North Tyneside Highway Asset Management Plan (HAMP) Annual Report 2025

Noted Executive 2 papers

AI summaryNorth Tyneside Cabinet noted the 2025 Highway Asset Management Plan annual report, covering 900km of roads and over 2,000km of footpaths, with more than £100 million invested since 2017 and an extra £2million per year continuing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet received the ninth HAMP annual report for information
MoneyOver £100 million invested since 2017Plus £2million per year additional council commitment
What happens nextReport to be published onlineWard councillors to view via members intranet
Who it affectsBorough residents and road usersUsers of 900km of roads and 2,000km of footpaths

What was decided

Cabinet noted the content of the Highway Asset Management Plan 2017 to 2032 Annual Information Report November 2025. Report P4

No decision was required as the item was presented for information only. Report P50, P52

Why

The HAMP includes a commitment to provide Cabinet with an annual information report on highway network maintenance and progress. Report P17, P1

Roads and pavements remain a priority for the Authority, Cabinet and the Elected Mayor, supported by an extra £2million per year. Report P2, P3

What happens next

The HAMP Annual Information Report will be published on the Authority's website for the public. Report P39

All ward councillors will be invited to view the report via the members intranet. Report P39

Investment and prioritisation options will be reviewed as part of medium-term financial planning and the Investment Plan process. Report P62

The money

  • £2million per annum Additional annual council and Mayoral investment in roads and pavements Report P2, P3, P26, P27
  • over £100 million Total invested in maintenance and improvement works since 2017 Report P18
  • £1.253m 2025/26 Local Transport Plan Maintenance Block allocation Report P22
  • £313k 2025/26 Highway Maintenance Incentive Fund allocation Report P23
  • £1.253m 2025/26 Pothole Fund allocation Report P24
  • £1.171m 2025/26 Department for Transport Uplift Funding allocation Report P25
  • £537,000 2025/26 City Region Sustainable Transport Settlement from NECA Report P28
  • £10million Government grant ringfenced for the Seafront Sustainable Route cycling and walking scheme Report P29
  • £1m Sustrans contribution to the Seafront Sustainable Route Report P29
  • £11m Cost of the seafront sustainable cycling and walking route completed in July 2025 Report P33
  • £1,520,000,000 (£1.52 billion) Current total value of highway assets on a Gross Replacement Cost basis Report P42

Options considered

  • Chosen: Receive and note the HAMP Annual Information Report 2025. Cabinet was not being asked to make a decision but simply to receive the report Report P4, P50, P52

Implications

  • Financial: No immediate financial implications arise from the report, but long-term funding pressures and inflation in the construction supply chain may affect future maintenance. Report P62, P32, P34
  • Financial: There is a risk that current funding trends will make it difficult to sustain the condition of the network in future years. Report P34
  • Legal: The Authority has a statutory duty to maintain the highway under section 41 of the Highways Act 1980 and a network management duty under Part 2 of the Traffic Management Act 2004. Report P64, P65
  • Equalities: Works include installing dropped kerbs to improve accessibility for people with mobility difficulties, wheelchair users and pushchair users, with an Equalities Impact Assessment carried out for every scheme. Report P71
  • Climate: The Highways Service seeks to use sustainable construction methods to support the Authority's Carbon Net-Zero 2030 Action Plan, including drainage works to improve flood resilience. Report P76
  • Staffing: Core highways services returned to the Authority from the Capita Technical Partnership on 1 January 2025, with reintegration work ongoing. Report P35, P46

Who and where

  • Residents of North Tyneside who travel on or maintain the highway network Report P17, P42
  • Visitors and businesses using the borough's roads and tourist attractions Report P42
  • Ward councillors receiving the report via the members intranet Report P39
  • Walking, cycling and active travel users, including users of the new seafront route Report P10, P33

Timeline

  • September 2017: Cabinet adopted the updated Highway Asset Management Plan 2017 to 2032 Report P16
  • May 2024: North East Combined Authority (NECA) was formed Report P36
  • 1 January 2025: Core highway services returned to the Authority from the Capita Technical Partnership Report P35
  • July 2025: Completion of the £11m seafront sustainable cycling and walking route Report P33
  • 19 September 2025: Report first appeared on the Forward Plan Report P6
  • November 2025: HAMP Annual Information Report published as appendix to Cabinet report Report P1, P54
  • 2025-11-24: Cabinet meeting to note the report

Plain English for the jargon

  • HAMP: Highway Asset Management Plan, covering 2017 to 2032
  • NECA: North East Combined Authority, administrator of external highway maintenance grants from May 2024
  • LTP: Local Transport Plan, the source of the annual Maintenance Block government grant
  • DfT Uplift Funding: Additional central government roads funding allocated in 2025/26
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB63/25

Resolved

RESOLVED to: 1. Note the content of the Highway Asset Management Plan (HAMP) 2017 to 2032 Annual Information Report November 2025. Reason for the DECISION: No alternative options have been outlined as Cabinet is not being asked to make a decision but to simply receive the HAMP Annual Information Report 2025.
Word for word from the decision North Tyneside published for this meeting. Source: democracy.northtyneside.gov.uk

Follow this further

Built from North Tyneside's papers

What the report saysPro

Report to Cabinet

Executive summary

The purpose of this report is to present the Highway Asset Management Plan (HAMP) 2017 to 2032 Annual Information Report November 2025 to Cabinet. This fulfils the commitment to provide Cabinet with an annual information report outlining the highway and infrastructure work undertaken across the Borough over the last 12 months. It includes work activities undertaken as well as other items of relevant interest. The annual information report attached to this report is the ninth annual report presented since adoption of the HAMP.

Roads and pavements continue to be a priority of the Authority, Cabinet and the Elected Mayor. The addition of an extra £2million per annum continues to

1 support the Authority’s efforts in maintaining the network in respect of roads and pavements.

Recommendation

It is recommended that Cabinet receive and note the content of the Highway Asset Management Plan (HAMP) 2017 to 2032 Annual Information Report November 2025, appended this report.

1.3Forward Plan:

Twenty-eight days’ notice of this report has been given, and it first appeared on the Forward Plan that was published on 19 September 2025.

1.4Council Plan and Policy Framework

The proposals in this report relate to a number of themes in Our North Tyneside, the Council Plan 2021 to 2025, in particular:

• A secure North Tyneside ➢ We will continue to invest £2m per year in addition to the government grant funding on fixing our roads and pavements

• A green North Tyneside ➢ We will increase opportunities for safe walking and cycling, including providing a segregated cycleway at the coast

• A thriving North Tyneside ➢ We will review how the council purchases and contracts for goods and services to maximise value for money, social value and environmental sustainability

In accordance with the Authority’s Constitution and Budget and Policy Framework Procedure Rules, the Authority has commenced the process to develop a new Council Plan for the period 2025-2029. The new Council Plan will be based on the following five ambitions: -

1. Better lives for all - a healthier, fairer and better quality of life, where everyone can thrive 2 2. Best start in life – giving our children and young people what they need to achieve their full potential 3. Places to be proud of – building neighbourhoods and town centres that are clean, green and safe and make North Tyneside a great place to live 4. Good work for all and economic growth – helping create more good quality jobs and strong economic growth 5. Housing and neighbourhoods that enhance lives – delivering more affordable and social housing and creating neighbourhoods we’re proud to call home

This report links to Ambitions 3 and 4 as well as contributing to several other priorities.

1.5Information:

Background

1.5.1 In September 2017, Cabinet adopted an updated Highway Asset Management Plan 2017 - 2032 (HAMP). The HAMP sets out the Authority’s approach to maintaining the highways for which it is responsible over a 15-year period. It delivers against Cabinet’s policy priority to place a greater emphasis on footways to help support walking and other means of active travel. It also responds to feedback from residents which has consistently told the Authority that the maintenance of roads and footpaths should be a high priority. This is reflected in the Authority’s Investment Plan which includes a commitment to invest additional capital funding in repairing roads and pavements, beyond the levels of external capital grant funding the Authority receives. A well- maintained highway network is vital for supporting the local economy and general wellbeing of the Borough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HAMP Annual Info Report 2025 DRAFT /25Appendix 1 2.8 MB Download
PDF
North Tyneside Highway Asset Management Plan (HAMP) Annual Report 2025Report 82 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 26 attended
MK
Mayor Karen ClarkElected Mayor, present
CJ
Councillor Carl JohnsonDeputy Mayor, present
PE
Councillor Peter EarleyCommittee Member, present
SG
Councillor Sandra GrahamCommittee Member, present
JH
Councillor John HarrisonCommittee Member, present
JH
Councillor Janet HunterCommittee Member, present
HJ
Councillor Hannah JohnsonCommittee Member, present
AM
Councillor Anthony McMullenCommittee Member, present
SP
Councillor Steven PhillipsCommittee Member, present
JW
Councillor Joan WalkerCommittee Member, present
RL
Roger LaytonGuest, in attendance
VS
Vicky SmithGuest, in attendance

All 26 on the meeting page

On this subject at North Tyneside

Search all
  1. North Tyneside Highway Asset Management Plan (HAMP) Annual Report 2025This decision
  2. North Tyneside Carbon Net-Zero Action Plan Update (2026)Agreed
  3. North Tyneside Local Plan Publication Draft and SubmissionApproved
  4. Healthwatch North Tyneside Annual ReportNoted
  5. Our North Tyneside Plan 2025-2029 – Annual ReportNoted
  6. North Tyneside Local Plan Consultation Initial ProposalsApproved

More from North Tyneside Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 North Tyneside Carbon Net-Zero Action Plan Update (2026)Agreeing this decision will support the ongoing delivery of the Authority’s ambitious net-zero programmes and will co... Agreed Open
21 Sep 2026 Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of... Noted Open
21 Sep 2026 North Tyneside Local Plan Publication Draft and SubmissionThe Authority has a statutory duty to prepare and keep up to date a development plan for the strategic development an... Approved Open
21 Sep 2026 No Detriment Financial Support Policy for Kinship Carers Transitioning to Special Guardianship Orders (SGOs)The decision is recommended for the following reasons: · It promotes permanence and stability for children living wit... Decided Open
21 Sep 2026 Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies