North Northamptonshire Council
Executive, Thursday 22 December 2022 at 9.00am

Capital Programme Update 2022/23

Approved Executive 1 paper

Executive approved this item on Thursday 22 December 2022. Below is the council's own wording, with the papers it was decided on.

Item361

Resolved

RESOLVED KEY DECISION That Executive: i ) Approved the following changes into the capital programme totalling £9.696m: a. Isebrook SEND College expansion of school - increase of £341k to the capital programme for 2022/23, which is to be funded from the SEND Capital grant. b. Schools Minor Works programme – budget approval for £3.894m; £1.95m in 2023/24, £1.95m in 2024/25, which is to be funded from the DfE Schools Condition Allocation (SCA) grant. c. Kingswood Secondary School Bulge funding – budget approval for £554k; £213k in 2022/23, £341k in 2023/24 which is to be funded from DfE Schools Basic Need grant. d. Earls Barton Primary School Expansion – budget approval for £2.8m; £215k in 2022/23, £1.29m in 2023/24, £1.29m in 2024/25 which is to be funded £2.084m from S106 and £713k from DfE Schools Basic Need grant. e. Rowan Gate Primary School – budget approval for £1.661m, £172k in 2022/23, £1.006m in 2023/24, £482k in 2024/25 which is to be funded from DfE Schools Basic Need grant. f. Wrenn Spinney installation of mobile classroom – budget approval for £190k for 2022/23 which is to be funded from the SEND Capital grant. g. Local Authority Treescape Fund (LATF) – budget approval for £260k; £90.5k in 2022/23, £56.4k in 2023/24, £56.4k in 2024/25, £56.4k in 2025/26, to be funded from external capital grant. Reasons for Recommendations are set out in greater detail within section 5 of the report, but can be summarised as: • To support the statutory delivery of school places and SEND school places across North Northamptonshire. • To access funding for planting and caring for trees across North Northamptonshire, helping to meet the priorities of the Corporate Plan, particularly: - Active, fulfilled lives - Thriving places Alternative Options Considered: • As all the schemes in this report are grant funded/S106 funded, the use of the funding is in line with the agreement, so there is no alternative option proposed in this report. • Where schemes are over £500k, individual reports are presented elsewhere on the agenda that set out the wider options that were considered before reaching the proposed schemes identified for grant funding/S106 funding.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update 2022/23Report 189 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Capital Programme Update 2022/23This decision
  2. General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030Approved
  3. Capital Programme Update 2025/26Noted
  4. Capital Programme Update 2025/26Approved
  5. Capital Programme Report 2025-2029Approved
  6. Capital Programme Update 2024/25Approved

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies