What the committee will consider, in order, with every paper attached to its item. Carbon Management Plan is the main business.
Decision: RESOLVED that: The Executive agreed the minutes of the meeting held on 10 th November 2022 as a true and accurate record of the meeting, subject to a minor addition to the Declarations of Interest relating to Cllr Pentland. Decision page
Decision: RESOLVED That the Executive: a) Noted the performance of the Council as measured by the available indicators at Period 7 2022/23 as set out in the appendices to this report. b) Noted the progress being made in the development of the Council’s approach to performance management. Reason for Recommendations – to better understand the Council’s performance as measured by performance indicators as at Period 7, 2022/23. Alternative Options Considered – reporting performance data on a less frequent... Decision page
Decision: RESOLVED KEY DECISION That the Executive: a) Approved for consultation the 2023-24 Draft Revenue Budget, which includes: i. An estimated net revenue budget of £335.9m (£683.9m including the Dedicated Schools Grant) as set out in Appendix A, noting that this is subject to further update and change following the publication of the provisional Local Government Finance Settlement. ii. A Band D Equivalent Council Tax of £1,657.51 for North Northamptonshire Council, representing an increase of 2.99%... Decision page
Decision: RESOLVED KEY DECISION T hat the Executive: a. Noted the draft 2023/24 Housing Revenue Account Budgets consisting of the Corby Neighbourhood Account and the Kettering Neighbourhood Account as set out in Appendix A of the report , which will be consulted upon with Tenants, which includes: i) an increase in dwelling rents for 2023/24 of 7% which adheres to the Department for Levelling Up, Housing and Communities (DLUHC) amended Policy statement on rents for social housing. b. Notes the draft... Decision page
Decision: RESOLVED KEY DECISION T hat the Executive: a) Approved for consultation the General Fund Capital Programme 2023-26 and HRA . b) Noted the Development Pool 2023-26 and that schemes within the pool will be subject to further approval prior to inclusion in the programme. Reason for Recommendations: To ensure that the Council complies with its Constitution and legislative requirements in setting the budget for North Northamptonshire Council for 2023-24. Alternative Options Considered - This is the... Decision page
Decision: RESOLVED KEY DECISION T hat the Executive: a) Considered and noted the content of the report, in particular the due diligence undertaken, legal considerations in sub-letting a specialist Care Centre and risks identified b) Noted the ongoing negotiations and commitments with systemwide partners to utilise various funding sources such as Winter Discharge monies, and Better Care Fund c) Considered and noted the various financial modelling scenarios set out in Appendix A and section 7.1 of this... Decision page
Decision: RESOLVED KEY DECISION That the Executive: a) Approved the creation of a single model of delivery for the Sensory Impairment Service within education across Northamptonshire, located within North Northamptonshire Council, which could be commissioned by others. b) Approved the proposal to seek transfer of Access and CommunicationSupport Workers (ACSWs) employment from the Sensory Impairment Service directly into schools (as outlined in the recommended new delivery model and explained within... Decision page
Decision: RESOLVED KEY DECISION That the Executive approved the at Appendix A of the report for adoption. Reasons for Recommendations: i) The Council has fiduciary responsibilities to progress surplus vacant sites within a reasonable time, which government policy recommends is no later than two years, to ensure value for money is achieved. The supports this outcome. ii) Progressing disposals of surplus properties in a co-ordinated way will contribute to the Corporate Plan and the commitment to be carbon... Decision page
Decision: RESOLVED KEY DECISION T hat the Executive approved the Carbon Management Plan at Appendix A of the report and priority areas for investment of the £1m climate change funding allocation. Reasons for Recommendation: • The plan sets out the key areas of focus for the Council in order to achieve its target to be carbon neutral by 2030. • The plan supports the Council’s ambition for climate change mitigation as set out in the Corporate Plan. • Whilst the projects deriving from the plan will require... Decision page
Decision: RESOLVED That the Executive: a) Noted the content of the PAS Peer Review Report and its recommendations b) Considered and approved the PAS Peer Review Action Plan (as set out in Appendix B of the report ) c) Approved the formation of a Planning Transformation Board and associated governance arrangements (as set out in Appendix C of the report ) to oversee the planning transformation activities associated with the Peer Review and Action Plan c) Agreed that the progress of transformation in... Decision page
Decision: RESOLVED KEY DECISION That the Executive: a) Delegated to the Executive Director of Finance, in consultation with the Executive Director of Place and Economy, authority to prepare and submit the Business Case Summary Document for the Multi-use Building (which is the final project in the Corby Town Fund) to the DLUHC. b) Approved the drawdown of funding for this project once released by the DLUHC and delegate to the Executive Member for Growth and Regeneration in consultation with the Executive... Decision page
Decision: RESOLVED KEY DECISION That the Executive approved the implementation of four key priorities for the corporate parenting board, specifically: a) Approved the establishment of Corporate Parenting Operational Groups as set out in Section 3 (page 19) of the annual report. b) Noted that the Head of Paid Service will consider the inclusion of corporate parenting responsibilities being set out in every North Northamptonshire job description as set out in Section 3 (page 19) of the annual report. c)... Decision page
Decision: RESOLVED KEY DECISION That the Executive: a) Noted the Council’s allocation of ‘School Condition Allocation’ funding for 2022/23 & 2023/24 confirmed by the DfE at a total of £3,893,829 and that the grant funding will be utilised as the Council’s ‘School Minor Works’ budget for 2022/24; b) Noted that the budget approval to complete works to rectify condition issues within schools, to support the Council to fulfil its statutory obligation of maintaining its school estate is included within the... Decision page
Decision: RESOLVED KEY DECISION That the Executive: i) Approved the Project to replace the Temporary Mobile Units at Rowan Gate Special School, Wellingborough with permanent classrooms. ii) Noted the scheme will be funded via High Needs Provision Capital Grant funding received directly from central government; The budget approval is included within the Capital Programme Update report to Executive elsewhere on this agenda. iii) Delegated authority to the Executive Member for Children, Families and... Decision page
Decision: RESOLVED KEY DECISION That the Executive : i) Approved the proposed scheme to be delivered through the Funding Agreement with Greenwood Academies to enable the Kingswood Secondary School to temporarily increase its PAN and enable the Local Authority to perform its statutory duty to provide sufficiency of places in Corby. ii) Noted that budget approval of £553,849 for this scheme is included within the Capital Programme Update report elsewhere on this Executive agenda. iii) Delegated authority... Decision page
Decision: RESOLVED KEY DECISION T hat Executive: i ) Approved the progression of the proposed scheme and to note that the scheme will be funded via S106 Funding and Basic Capital Grant Allocations funding received directly from central government; ii) Noted that budget approval £2.798m for the project is included within the Capital Programme Update report elsewhere on this Executive agenda. iii) Delegated authority to the Executive Member for Children, Families and Education in consultation with the... Decision page
Decision: RESOLVED KEY DECISION That Executive: i ) Approved the following changes into the capital programme totalling £9.696m: a. Isebrook SEND College expansion of school - increase of £341k to the capital programme for 2022/23, which is to be funded from the SEND Capital grant. b. Schools Minor Works programme – budget approval for £3.894m; £1.95m in 2023/24, £1.95m in 2024/25, which is to be funded from the DfE Schools Condition Allocation (SCA) grant. c. Kingswood Secondary School Bulge funding –... Decision page
Decision: RESOLVED That the Executive: a) Noted the Council’s forecast outturn position for 2022/23 as summarised in Section 4, alongside the further analysis, risks and other considerations as set out in Section 5 and Section 6 of the report. b) Noted the assessment of the current deliverability of the 2022/23 savings proposals in Appendix A of the report. c) Noted the release of the contingency budget, totalling £2.450m, to fund the pay award (£1.532m) and to partially mitigate the additional pressures... Decision page
Item 353 is where most of this meeting's papers sit: 2 papers, about 6.1 MB.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 46 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 10 November 2022. 8 of its items lead into this meeting; 8 items are new. Point at any item to follow a thread. Procedural items are left out.
Hackney Carriage Tariffs, UK Shared Prosperity Fund, Provision of Building Cleaning Services, Street Lighting LED Upgrade and 6 more do not return this time.
See the 10 November meetingEvery Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
North Northamptonshire, Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.