Overview, Scrutiny & Policy Development Committee (no longer active) agreed this item on Monday 8 November 2021. Below is the council's own wording, with the papers it was decided on.
Agreed to (1) note the Efficiency Savings Programme Progress Report and (2) that future reports providing greater detail for each business case with associated timescales for those with Red/Amber rating and those areas of interest requested; and (3) where a business case hold a Red rating ensure officers are in attendance at meetings.
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
2 Executive Summary This is the 2021/22 Quarter 2 Progress Report summarising the delivery status of the Efficiency Savings Programme for the full year to 31 March 2022.
The overall savings requirement for 2021/22, agreed by Council in February 2021 is £4.537m. This is made up of £1.792m for the impact of prior year business cases on 2021/22 and £3.066m of business cases within Health, Education, Care and Safeguarding and Commissioning and Asset Management, that were previously achieved by management actions that require permanent delivery in 2021/22. There were no new business cases in 2021/22.
The delivery of some of the savings proposals in 2021/22 have been significantly impacted by the Covid-19 pandemic especially within Health, Education, Care and Safeguarding and Commissioning & Asset Management. All savings are forecasted to be fully achieved, however, when the impact of Covid-19 is taken into account.
This report shows the outcome of both the project work and the realisation of associated savings, broken down by the six key outcomes: Ready for School; Ready for Work and Life; Cared for, Safeguarded & Healthy; Great Place to Live, Work and Visit; Fit for Purpose Organisation; and Managing Resources.
The Q2 financial position at the end of September is set out in the table below. All projected shortfalls in savings achieved, are forecasted to be met through support from Covid-19 grants, given the impact of the Covid-19 pandemic on the ability to achieve the savings outright.
Service 2021/22 Delivery In Year Yet to be Target Management Achieved Actions
£2.080m has been delivered against the overall target via project activities outlined in associated business cases; A further £0.830m was achieved as the direct result of management actions during the course of the financial year; £1.627m of the overall target is yet to be achieved.
3 As part of the Authority’s programme management arrangements, all business cases and projects within the Efficiency Savings Programme are monitored on a regular basis. Each project is given a RAG rating for project delivery and savings delivery. The definitions and numbers of projects falling into those categories are shown in the table below.
Work Delivery Savings Delivery £m 4 Full saving realised and coded in 0 0.000 Blue All milestones complete Blue the General Ledger All milestones are forecasted to be met within 5 Full saving forecasted to be 8 2.080 Green timescales; no concerns Green realised but not yet coded in the about delivery of future General Ledger. milestones Some milestones delayed and/or minor concern about 3 Projected shortfall in savings up 2 0.035 Amber delivering some future Amber to a value of £0.050m. milestones Milestones significantly delayed and/or major 6 Projected shortfall in savings in 8 2.422 Red Red concern about delivering excess of £0.050m future milestones Total Savings Target 4.537
4 Ready for School Continue to Redesign 0-19 Services (2021/22 target: £0.025m) Starting with ante-natal services this proposal aims to continue our work to target our services at need and to manage demand for more specialist services. Critical to delivery will be the Healthy Child Programme and the work to increase the richness and consistency of the Early Help offer. This approach links to Government Policy and best practice through concentrating on prevention and developing more schools to deliver Early Years, which, in turn, saves money and avoids cost.
Savings from Full Year Effect of 2019/20 Saving £0.025m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview, Scrutiny & Policy Development Committee (no longer active) at North Tyneside and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.