RESOLVED THAT: a) The progress made by the Coalville Project be noted. b) The future direction of work for the Coalville Project be approved. c) The grant of exemption to the C ouncil’s Contract Procedure R ule 6.7 to allow the direct award of a contract for the provision of specialist community engagement services be noted. d) Authority be delegated to the Chief Executive in consultation with the Leader to commit expenditure for the remaining £450,000 of the Coalville Project reserve . Reason for decision: To provide Cabinet with an update on the progress of the Coalville Project. The Contract Procedure Rules require that the exercise of the Statutory Officer’s discretion to grant exemptions is reported to Cabinet.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
To provide Cabinet with an update on the progress of the Coalville Project. Purpose of report To advise Cabinet of an exemption to the Contract Procedure Rules relating to procurement of community engagement activities.
To provide Cabinet with an update on the progress of the Coalville Project. Reason for Decision The Contract Procedure Rules require that the exercise of the Statutory Officer’s discretion to grant exemptions is reported to Cabinet
Building Confidence in Coalville Value for Money Council Priorities Business and Jobs Homes and Communities Green Footprints Challenge
Implications:
Financial/Staff Included within the report
Link to relevant CAT None Risks are being managed through the Coalville Project governance Risk Management process.
Equalities Impact Screening Not applicable
Human Rights None
Working with other public and private partners to deliver a better Transformational deal for Coalville and maximising investment to build confidence in Government the town and community.
Comments of Head of Paid The report is satisfactory. Service
Comments of Deputy The report is satisfactory. Section 151 Officer
Comments of Monitoring The report is satisfactory. Officer
Consultees None
Building Confidence in Coalville report to Cabinet on 22 September 2015 Building Confidence in Coalville report to Cabinet on 12 January Background papers 2016 Building Confidence in Coalville report to Cabinet on 9 February 2016
THAT CABINET: 1. NOTES THE PROGRESS MADE BY THE COALVILLE PROJECT. 2. APPROVES THE FUTURE DIRECTION OF WORK FOR THE COALVILLE PROJECT 3. NOTES THE GRANT OF EXEMPTION TO THE COUNCIL’S CONTRACT PROCEDURE RULE 6.7 TO Recommendations ALLOW THE DIRECT AWARD OF A CONTRACT FOR THE PROVISION OF SPECIALIST COMMUNITY ENGAGEMENT SERVICES. 4. DELEGATES AUTHORITY TO THE CHIEF EXECUTIVE IN CONSULTATION WITH THE LEADER TO COMMIT EXPENDITURE FOR THE REMAINING £450,000 OF THE COALVILLE PROJECT RESERVE. 1.0 BACKGROUND
1.1Following the May 2015 election, the Leader set out the regeneration of Coalville as one of the Council’s priorities and gave responsibility for delivery to the Chief Executive. “Building confidence in Coalville” has become one of the council’s stated priorities in the 2016/17 Council Delivery Plan.
1.2On 22 September 2015 Cabinet agreed to progress with the Building Confidence in Coalville project as outlined in that report (the “Coalville Project”) and to access the Scape Major Works framework in order to procure specialist advisors to commence the feasibility stage of potential works on Stenson Square (referred to as Phase 1 of the Coalville Project).
1.3On 12 January 2016, Cabinet received a report on the progress of the Coalville Project which outlined establishment of project governance, progress made by specialist advisors delivering the feasibility stage of Phase 1 of the Coalville Project, noted the procurement of specialist advisors to conduct an options appraisal for the leisure and culture offer of the district and approved creation of a Coalville Project reserve and re-assignment of underspent reserves.
1.4On 9 February 2016, Cabinet approved procurement of further feasibility studies related to phase 1 of the Coalville Project and delegated authority to the Chief Executive in consultation with the Leader to commit expenditure of part of the Coalville Project Reserve.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.