That the proposal to increase the electrical inspections to a five year programme be approved; 2. That the budget for 2015/16 be established in line with the proposal detailed within the report; and 3. That a budget bid be submitted through the budget making process for 2016/17 to secure the long term funding. 1. That the proposal to increase the electrical inspections to a five year programme be approved; 2. That the budget for 2015/16 be established in line with the proposal detailed within the report; and 3. That a budget bid be submitted through the budget making process for 2016/17 to secure the long term funding. Actions: Mick Gadd Michael Kelleher Philip Roberts
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Current Position The current Housing Asset Strategy (2012) sets out the council’s position with regard to the inspection of fixed wiring in the councils housing stock. It states;
Electrical safety inspections of the fixed wiring installations are undertaken at periods of between five and ten years based on condition. The next inspection date is detailed on each certificate issued.
The 30 year business plan included a budget provision for this work. The budget allocation is for £210k a year, for three years, every 10 years. The next round of inspections is not due to start until 2017/18.
Although there isn’t a legal requirement to test fixed wiring at a stated period, landlords do have a duty to ensure that electrical installations are safe. The Electrical Inspection Council have recently issued new best practice guidance which suggests that inspections should be undertaken at periods not exceeding five years.
Proposal It is proposed that a new inspection regime be commenced based on carrying out inspections in accordance with the best practice guidance. It would be intended to inspect 20% of the stock each year over a five year period. This will have an impact on the HRA over the 30 years of £1m (based on 2015 costs)
As part of the tender package for the collaborative Gas Servicing Contract, electrical inspections were included. Contract costs have therefore been established and the work would be issued to Aaron Services through this contract ( the City of Lincoln already use Aaron for this service)
Finance If agreed, in order to finance this proposal in the longer term, a Revenue Budget Bid will be submitted in September. The existing budget provision will assist to smooth this out. However, In order to fund the work in 2015/16 a Revenue budget would need to be established of an additional £100k.
The provisional HRA capital programme underspend of £1,621,200 (subject to sundry creditors and budget carry forward requests) is predominantly due to the £928,500 heating budget underspend. This means that there will be a much reduced drawdown from the Major Repairs Reserve (MRR) to fund the 2014/15 HRA capital programme.
As the MRR will have a higher drawable balance than originally anticipated as at 31st March 2015, it is suggested that a reduced contribution of £100,000 to the MRR from the Housing Revenue Operating Account be made, keeping back £100,000 in the working balance to fund the revenue expenditure for electrical testing budget required in 2015/2016.
Benchmarking Exercise An exercise has been carried out with other local social landlords to establish the frequency of inspections within their organisations.
Of the seven landlords who responded four have implemented a five year programme already. Two are in a transitional period from a ten year programme to a five year programme due to budgetary constraints and one is remaining with a ten year programme.
.
Recommendations
1. That the Executive Board approve the proposal to reduce the electrical inspections to a five year programme. 2. That the budget for 2015/16 be established in line with the proposal detailed within the report. 3. That a budget bid be submitted through the budget making process for 2016/17 to secure the long term funding. IMPLICATIONS Relationship to Community Strategy Relates to the Our Homes Priority.
Customer Impacts Ensures properties are kept safe
Financial Impacts
Additional cost to the HRA
Impact on Performance and data quality None.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.