Cabinet, Monday 22 June 2026 at 6.00pm

2025/26 Performance and Financial Management Report to 31st March 2026

Agreed Executive 7 papers

AI summaryNorth Tyneside Cabinet notes 2025/26 outturn of £1.115m overspend, approves £11.812m investment plan reprogramming, £0.383m new revenue and £3.841m new capital grants.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed£1.115m overspend, funded from Strategic Reserve
Money£1.115m overspend, £90.508m investment plan spendStrategic Reserve balance £4.885m after transfer
What happens nextStatement of Accounts by 30 June 2026Statutory publication deadline
Who it affectsCouncil services, schools, HRA tenantsChildren's Services, Adult Services, Environment, schools, housing

What was decided

Cabinet noted the outturn position for 2025/26, including a £1.115m overspend funded by a transfer from the Strategic Reserve, leaving the General Fund in balance. Report P6, P11, P37

Cabinet approved reprogramming of £11.812m of 2025/26 Investment Plan spend into future years and variations of £0.167m within the 2025-2030 Plan, with £90.508m spent by 31 March 2026. Report P12, P13, P50, P51

Cabinet approved receipt of £0.383m new revenue grants and £3.841m new capital grants, plus write-offs of unrecoverable debt. Report P14, P15, P65, P66, P67

Why

The Authority has a statutory duty under the Local Government Act 2003 to monitor its budgets and ensure a balanced budget. Report P93

Cabinet must continue to monitor performance against the Budget given current public sector financial pressures, and must accept revenue and capital grants referred to in the report. Report P78

The improved position reflects restraint on non-essential spend, maximised income and a £6.600m one-off dividend from Newcastle International Airport that offset in-year pressures, particularly in social care. Report P4, P5, P30

What happens next

The Authority will prepare and publish its draft 2025/26 Statement of Accounts by 30 June 2026. Report P3

Maintained schools must submit 2026/27 three-year budget plans to the Authority by 31 May 2026, and the Authority will continue to work with deficit schools on recovery plans. Report P42

Work on the 14 MTFP workstreams will continue into 2026/27, with the Strategic Reserve to be further increased in 2026/27. Report P8, P37

The money

  • £1.115m 2025/26 General Fund overspend, funded from Strategic Reserve Report P4, P6, P37
  • £4.355m Improvement in overspend since January 2026 forecast Report P4
  • £6.600m One-off dividend from Newcastle International Airport shareholding Report P5, P30
  • £4.885m Strategic Reserve balance after 2025/26 transfer (net increase of £0.385m) Report P6
  • £90.508m Investment Plan spend to 31 March 2026 Report P12, P51
  • £11.812m Reprogramming of 2025/26 Investment Plan into future years Report P13, P50
  • £0.167m Variations within 2025-2030 Investment Plan Report P13
  • £0.383m New revenue grants received to 31 March 2026 Report P14, P65
  • £3.841m New capital grant (Bus Service Improvement Plan) Report P14, P66, P67
  • £10.064m Children's Services directorate overspend Report P23
  • £2.159m Adult Services directorate overspend Report P28
  • £1.520m Environmental services underspend Report P29
  • £0.034m Housing Revenue Account small underspend Report P47
  • £7.716m Closing collective deficit of Authority maintained schools Report P40
  • £13.545m High Needs block cumulative DSG deficit, including final £1.950m Safety Valve instalment Report P42
  • £520.443m External borrowing at 31 March 2026 (excluding PFI) Report P58
  • £8.880m Total treasury investments at 31 March 2026 Report P59
  • £28.942m Section 106 contributions received to date Report P61
  • £4.016m Community Infrastructure Levy funding received to date Report P62

Options considered

  • Chosen: Cabinet agrees the recommendations (notes outturn, approves reprogramming, grants and write-offs). Recommended to ensure continued budget monitoring and acceptance of grants, given current public sector financial pressures and the statutory duty to deliver a balanced budget Report P72, P73, P77, P78, P93
  • Rejected: Cabinet does not agree the recommendations. No reason given in the report Report P74, P75

Implications

  • Financial: A £1.115m unplanned use of the Strategic Reserve in 2025/26 leaves a balance of £4.885m, with planned further increases in 2026/27. Report P6, P37
  • Financial: Without the one-off £6.600m Newcastle International Airport dividend, the 2025/26 overspend would have been around £7.7m. Report P30
  • Financial: Three MTFP workstreams (Children's Finance, People and Workforce, Commissioning) are delayed with savings not fully achieved. Report P8
  • Legal: The Authority must publish its draft 2025/26 Statement of Accounts by 30 June 2026, a statutory requirement. Report P3, P93
  • Equalities: There are no direct equalities and diversity implications from this report. Report P101
  • Risk: Potential future financial pressures are registered through the Authority's risk management process. Report P102
  • Other: The Department for Education's Safety Valve programme ends 1 April 2026; a new High Needs Stability Grant will cover 90% of historic and accruing DSG deficits, subject to approval of the local SEND Reform Plan. Report P42

Who and where

  • Children's Services, with 419 children in care and 50 placed in external children's homes costing £9.592m Report P23
  • Adult Services users, with continued demand and complexity of care pressures Report P28
  • Authority maintained schools, with a collective deficit of £7.716m and 25 of 57 schools in cumulative deficit; Monkseaton High School to close in July 2026 with a £6.682m cumulative deficit Report P40, P41
  • Housing Revenue Account tenants, with rent collection at 94.12% and rising arrears linked to Universal Credit migration Report P45, P46
  • Residents receiving home to school transport (844 pupils in March 2026) Report P27
  • Children and young people with EHCPs, totalling 2,714 at end of March 2026 (16% increase) Report P43

Timeline

  • 31 March 2026: End of 2025/26 financial year; outturn position reported Report P1, P4
  • 1 April 2026: DfE Safety Valve programme ends; High Needs Stability Grant begins Report P42
  • 31 May 2026: Maintained schools to submit 2026/27 three-year budget plans Report P42
  • 30 June 2026: Deadline for publication of draft 2025/26 Statement of Accounts Report P3
  • July 2026: Planned closure of Monkseaton High School Report P41
  • 2026/27: Strategic Reserve to be further increased; MTFP workstreams continue Report P8, P37

Plain English for the jargon

  • General Fund: The council's main revenue account for day-to-day services, separate from the Housing Revenue Account.
  • Strategic Reserve: An earmarked reserve held to manage in-year financial pressures; balance of £4.885m after 2025/26 transfer.
  • MTFP: Medium Term Financial Plan, the council's multi-year savings and budget programme, here covering 2025-2029 with 14 workstreams.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing rents and services.
  • DSG / High Needs block: Dedicated Schools Grant funding for SEND and alternative provision; the High Needs block ended 2025/26 with a £13.545m cumulative deficit.
  • Safety Valve: Department for Education programme for high-need deficits, ending 1 April 2026 and replaced by a High Needs Stability Grant.
  • PFI: Private Finance Initiative, a long-term contract where private firms build and operate assets; £7.8m of payments are transferred to capital financing lines.
  • Section 106 / CIL: Developer contributions towards local infrastructure; £28.942m of Section 106 and £4.016m of CIL received to date.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, which sets treasury and prudential standards for local authorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB15/26

Resolved

It is important that Cabinet continues to monitor performance against the Budget, especially given the current level of financial pressures faced by the public sector. It is also important that Cabinet agrees to receive the revenue and capital grants referred to in the report.
Word for word from the decision North Tyneside published for this meeting. Source: democracy.northtyneside.gov.uk

Follow this further

Built from North Tyneside's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1.1 This report provides Cabinet with an overview of both service performance and financial outturn position for 2025/26 across the Authority. It sets out the key areas of service delivery for Cabinet to note, including where this impacts in budgetary terms, and shows the outturn position to 31 March 2026 for both revenue and capital.

1.1.2 The report also sets out the outturn position in relation to schools’ finance, the Authority’s Investment Plan, the Housing Revenue Account, developers’ contributions, treasury management and prudential indicators, which remain broadly in line with previous reports. In addition, it provides details of additional revenue and capital grants received up until 31 March 2026 for Cabinet to approve.

1.1.3 The Authority is preparing its draft Statement of Accounts for 2025/26 which must be published by 30 June 2026. The Statement of Accounts is a statutory document that sets out the Authority’s financial position in a series of formal statements prepared according to a specific statutory and regulatory framework, which makes it a very technical document and the reported position includes a number of accounting adjustments. As in previous years, this report sets out the Authority’s financial performance in an outturn report which reflects the Authority’s structure and the reports presented to Cabinet throughout the year.

1.1.4 The Authority ended the 2025/26 financial year with an overspend of £1.115m as at 31 March 2026, an improvement of £4.355m since the forecast in the last Cabinet report. This significant improvement since January 2026 reflects the continued drive to minimise non-essential spend and maximise income to offset the main areas of pressure, the most significant of which remain linked to social care.

1.1.5 Whilst the Authority continues to identify and deliver sustainable savings as part of the Medium-Term Financial Plan and Plan for Change programme, during 2025/26 the Authority also received a significant one-off dividend payable to shareholders of Newcastle International Airport which was £6.600m and this helped to significantly reduced the in-year pressure.

1.1.6 As previously reported, any overspend needs to be funded through the use of reserves. This report sets out the proposed release of £1.115m from the Strategic Reserve to support the year end position. After this transfer, the General Fund will be in balance for 2025/26. This means that the Strategic Reserve has a balance as at 31 March 2025 of £4.885m, representing a net increase of £0.385m during the year with further increases planned throughout the MTFP.

1.1.7 This report outlines the main drivers of the variance, the mitigating actions which drove the improved position, and the achievement of planned in-year savings. Good progress continues to be made on delivering the MTFP savings and the majority of savings included in the budget for 2025/26 were achieved. The continued challenge to review and halt non-essential expenditure throughout 2025/26 has helped the Authority continue to manage significant financial pressures, consistent with the broader local government sector.

1.1.8 Over £14m of savings were identified for 2025/26 as part of the 2025-2029 MTFP with 14 separate workstreams, all of which will continue into 2026/27. Challenges remain in MTFP 07 - Handling Children’s Finance, MTFP 12 – People and Workforce and MTFP 14 – Commissioning, with savings being delayed and costs continuing to increase. A summary of the progress is set out in Appendix 3.

Recommendations

It is recommended that Cabinet:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Performance and Financial Management Report to 31st March 2026Report 116 KB DownloadRead as text
PDF
Perf and Financial Mgmt Report /26Appendix 1 4.3 MB Download
PDF
outturn: Outturn Financial Summary /26Appendix 2 332 KB Download
PDF
MTFP Project Highlight Report /26Appendix 03 659 KB Download
PDF
2025-2030 Investment Plan Summary 31 March 2026 /26Appendix 1 398 KB Download
PDF
2025-26 Prudential Indicators /26Appendix 4 355 KB Download
PDF
Section 106 Summary /26Appendix 2 410 KB Download

At this meeting

Whole meeting

Who was there

9 of 23 attended
MK
Mayor Karen ClarkElected Mayor, present
CJ
Councillor Carl JohnsonDeputy Mayor, present
PE
Councillor Peter EarleyCommittee Member, present
JH
Councillor John HarrisonCommittee Member, apologies
JH
Councillor Janet HunterCommittee Member, present
HJ
Councillor Hannah JohnsonCommittee Member, present
RL
Roger LaytonGuest, in attendance
DM
Dawn McNallyGuest, in attendance
JB
John BartonOfficer, expected
SB
Stephen BallantyneOfficer, expected
DM
David MasonOfficer, expected
JR
Jon RitchieOfficer, expected

All 23 on the meeting page

On this subject at North Tyneside

Search all
  1. 2025/26 Performance and Financial Management Report to 31st March 2026This decision
  2. 2026/27 Performance and Financial Management Report to 30th June 2026Decided
  3. 2025/26 Performance and Financial Management Report to 31st January 2026Noted
  4. 2025/26 Performance and Financial Management Report to 30 November 2025Noted
  5. 2025/26 Performance and Financial Management Report to 30 September 2025Noted
  6. 2025/26 Performance & Financial Management Report to 31 July 2025Agreed

More from North Tyneside Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 North Tyneside Carbon Net-Zero Action Plan Update (2026)Agreeing this decision will support the ongoing delivery of the Authority’s ambitious net-zero programmes and will co... Agreed Open
21 Sep 2026 Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of... Noted Open
21 Sep 2026 North Tyneside Local Plan Publication Draft and SubmissionThe Authority has a statutory duty to prepare and keep up to date a development plan for the strategic development an... Approved Open
21 Sep 2026 No Detriment Financial Support Policy for Kinship Carers Transitioning to Special Guardianship Orders (SGOs)The decision is recommended for the following reasons: · It promotes permanence and stability for children living wit... Decided Open
21 Sep 2026 Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th... Noted Open