Resolved
To ensure the Mobile Working Programme is delivered in an effective and efficient manner.
Cabinet decided this item on Tuesday 10 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
To ensure the Mobile Working Programme is delivered in an effective and efficient manner.
NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL
CABINET – 10 DECEMBER 2013
INTRODUCTION OF MOBILE WORKING WITHIN THE Title of report HOUSING SERVICE
a) Financial Yes Key Decision b) Community Yes
Councillor Roger Bayliss 01530 411055 [email protected]
Director of Services Contacts 01530 454555 [email protected]
Head of Housing 01530 454780 [email protected]
To ask Cabinet to waive Contract Procedure Rule 5 and delegate Purpose of report authority for the award of contract to the Director of Services.
To ensure the Mobile Working Programme is delivered in an Reason for Decision effective and efficient manner.
Value for Money Council Priorities Homes and Communities Green Footprints Challenge
Implications:
Financial implications can be met within existing budgets. There is Financial/Staff no impact on staffing
Link to relevant CAT Improving Customer Experience
The report addresses the proper procurement of a contract to provide a scheduling system for the Repairs Management Team. Risk Management Without such a system the Council’s spend on third party repairs contracts will continue to grow and the reduction in repairs costs as a result of the Decent Homes Investment Program will not be fully realised.
Equalities Impact Not applicable Assessment
Human Rights No human rights implications are apparent. This relates to the new ways in which councils are being asked to Transformational deliver their services. The approach to tendering for this service Government represents procurement best practice and will deliver optimum value for money.
Comments of Head of The report is satisfactory. Paid Service
Comments of Section The report is satisfactory. 151 Officer
Comments of Monitoring The report is satisfactory. Officer
Consultees Procurement Team, Legal Services, Housing Team
Background papers None.
THAT CABINET:
(1) WAIVES CONTRACT PROCEDURE RULE 5 FOR THE PURPOSES OF THIS PROCUREMENT; AND Recommendations (2) DELEGATES THE AWARD OF THE CONTRACT FOR MOBILE WORKING TO THE DIRECTOR OF SERVICES IN CONSULTATION WITH THE PORTFOLIO HOLDER
1.0BACKGROUND.
1.1Optimised or dynamic scheduling is being increasingly utilised by local authorities and housing associations operating in-house repairs teams. Currently we use paper job tickets which are collected and returned on a weekly basis severely restricting our ability to deliver an efficient service for our customers.
1.2Designed to deliver efficiencies within the scheduling of appointments, it also reduces non productive time by minimising the time and cost repairs officers spend travelling between appointments as well as simplifying the ordering of parts.
1.3In turn this delivers a much improved service to customers as well as vastly improved management information.
1.4The resulting efficiency savings will reduce the additional costs incurred using Lakers who are a third party external repairs contractor used by the Council as additional resource to help deliver the right service to our customers as well as specialised jobs such as asbestos removal and drainage works.
1.5Although Housing will initially benefit from mobile working it is expected that this will expedite mobile working technology within other functions and services offered by the Council and in support of ICE (Improving Customer Experience) work stream. 2.0 PROCUREMENT APPROACH
2.1At the beginning of 2013 a Prior Information Notice was placed in the Official Journal of the European Union, following which the Council received 15 expressions of interest. Based on Council requirements and needs, of these 15, two contractors were identified as being able to provide an appropriate solution. Capita, who operate our Housing Management System OPENHousing, working in partnership with Totalmobile Xmbrace DRS and Oneserve Ltd.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Introduction of Mobile Working Within the Housing ServiceMinutes | 32 KB | DownloadRead as text |
Follow Cabinet at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... | Approved | Open |
| 22 Sep 2026 | Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... | Noted | Open |
| 22 Sep 2026 | Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... | Noted | Open |
| 22 Sep 2026 | Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... | Agreed | Open |
| 22 Sep 2026 | Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.