North West Leicestershire District Council
Cabinet, Tuesday 22 September 2026 at 5.00pm

Consultancy Services for the Local Plan

Approved Executive 2 papers

AI summaryCabinet approved awarding the Phase 2 Local Plan consultancy contract to Hyas, with both phases totalling £156,000, exempting it from competitive tender rules to secure plan submission by December 2026 and examination in spring 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 2 Local Plan consultancy, CPR exemption approved
Money£156,000 totalAggregated Phase 1 and Phase 2 value
What happens nextSubmit plan by December 2026Examination expected spring 2027
Who it affectsLocal Plan preparation and adoptionPlanning Policy team, residents, developers

What was decided

Cabinet exempted the procurement from the Council's Contract Procedure Rules. Report 3.3

Cabinet approved awarding the Phase 2 contract to Hyas to take the Local Plan through to examination and adoption. Report 1.3, 5.1

The reason given was to obtain the necessary resource to meet the Council's obligations in preparing the Local Plan.

Why

The Planning Policy and Land Charges Manager retired in late 2025 and two recruitment attempts produced no applicants, so Hyas was brought in for eight months of Phase 1 support. Report 1.1

Officers argued there are special circumstances for exemption because Hyas has significant knowledge of the Local Plan, its evidence base, and cross-boundary issues, and retendering would duplicate effort and delay progress. Report 3.6

Without a submitted Regulation 19 Plan by December 2026, the Council would be left without a Local Plan and significantly vulnerable to speculative development proposals across the district. Report 3.7

What happens next

Hyas will prepare all documentation required for submission of the Local Plan for examination in line with legislative requirements, working with the Planning Policy team and the Head of Planning and Infrastructure. Report P6, P7, 2.1

Hyas will represent the Council throughout the Examination process, including providing expert testimony, defending challenges, and responding to the Inspector, and will implement any recommended modifications following consultation. Report P11, P12, P13

Any decision to extend or vary the contract will be made by the Strategic Director of Place in consultation with the Head of Legal and Support Services and the Infrastructure Portfolio Holder, with advice from Legal and Finance. Report 6.1, 6.2

The money

  • £62,400 Phase 1 contract value with Hyas Report 1.1
  • £156,000 Aggregated Phase 1 and Phase 2 contract value Report 3.1, 5.1
  • £81,000 Government grant provided to contribute to Local Plan preparation costs Report 4.1

Options considered

  • Chosen: Exempt the contract from CPR and award Phase 2 directly to Hyas. Hyas holds significant knowledge of the Local Plan and retendering would duplicate work and risk the December 2026 submission deadline Report 3.4, 3.6, 3.7
  • Rejected: Run a competitive tender for Phase 2. Would require duplication of effort getting a new provider up to speed and could delay submission Report 3.6

Implications

  • Financial: Total cost of £156,000 will be met by the salary saving from the vacant Planning Policy and Land Charges Manager post and £81,000 of government grant funding. Report 4.1
  • Risk: A risk assessment for the Local Plan Review is kept up to date, with risks reviewed at Local Plan Steering Group meetings. Report P35
  • Legal: The Local Plan must be consistent with the National Planning Policy Framework and other government guidance; Hyas will liaise with Legal and Finance before any additional unforeseen work. Report P29, 6.1
  • Staffing: The Planning Policy and Land Charges Manager post remains vacant after two failed recruitment attempts; Hyas provides contingent resource. Report 1.1
  • Equalities: An Equalities Impact Assessment of the Local Plan is part of the Sustainability Appraisal. Report P31
  • Climate: The new Local Plan aims to deliver positive environmental and climate change impacts, with specific policies recorded through the Sustainability Appraisal. Report P34

Who and where

  • North West Leicestershire District Council Planning Policy team and Head of Planning and Infrastructure Report 1.1, P6
  • Local Plan Committee members
  • Residents and developers across the district Report 3.7
  • Neighbouring councils whose Local Plans interact with the district, including Oadby and Wigston

Timeline

  • Late 2025: Planning Policy and Land Charges Manager retired Report 1.1
  • Following two failed recruitment attempts: Hyas contracted for eight months of Phase 1 support, value £62,400 Report 1.1
  • 17th July and 11th September: Regulation 19 Local Plan consultation took place Report P34
  • June 2026: A number of evidence-based studies to inform the Local Plan were not available in draft until this date Report 6.1
  • November 2026: Meetings of Local Plan Committee, Cabinet and Council expected
  • December 2026: Deadline for submission of the Local Plan Report 3.7, P6
  • Spring 2027: Examination of the Local Plan expected

Plain English for the jargon

  • Local Plan: The council's planning document that sets out planning policies and site allocations for the district.
  • Regulation 19 Plan: The publication version of the Local Plan that is submitted for examination.
  • Contract Procedure Rules (CPR): The council's internal rules governing how contracts must be procured.
  • Programme Officer: An independent officer appointed to manage the administration and procedural requirements of the Local Plan examination.
  • Sustainability Appraisal: An assessment of the social, environmental and economic effects of the Local Plan, which includes an Equalities Impact Assessment.
  • Phase 1 and Phase 2: Phase 1 was eight months of initial Planning Policy consultancy support; Phase 2 covers support through to examination and adoption.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item69

Resolved

RESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules (CPR) be exempt. 2) The award of the contract to HYAS for phase 2, to take the Local Plan through to examination and adoption, be approved. Reason for decision: To obtain necessary resource to meet the Council’s obligations in preparing the Local Plan.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Consultancy Services for the Local Plan Cabinet ReportReport Copy on its way
PDF
Consultancy Services for the Local PlanMinutes 98 KB Download

At this meeting

Whole meeting

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Marlborough Centre RegenerationRESOLVED THAT: 1) The progress of the Marlborough Centre Project be noted. 2) Authority be delegated to the Strategic... Noted Open