CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Northamptonshire Council
Executive, Thursday 26 August 2021 at 2.00pm

Improvement of facilities at Montsaye Academy, Rothwell, using banked Section 106 funding

Approved Executive

Executive approved this item on Thursday 26 August 2021. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

(KEY DECISION) a) That the release of £606,446 of Section 106 contributions for Montsaye Academy be approved; b) That the delivery of the project by Pathfinder Schools Academy Trust be approved; c) That authority be delegated to the Executive Member for Children, Families, Education and Skills in consultation with the Director of Children’s Services to enter into a Funding Agreement between North Northamptonshire Council and Pathfinder Schools Academy Trust for the delivery of planned improvement works. (Reasons for Decisions – · The recommended course of action will allow the timely progression of capital improvement works at Montsaye Academy that are required to improve the educational environment for students and staff; · The recommended course of action will benefit students currently being educated at Montsaye Academy; · The Council (or customers) will receive the maximum benefit from the option proposed and Montsaye Academy will be able to derive the full benefit of the banked S106 contributions.)
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies