RESOLVED THAT: Cabinet 1. Notes the reduction in the number of grant eligible properties and the consequent reduction in backlog funding grant as detailed in section 4.0 of this report, and the projected additional cost of making all identified non decent homes meet the decent homes standard by March 2015. 2. Considers the outcome of the Policy Development Group's consideration of this matter at their meeting on 16 July 2014. 3. Recommends to Council the revised 2014/15 Housing Capital Programme and HRA budget as detailed in appendix a and b of this report to ... view the full minutes text for item 23.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
To outline the additional costs of the Decent Homes Programme 2014/15, to consider the Policy Development Group's comments Purpose of report and to consider a recommendation to Council as a departure from the budget
To make recommendations to Council for funding to complete the Reason for Decision Decent Homes Programme.
Value for Money Council Priorities Homes and Communities
Implications:
Financial/Staff The implications of the decision are covered in the report
Link to relevant CAT Not applicable
Risk Management The risks associated with the decision are covered in the report Equalities Impact The implications of the decision are covered in the report Assessment
Human Rights Not applicable
Transformational Not applicable Government
Comments of Deputy Chief The report is satisfactory Executive
Comments of Section 151 The report is satisfactory Officer
Comments of Monitoring On the advice of Bevan Brittan this report is satisfactory Officer
Consultees Housing Revenue Account Business Plan Project Board
Additional Costs of the Decent Homes Improvement Programme 2014/15 (Cabinet - 4 March 2014)
Background papers Call-in of Cabinet decision of 4 March 2014 entitled ‘Additional Costs of the Decent Homes Programme 2014/15’ (Policy Development Group - 12 March 2014)
THAT CABINET -
1. NOTES THE REDUCTION IN THE NUMBER OF GRANT ELIGIBLE PROPERTIES AND THE CONSEQUENT REDUCTION IN BACKLOG FUNDING GRANT AS DETAILED IN SECTION 4.0 OF THIS REPORT, AND THE PROJECTED ADDITIONAL COST OF MAKING ALL IDENTIFIED NON DECENT HOMES MEET THE DECENT HOMES STANDARD BY MARCH 2015.
Recommendations 2. CONSIDERS THE OUTCOME OF THE POLICY DEVELOPMENT GROUP'S CONSIDERATION OF THIS MATTER AT THEIR MEETING ON 16 JULY 2014.
3. RECOMMENDS TO COUNCIL THE REVISED 2014/15 HOUSING CAPITAL PROGRAMME AND HRA BUDGET AS DETAILED IN APPENDIX A AND B OF THIS REPORT TO FUND THE COMPLETION OF ALL THE REQUIRED WORK, AND THE AMENDED PRUDENTIAL INDICATORS DETAILED IN APPENDIX C AS A DEPARTURE FROM THE CURRENT BUDGET 1.0 BACKGROUND
1.1This report will advise Cabinet of the outcome of the detailed evaluation of the number of newly identified non decent properties, the projected cost of completing works to them, and the funding sources for completing this work This includes the draft revised Housing Revenue Account (HRA) Budget (as Appendix A), draft revised Capital Programme (as Appendix B) and draft revised prudential indicators (as Appendix C).
1.2In addition it will also explain the implications of the data analysis completed as part of the end of year process following the successful completion of the 2013/14 Decent Homes Improvement Programme, and the effect of this on our Decent Homes Backlog Funding Grant allocation for 2014/15.
1.3The impact of the funding implications of these matters on the Housing Revenue Account Business Plan is addressed in a separate paper on the agenda for this meeting of Cabinet.
2.0DELIVERY OF THE DECENT HOMES PROGRAMME TO DATE
2.1The Decent Homes Improvement Programme (DHIP) for 2013/14 has recently been completed, with a total of 2,118 Council tenants homes having now been made decent over two years using a combination of Homes and Communities Agency (HCA) backlog funding grant (£12.2m) and North West Leicestershire District Council funding sources during 2012/13 and 2013/14. Customer satisfaction with the completed works is 97.5% for Q4 of 2014/15 against a target of 95%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.