Agreed that (1) the Efficiency Savings Programme 2020/21 (Quarter 4) update be noted ; and (2) information in relation to the Youth Offending and Early Help target be provided.
Overview, Scrutiny & Policy Development Committee (no longer active) agreed this item on Wednesday 7 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that (1) the Efficiency Savings Programme 2020/21 (Quarter 4) update be noted ; and (2) information in relation to the Youth Offending and Early Help target be provided.
Efficiency Savings Programme 2020/21 Quarter 4 Report Contents Section Page
Executive Summary 3
Ready for School 5
Ready for Work and Life 7
Cared for, Safeguarded and Healthy 9
Great Place to Live, Work and Visit 15
Fit for Purpose Organisation 17
Maximising Resources 19
2 Executive Summary This is the 2020/21 Quarter 4 Progress Report summarising the delivery status of the Efficiency Savings Programme for the full year to 31 March 2021.
The overall savings requirement for the 2020/21 business cases agreed by Council in February 2020 is £3.622m. This is made up of £0.805m of business cases new to 2020/21, £1.346m for the impact of prior years’ on 2020/21 and £1.471m of business cases within Health, Education, Care and Safeguarding that were previous achieved by management actions that require permanent delivery in 2020/21.
The delivery of some of the savings proposals in 2020/21 were significantly impacted by the Covid-19 pandemic especially within Health, Education, Care and Safeguarding and Commissioning & Asset Management. All savings were fully achieved, however, when the impact of Covid-19 is taken into account.
This report shows the outcome of both the project work and the realisation of associated savings, broken down by the six key outcomes: Ready for School; Ready for Work and Life; Cared for, Safeguarded & Healthy; Great Place to Live, Work and Visit; Fit for Purpose Organisation; and Managing Resources.
The Q4 financial position at the end of the year is set out in the table below. All projected savings were fully achieved, given the impact of Covid-19 pandemic.
Service 2020/21 Delivery In Year Impacted Target Management By Covid Actions (grant funded) £m £m £m £m HECS 3.069 1.283 0.470 1.316 Commissioning & 0.249 0.167 0.000 0.082 Asset Management Environment 0.360 0.360 0.000 0.000 Housing & Leisure Central Items (0.056) (0.056) 0.000 0.000 TOTAL 3.622 1.754 0.470 1.398
£1.754m has been delivered against the overall target via project activities outlined in associated business cases; A further £0.470m was achieved as the direct result of management actions during the course of the financial year; £1.398m of the overall target was met as a result of Covid-19 grant funding.
3 As part of the Council’s programme management arrangements, all business cases and projects within the Efficiency Savings Programme are monitored on a regular basis. Each project is given a RAG rating for project delivery and savings delivery. The definitions and numbers of projects falling into those categories are shown in the table below.
Work Delivery Savings Delivery £m Blue All milestones complete 14 Blue Full saving realised 12 1.754 All milestones are forecasted to be met Saving achieved as a result of Green within timescales; no 2 Blue 2 0.470 management actions concerns about delivery of future milestones Some milestones delayed and/or minor concern Target achieved through Covid- Amber 4 Blue 9 1.398 about delivering some 19 grant income future milestones Milestones significantly delayed and/or major Red 3 concern about delivering future milestones Total Savings Target 3.622
All savings delivery targets are shown at the year end as having been achieved, by one of the three means shown above.
For comparative purposes, in the previous quarters, the relevant financial RAG ratings were as follows:
Blue Full saving realised and coded in the General Ledger
Green Full saving forecasted to be realised but not yet coded in the General Ledger.
Amber Projected shortfall in savings up to a value of £0.050m.
Red Projected shortfall in savings in excess of £0.050m
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
6b. ESP Update Report 2020-21 (Q4) /21Report | 792 KB | DownloadRead as text |
PDF |
Efficiency Savings Programme 2020/21 Quarter 4: Progress ReportReport | 33 KB | Download |
Follow Overview, Scrutiny & Policy Development Committee (no longer active) at North Tyneside and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2023 | Efficiency Savings Programme: 2022/23 Quarter 3: Progress ReportAgreed that the Efficiency Savings Programme: 2022/23 Quarter 3: Progress Report be noted. | Agreed | Open |
| 13 Mar 2023 | Annual Scrutiny ReportAgreed that the Overview and Scrutiny Annual report be approved and referred to the Annual Council meeting on 18 May ... | Agreed | Open |
| 16 Jan 2023 | Appointment of ChairAgreed that Members of the Committee present elected that Councillor J Kirwin to Chair the meeting. | Agreed | Open |
| 16 Jan 2023 | Technical Services Partnership - Capita UpdateAgreed that the Technical Services Partnership Q1 & Q2 22022-23 report be noted. | Agreed | Open |
| 16 Jan 2023 | Exclusion ResolutionResolved that under Section 100 A( 4) of the Local Government Act 1972 (as amended) and having applied a public inter... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.