Cabinet, Monday 24 November 2025 at 6.00pm

2025/26 Performance and Financial Management Report to 30 September 2025

Noted Executive 6 papers

AI summaryNorth Tyneside Cabinet noted a £9.863m forecast revenue overspend for 2025/26 and approved £11.520m of investment plan reprogramming, £0.273m of new revenue grants and £1.526m of new capital grants.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSix recommendations noted or approved
Money£9.863m forecast overspendDown from £12.291m previously reported
What happens nextContinued monitoring by SLTBi-monthly budget monitoring to Cabinet
Who it affectsAuthority services, residents, schoolsParticularly Children's and Adult Services

What was decided

Cabinet noted the performance update and forecast budget monitoring position for the General Fund, Housing Revenue Account, schools finance and Treasury Management as at 30 September 2025. Report P16, P17

Cabinet approved reprogramming of £11.520m of 2025/26 investment plan into future years and variations of £2.616m within the 2025 to 2030 Investment Plan, and noted the position on Developers' Contributions. Report P19

Cabinet approved receipt of £0.273m of new revenue grants and £1.526m of new capital grants. Report P20, P21

Why

It is important that the Authority continues to monitor performance against the budget given the current level of financial pressures faced by the public sector. Report P85

It is also important that the Authority agrees to receive the revenue and capital grants referred to in the report. Report P85

What happens next

The Senior Leadership Team will continue to work with Cabinet and senior officers to update the 2025 to 2029 Medium Term Financial Plan workstreams and progress in-year mitigations to support the 2025/26 position. Report P42

Three Medium Term Financial Plan projects rated Red will continue to be actively worked on to mitigate the risk of not achieving in-year savings targets. Report P70, P71, P72, P73, P74

Consultation results on the 2026/27 Local Funding Formula will be used once the Department for Education publishes notional Schools and High Needs National Funding Formula allocations. Report P44

The money

  • £9.863m Forecast General Fund revenue overspend for 2025/26 as at 30 September 2025 Report P8, P41
  • £31.376m Investment Plan spend to 30 September 2025 Report P18, P53
  • £11.520m Reprogramming of 2025/26 investment plan into future years Report P19, P52
  • £2.616m Variations within the 2025 to 2030 Investment Plan Report P19, P12
  • £0.273m New revenue grants received up to end September 2025 Report P20, P68
  • £1.526m New capital grants received up to end September 2025 Report P21, P69
  • £9.700m Forecast pressure within Children's Services Report P30, P41
  • £0.018m Forecast Housing Revenue Account underspend for 2025/26 Report P14, P50

Options considered

  • Chosen: Option 1: Cabinet agrees the recommendations at section 1.2 of the report. It is important that Cabinet continues to monitor performance against the Budget given the level of financial pressures faced by the public sector, and agrees to receive the revenue and capital grants. Report P79, P80, P84, P85
  • Rejected: Option 2: Cabinet does not agree the recommendations at section 1.2 of the report Report P81, P82

Implications

  • Financial: A £9.863m forecast overspend for 2025/26 remains a significant risk, though improved from £12.291m previously reported. Three Medium Term Financial Plan projects are rated Red. Report P8, P11, P70, P71
  • Legal: The Authority has a duty under the Local Government Act 2003 to ensure it can deliver a balanced budget and to monitor its budgets during the year, considering action if potential deterioration is identified. Report 2.2
  • Equalities: There are no direct equalities and diversity implications arising from this report. Report P107
  • Risk: Potential future financial pressures are covered in this report and registered through the Authority's risk management process. Report P108
  • Staffing: Reliance on agency staff to cover vacant social work posts continues, and further savings are required in the People and Workforce Medium Term Financial Plan project after initial savings from the Voluntary Redundancy programme. Report P32, P73
  • Other: There are no direct environmental and sustainability implications, no direct Human Rights Act 1998 implications, and no crime and disorder implications directly arising from this report. Report P105, P110, P112

Who and where

  • Children in the Authority's care, including those placed in external children's homes Report P30, P31
  • Adult social care service users and providers Report P35, P36
  • Schools across the Borough, including those with budget deficits Report P43
  • Council housing tenants, including those moving to Universal Credit Report P48, P49
  • Residents and businesses receiving council services funded by the Investment Plan Report P55, P56, P57, P58, P59

Timeline

  • 30 July 2025: Report first appeared on the Forward Plan Report P23
  • September 2025: Revised Home to School Transport Policy and Annual Post 16 Transport Policy Statement implemented Report P34, P75
  • 30 September 2025: Reporting date for financial and performance position Report P1
  • 7 October 2025 to 24 October 2025: Consultation with schools on the 2026/27 Local Funding Formula Report P44
  • By March 2026: Introduction of food waste collection under the Environment Act 2021 Report P7
  • By March 2027: Introduction of soft plastics recycling collection Report P7
  • 2027/28: Target date for high needs expenditure to return to in-year balance under the Safety Valve programme Report P4, P45

Plain English for the jargon

  • MTFP: Medium Term Financial Plan, the council's multi-year financial planning and savings programme
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
  • DfE: Department for Education
  • DSG: Dedicated Schools Grant, the ring-fenced funding for schools
  • Safety Valve: Department for Education intervention programme for high needs funding pressures, with the aim of achieving an in-year balance by 2027/28
  • EHCP: Education, Health and Care Plan, a plan for children and young people with special educational needs and disabilities
  • SRMA: Schools Resource Management Advisors, Department for Education support for schools with budget pressures
  • S106: Section 106 planning obligations, contributions from developers towards local infrastructure
  • CIL: Community Infrastructure Levy, a charge on new development to fund infrastructure
  • UKSPF: UK Shared Prosperity Fund, central government funding for local growth
  • SLT: Senior Leadership Team of senior council officers
  • CIPFA: Chartered Institute of Public Finance and Accountancy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB60/25

Resolved

RESOLVED to: 1. Note the update provided on the Performance of the Authority including updated data on the key pressures facing the Authority; 2. Note the forecast budget monitoring position for the General Fund, Housing Revenue Account, schools finance and Treasury Management as at 30 September 2025; 3. Note the Authority’s Investment Plan spend of £31.376m to 30 September 2025 and the proposed financing of the Plan to the end of the year; 4. Approve reprogramming of £11.520m of the 2025/26 investment plan into future years and variations of £2.616m within the 2025-2030 Investment Plan and note the current position with Developers’ Contributions; 5. Approve the receipt of £0.273m new revenue grants; and 6. Approve the receipt of £1.526m of capital grants. Reason for the DECISION: It is important that the Authority continues to monitor performance against the Budget, especially given the current level of financial pressures faced by the public sector. It is also important that the Authority agrees to receive the revenue and capital grants.
Word for word from the decision North Tyneside published for this meeting. Source: democracy.northtyneside.gov.uk

Follow this further

Built from North Tyneside's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1.1 This report provides Cabinet with an overview of both service performance and financial position across the Authority as at 30 September 2025. It sets out the key areas of service delivery for Cabinet to note, including where this impacts in budgetary terms, and shows the forecast outturn position to 31 March 2026 for both revenue and capital.

1.1.2 The report also sets out the forecast outturn position in relation to schools’ finance, the Authority’s Investment Plan, developers’ contributions, treasury management and prudential indicators. In addition, it provides details of additional revenue and capital grants received up until 30 September 2025 for Cabinet to approve.

1.1.3 In terms of service performance, the Affordable Homes Programme is progressing well and has delivered 2,504 affordable homes at the end of quarter two. The programme is on track to deliver 206 affordable homes in year.

1.1.4 Good progress is being made to deliver Inclusive Education/Special Educational Needs and Disabilities initiatives as part of the Department for Education (DfE) Safety Valve Intervention Programme and annual growth of Education, Health and Care Plans remains lower than before the Authority joined the programme and performance is better than national and regional comparators. Whilst there is a variance from the original Safety Valve plan, the Department for Education (DfE) has confirmed their agreement with a remodelled submission of the plan which still sees high needs expenditure return to an in-year balance by 2027/28, but that further work will be required to address the cumulative breakeven position by that date.

1.1.5 North Tyneside is comparatively one of the safest places in the country. Anti-social behaviour has decreased by 28% compared to last year, whereas crime remains consistent and significantly lower than the average Northumbria Police Force Area crime rate.

1.1.6 The proportion of 16-17 year olds not in Education, Employment or Training remains low at 2.7% and is significantly better than the North-East average (5.6%) and the average for England (3.8%). Overall and persistent absence from school significantly decreased during 2024/25 academic year and remains consistent at the start of the 2025/26 academic year. Suspensions and permanent exclusions increased during the 2024/25 academic year.

1.1.7 The proportion of waste recycled, reused and composted has dipped in the first quarter of this year, largely attributable to a reduction in composting. The Environment Act 2021 brings more consistency around recycling collections across all local authorities. For North Tyneside, this will include the introduction of a food waste collection by March 2026 and soft plastics by March 2027. The collection of more recycling materials will increase the proportion of waste recycled, reused and composted. In addition, the “Wash, Squash and Recycle” Campaign continues to raise awareness and promotes participation in recycling, reuse and composting across North Tyneside.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Performance and Financial Management Report to 30 September 2025Report 114 KB DownloadRead as text
PDF
Performance and Financial Management Report /25Appendix 1 3.4 MB Download
PDF
forecast to 30 September: Forecast Financial Summary /25Appendix 2 443 KB Download
PDF
MTFP Project Highlight Reports Aug- Sept /25Appendix 03 567 KB Download
PDF
2025-2030 Investment Plan Summary Sept 2025 /25Appendix 1 521 KB Download
PDF
Section 106 Summary and Balances to 30 September 2025 /25Appendix 2 415 KB Download

At this meeting

Whole meeting

Who was there

10 of 26 attended
MK
Mayor Karen ClarkElected Mayor, present
CJ
Councillor Carl JohnsonDeputy Mayor, present
PE
Councillor Peter EarleyCommittee Member, present
SG
Councillor Sandra GrahamCommittee Member, present
JH
Councillor John HarrisonCommittee Member, present
JH
Councillor Janet HunterCommittee Member, present
HJ
Councillor Hannah JohnsonCommittee Member, present
AM
Councillor Anthony McMullenCommittee Member, present
SP
Councillor Steven PhillipsCommittee Member, present
JW
Councillor Joan WalkerCommittee Member, present
RL
Roger LaytonGuest, in attendance
VS
Vicky SmithGuest, in attendance

All 26 on the meeting page

On this subject at North Tyneside

Search all
  1. 2025/26 Performance and Financial Management Report to 30 September 2025This decision
  2. 2026/27 Performance and Financial Management Report to 30th June 2026Decided
  3. 2025/26 Performance and Financial Management Report to 31st March 2026Agreed
  4. 2025/26 Performance and Financial Management Report to 31st January 2026Noted
  5. 2025/26 Performance and Financial Management Report to 30 November 2025Noted
  6. 2025/26 Performance & Financial Management Report to 31 July 2025Agreed

More from North Tyneside Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 North Tyneside Carbon Net-Zero Action Plan Update (2026)Agreeing this decision will support the ongoing delivery of the Authority’s ambitious net-zero programmes and will co... Agreed Open
21 Sep 2026 Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of... Noted Open
21 Sep 2026 North Tyneside Local Plan Publication Draft and SubmissionThe Authority has a statutory duty to prepare and keep up to date a development plan for the strategic development an... Approved Open
21 Sep 2026 No Detriment Financial Support Policy for Kinship Carers Transitioning to Special Guardianship Orders (SGOs)The decision is recommended for the following reasons: · It promotes permanence and stability for children living wit... Decided Open
21 Sep 2026 Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th... Noted Open