RESOLVED THAT: a) The additional allocated funds of £48,000 from reserves and the variation of the delivery contract with Firmstep to include the items set out in paragraph 2.3 be approved to ensure phase one of the programme is delivered. b) The allocated funds totalling between £155,000 - £180,000 be approved for phase two of the programme to be delivered, and that this expenditure be attributed to the Housing Revenue Account (51.5% of cost) and General Fund reserves (48.5% of cost) c) Authority be delegated to the Director of Housing in consultation with the Corporate Portfolio Holder to award a contract to Firmstep through the G-Cloud framework for the delivery of phase two. d) It be noted that further updates will be brought to Cabinet as the programme progresses. Reason for decision: To ensure Members are aware of the additional cost to complete Phase One and the cost to complete Phase Two. The additional costs takes the contract value above the £100,000 threshold which requires Cabinet approval. Without the additional investment to complete Phase One, this would jeopardise the scheduled “go live” date of 19 April 2018, as well as non-completion of online services for key areas, where efficiency savings are to be made. Without the additional investment to complete Phase One, this would cause a delay in the launch of the new internet web site, as both projects are intrinsically linked to provide an improved customer experience, which is part of the customer first strategy. To authorise the procurement of Firmstep to deliver Phase Two of the Digital Transformation Programme.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Provide members with details of the Council’s Digital Transformation Programme, additional cost requirements to Purpose of Report complete Phase One and costs required for Phase Two. The completion of Phase One and Phase Two, will see the completion of digitally online Council services. 1. To ensure Members are aware of the additional cost to complete Phase One and the cost to complete Phase Two. 2. The additional costs takes the contract value above the £100,000 threshold which requires Cabinet approval. 3. Without the additional investment to complete Phase One, this would jeopardise the scheduled “go live” date of 19 Reason for Decision April 2018, as well as non-completion of online services for key areas, where efficiency savings are to be made. 4. Without the additional investment to complete Phase One, this would cause a delay in the launch of the new internet web site, as both projects are intrinsically linked to provide an improved customer experience, which is part of the customer first strategy. 5. To authorise the procurement of Firmstep to deliver Phase Two of the Digital Transformation Programme. Value for Money Council Priorities Spend Our Money Wisely Building Confidence in Coalville Implications:
Financial/Staff As detailed in the report
Link to relevant CAT No direct link
The original project plan includes a risk management framework, which is being reviewed on a monthly basis as Risk Management part of the project management process. Risks are being updated and added to as required and any issues are raised with the Director of Housing. Equalities Impact Screening N/A
Human Rights N/A
Transformational This relates to the new ways in which Councils are being Government asked to deliver their services.
Comments of Head of Paid The report is satisfactory. Service Comments of Deputy The report is satisfactory. Section 151 Officer Comments of Monitoring The report is satisfactory. Officer
Consultees None
NOVEMBER 2017 CABINET - DIGITAL Background Papers TRANSFORMATION PROGAMME
THAT CABINET: 1. APPROVES THE ADDITIONAL ALLOCATED FUNDS OF £48,000 FROM RESERVES AND THE VARIATION OF THE DELIVERY CONTRACT WITH FIRMSTEP TO INCLUDE THE ITEMS SET OUT IN PARAGRAPH 2.3 TO ENSURE PHASE ONE OF THE PROGRAMME IS DELIVERED
Recommendations 2. APPROVES THE ALLOCATED FUNDS TOTALLING BETWEEN £155,000 - £180,000 FOR PHASE TWO OF THE PROGRAMME TO BE DELIVERED, AND THAT THIS EXPENDITURE BE ATTRIBUTED TO THE HOUSING REVENUE ACCOUNT (51.5% OF COST) AND GENERAL FUND RESERVES (48.5% OF COST) 3. THAT CABINET DELEGATES AUTHORITY TO THE DIRECTOR OF HOUSING IN CONSULTATION WITH THE CORPORATE PORTFOLIO HOLDER TO AWARD A CONTRACT TO FIRMSTEP THROUGH THE G-CLOUD FRAMEWORK FOR THE DELIVERY OF PHASE TWO. 4. NOTES THAT FURTHER UPDATES WILL BE BROUGHT TO CABINET AS THE PROGRAMME PROGRESSES.
1. BACKGROUND 1.1 The use of digital services is now an entrenched way of everyday life. From requesting doctors’ appointments, undertaking bank transactions, buying goods and services and booking holidays, the process offers wider choice, customer convenience, corporate flexibility and significantly reduced costs via automated processes and minimal manual interventions. Until fairly recently Local Government was far behind most industries and at this point NWLDC is significantly behind the bulk of local authorities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.