What the committee will consider, in order, with every paper attached to its item. Chester House Estate Programme and Business Plan Update is the main business.
To set out the forecast outturn position for the Council based on the Period 4 monitoring forecasts for the General Fund and the Housing Revenue Account.
Decision: (KEY DECISION) a) That the Council’s forecast outturn position for 2021/22 and the associated risks and other considerations be noted; b) That the assessment of the current deliverability of the 2021/22 saving proposals in Appendix A to the report be noted; c) That a virement of £690k from contingency to enabling and support services be approved to allow budget realignment within overall available resources, as set out in paragraph 6.54 and 6.58 of the report; d) That support for local bus... Decision page
To request approval for capital schemes that have come forward for inclusion in the Council’s Capital Programme. Approval of the funding will allow the schemes to move forward to procurement and delivery.
Decision: (KEY DECISION) 1. That the following changes into the capital programme totalling £2.295m be approved: - a) A43/A6116 Steel Road Roundabout – increase in budget of £1.020m to £3.973m funded from external grant; b) Isebrook SEND College – Connected offer expansion of the school – approval for additional £482k funded from Special Educational Needs and Disabilities (SEND) Capital Grant, taking the total of the scheme to £0.532m; c) Improvement of Facilities at Montsaye Academy, Rothwell – Council... Decision page
To enable mobilisation of the refreshed business plan ahead of planned site opening to the public on 23rd October 2021.
Decision: a) That the positive progress to date with the Chester House Estate Capital Works programme and future business development be noted; b) That the refreshed Business Plan July 2021 attached at Appendix B to the report be endorsed and regular updates on progress against it be received. (Reason for Decision page
To provide an up-to-date development plan for making planning decisions and to guide development in Corby.
Decision: Recommendations to Council That Council be recommended: - a) that the Part 2 Local Plan for Corby (set out in Appendix A to the report) be adopted; b) to delegate authority to the Executive Member for Growth and Regeneration in consultation with the Assistant Director for Growth and Regeneration, to make any further Additional Modifications to the Part 2 Local Plan for Corby or its accompanying Policies Map that relate exclusively to factual updates, grammatical corrections, and formatting for... Decision page
To inform of the grants received from the Department of Transport ( DfT ) for infrastructure improvements and the intention to spend these amounts on the highways network.
Decision: (KEY DECISION) 1. That the receipt of the government grants totalling £9.955m be noted and accepted, made up of the following: a) Allocation of Department for Transport Capital Maintenance Funding 2021/22 - £8.404m b) Local Transport Plan Integrated Transport Block Funding 2021/22 - £1.551m 2. That it be agreed to spend the grants on maintaining and upgrading the highways network in line with the Northamptonshire Transport Plan. (Reason for Decisions - Utilisation of government grant to support... Decision page
To ensure there is a comprehensive approach to tackling litter and fly-tipping, using a number of different intervention actions to tackle the issue.
Decision: That the North Northamptonshire Strategy for tackling litter and fly-tipping, attached at Appendix 1 to the report, be approved. (Reasons for Decision – To accord with legislation and the policies of the Council; To provide a comprehensive approach to tackling litter and fly-tipping across North Northamptonshire; and To support the North Northamptonshire Street Cleansing Policy.) Decision page
To passport banked Section 106 funding, that names Montsaye Academy as beneficiary, for use on a capital improvement scheme to improve the educational facilities at the school.
Decision: (KEY DECISION) a) That the release of £606,446 of Section 106 contributions for Montsaye Academy be approved; b) That the delivery of the project by Pathfinder Schools Academy Trust be approved; c) That authority be delegated to the Executive Member for Children, Families, Education and Skills in consultation with the Director of Children’s Services to enter into a Funding Agreement between North Northamptonshire Council and Pathfinder Schools Academy Trust for the delivery of planned... Decision page
To consider the proposal to fund an annex site or ‘Connected Offer’ provision to Isebrook SEND College, Kettering.
Decision: (KEY DECISION) a) That the proposal to establish an annex site or ‘Connected Offer’ provision to Isebrook SEND College at the ‘Four Seasons’ building, Kettering by the Creating Tomorrow Academy Trust (the Academy Trust that operates Isebrook SEND College) be noted; b) That the required expenditure of £481,886 to allow for the progression of the proposed scheme and to note that this scheme will be funded via SEND Capital Grant funding received directly from central government be approved; c)... Decision page
To secure an efficient, proportionate, consistent and effective approach to all regulatory, inspection and enforcement activity undertaken by the Council.
Decision: (KEY DECISION) That the , attached at Appendix A to the report, be approved. (Reasons for Decision - The adoption of an by the Council provides clarity as to the regulatory approach which will be adopted by the Council. Adoption of the policy ensures that the Council discharges its obligations under the Regulator’s Code, issued by the Better Regulation Delivery Office (BRDO) pursuant to the Legislative and Regulatory Reform Act 2006.) Decision page
To agree technical updates to the Planning Obligations Framework and Guidance Document “Creating Sustainable Communities” (2015).
Decision: a) That it be agreed that the 2021 updated baseline pupil yield figures (as set out in Table 3 of the report) and benchmark costs (as set out in Table 5) replace those set out in the Obligations Framework 2015; b) That authority be delegated to the Executive Member for Growth and Regeneration in consultation with the Director of Place and Economy to review and amend the pupil yield figures and benchmark costs on an annual basis. (Reasons for Decisions - To ensure the Section 106 contributions... Decision page
To set out the options for distribution of the Additional Restrictions Grant top-up funding in order to support the local economic recovery framework.
Decision: (KEY DECISION) a) That the approach taken by the Council to allocate previous discretionary Additional Restrictions Grant be noted; b) That the four options outlined at Appendix A to the report for utilising Additional Restrictions Grant top-up funding to support the local economic recovery be approved; c) That authority be delegated to the Executive Member of Growth and Regeneration in consultation with the Executive Director of Place and Economy to allocate the Additional Restrictions Grant... Decision page
Decision: That the forecast outturn position for 2020/21 for Kettering Borough Council and the Borough Council of Wellingborough be noted. (Reason for Decision – To inform Members of the outturn position for 2020/21 for both Kettering Borough Council and the Borough Council of Wellingborough as the outturn will form part of the Statutory Statement of Accounts.) Decision page
Decision: (KEY DECISION) a) That it be agreed to commence a procurement process for a Leisure Management Contract for the management of Kettering Swimming Pool, Kettering Athletics Track and Synthetic Pitch, Corn Market Hall, and Desborough Leisure Centre for a contract as set out in paragraph 4.11 of the report; b) That authority be delegated to the Executive member for Sport, Leisure, Culture and Tourism in consultation with the Assistant Director, Housing & Communities, to take any further decisions... Decision page
Decision: (KEY DECISION) a) That the work undertaken to date to get the project to the delivery Stage be endorsed; b) That it be agreed to increase the project cost within the Delivery Plan from £2,950,000 to £3,973,252. (Reasons for Decisions – The Council and general public will receive the maximum benefit from the option proposed; To re-affirm the Council’s ambitious plans for growth and regeneration; Consistency with previous decisions made by Corby Borough Council; Northamptonshire County Council... Decision page
Item 49 is where most of this meeting's papers sit: 3 papers, about 30 MB.
To enable mobilisation of the refreshed business plan ahead of planned site opening to the public on 23rd October 2021.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 29 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 5 August 2021. 3 of its items lead into this meeting; 9 items are new. Point at any item to follow a thread. Procedural items are left out.
Housing Land Supply in North Northamptonshire, Integrated Care System Design Principles, Oxford to Cambridge Arc - Environmental Principles, Performance Indicator Report 2021/22 (Quarter One) and 3 more do not return this time.
See the 5 August meetingEvery Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
North Northamptonshire, Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.