Coalville Special Expenses Working Party agreed this item on Tuesday 17 December 2019. Below is the council's own wording, with the papers it was decided on.
It was agreed that the contact details for the relevant officer working on the project be circulated to Members. Councillor J Legrys suggested the creation of a community group to maintain the wildflowers, as he was aware that there would be a cost involved for officers. Councillor J Legrys wanted to see progress before spring because once bird-nesting season began work would be halted. By affirmation of the meeting it was RESOLVED THAT: a) The progress update on the 2019/20 Capital Projects be noted. b) The delivery of the five-year asset management schedule at appendix A be supported. RECOMMENDED THAT: Cabinet allocate £5,000 as a budget proposal for 2020/21 towards Coalville in Bloom 2020.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Report to Coalville Special Expenses Working Party
NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL
COALVILLE SPECIAL EXPENSES WORKING PARTY – TUESDAY, 17 DECEMBER 2019
Title of Report CAPITAL PROJECTS UPDATE
Presented by Leisure Services Team Manager 01530 454602 [email protected]
Financial Implications The allocation of £5,000 as a 2020/21 budget proposal for Coalville in Bloom Delivery of the 5 year Asset Management Schedule
Purpose of Report To update members with regards to Capital Projects within the Coalville Special Expense Area
Recommendations 1. THE WORKING PARTY NOTE THE PROGRESS UPDATE ON THE 2019/20 CAPITAL PROJECTS. 2. THE WORKING PARTY SUPPORT THE ALLOCATION OF £5,000 AS A BUDGET PROPOSAL FOR 2020/21 TOWARDS COALVILLE IN BLOOM 2020 3. THE WORKING PARTY SUPPORT DELIVERY OF THE 5 YEAR ASSET MANAGEMENT SCHEDULE AT APPENDIX A
1.02019/20 CAPITAL PROJECTS
1.1Thringstone Miners Social Centre Training Pitch – £7,431 Since the departure of the football club, the centre is now on a much more stable financial footing. Two football clubs are using the facility, there are more functions and fund raising events being held, and the bar is being managed and run by the Whitwick Conservative Club. However, there is still a lack of trustees to support the management and development of the facility and a new treasurer is potentially required. The Chair of Trustees is being supported in attempting to recruit to these vacancies by the NWLDC Community Focus team. Once back up to capacity, focus will turn to the training pitch development.
1.2Melrose Road Play Hub – £4,000 The path is in the process of being installed although poor weather conditions have delayed the installation. It is anticipated it will be completed during December. Once completed, the item will be removed from the agenda.
1.3Coalville Park – £35,470 S106 funding and £1,200 CSE funding Representatives of the Friends of Coalville Park group will be attending the meeting to update members on progress of projects and their vision for the park.
1.3.1 Play Equipment Following resident engagement, this is considered the highest priority and in principle support has been given by CSEWP to allow the majority of S106 funding to be allocated to this project. The Friends Group are working with officers to develop proposals and identify external funding sources to improve the play equipment.
1.3.2 Community Garden This has been identified as the second priority. John Merison is working with the Friends of Coalville Park group to develop proposals, costings, and a business plan for the management of the community garden as part of an Incredible Edible scheme.
1.3.3 Park Improvement Improving the park by extending into the adjacent field to provide additional planted areas, trees and pathways has been identified as the lowest priority
1.3.4 Skate Park Graffiti Project - £1,200 Officers will be engaging Graffwerk, an arts project team from Leicester who specialise in graffiti art, to support with the delivery of this project. In liaison with them, a project brief will be devised which will go out to consultation with skateboard users of the area next spring when usage of the area has increased after winter.
1.4Lillehammer Drive - £6,000 Following liaison with Barratt’s, they have agreed to the following-:
That the £35,470 S106 funding allocated to replacing the MUGA could be allocated instead to any of the 3 projects; o Extending Coalville Park into the field at the rear of the site o Improving the play equipment provision at Coalville Park o Improving the community garden to support community access as part of an Incredible Edible scheme That the former MUGA site that should be converted to open space could instead become an educational nature area that is part of Belvoirdale School which would then be leased to them for a peppercorn rent That the S106 funding received to convert the MUGA area into open space and to maintain it, could instead be used to help create the educational area above
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Coalville Special Expenses Working Party at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingRESOLVED THAT: The minutes of the meeting held on 2 June 2026 be approved and signed by the Chair as an accurate reco...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.