, Tuesday 6 December 2011 at 2.00pm

Sports Hall Floor: North Kesteven Sports Centre

Approved Executive 1 paper

Executive Board approved this item on Tuesday 6 December 2011. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

Approved: 1. That Options 1 2 and 3 to reduce the risk of future water ingress are further investigated and costed . 2. That the Sports Hall Floor should be replaced during the Summer School Holidays 2012 following the investigations and conclusions of options 1, 2 and 3. 3. That the cost of replacement is initially funded from the renewals reserve and the project treated as capital within the tripartite agreement. This will provide for up to 40% of the cost from Lincolnshire County Council as per the tripartite agreement.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board, 7 pages

Summary

1.0BACKGROUND INFORMATION

1.1On February 19th 2004 a burst mains water pipe near the building caused a build up of water under the sports hall, which lifted the granwood floor. Following the incident the damaged sports hall floor was assessed and tests carried out by a structural engineer in accordance to the requirements of the loss adjustor acting on behalf of the Council’s Insurers. A replacement floor was met by the Council’ Insurers with the burst water pipe being paid for by the Council 1.2 The flooring system was selected in consultation with the School and was a Dyna – Combi floor which required the removal of the entire granwood floor. This new floor system has three elements an elastic matt layer, a marine play matrix and a polymer floor. It has proved very popular across the wide range of sports due to its cushioning and improved flexibility and durability over the granwood floor.

1.3The floor began to distort in two places a few years after installation. This gradually became more pronounced and investigations were undertaken to determine the cause. These investigations were not entirely conclusive in determining the cause of the water damage. After discussion with the project management consultant who managed the floor installation on behalf of the Council it was confirmed that the floor had been laid in compliance with manufacturer’s recommendations.

1.4Leisure Connection carried out further investigations which identified water penetration above and below the waterproof membrane which had caused the floor to swell in two distinct areas. There were a number of rainwater pipes from the roof which ran under the sports hall floor and these were surveyed using a camera imaging system. This identified no visible damage to these pipes although water leakage from these pipes could not be discounted. Ground water had also been suspected as a cause of the water damage. There was again no conclusive evidence which gave confidence to both these theories. 1.5 Inspection of the whole floor identified that there was damp in other areas although worse in the two main damaged areas. A partial repair was ruled out due to the floor construction and inherent risk of further distortion or damage in other areas.

1.6The inconclusive inspections and examinations raised three key issues:

1 Whether the water ingress would be covered under an insurance claim 2. The actual cause of the water ingress and how to prevent it in the future 3. Whether the floor could be repaired or a new floor would be required and the type of flooring to replace the current system.

1.7The property services team were involved in suggesting companies who could investigate the issues and provide a detailed report to form the basis of an insurance claim. In November 2009 Leisure Connection engaged Stirling Maynard one of the suggested companies to investigate the cause of the water ingress.

2.0DETAILED INVESTIGATIONS

Stirling Maynard was appointed by Leisure Connection to carry out further extensive tests to establish the cause of the water ingress which would enable an insurance claim to be submitted. 2.1 Initial Site Investigation A site investigation was undertaken on the 11 February 2010, by Andrew Elloway and Daniel Morrell of Stirling Maynard. On site they met with Steve Dunn, the Site Manager.

The site work comprised:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sports Hall Floor: North Kesteven Sports CentreReport 7 pages DownloadRead as text

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies