It was agreed by the Leisure Services Team Manager that these concerns would be raised with the team and agreed to update the Chair and ward member. Members asked where the trees would be sourced from and who would be supplying them. The Leisure Services Team Manager replied that the trees were funded by the National Forest but was unsure who was supplying them. He agreed to find out this information and provide it outside of the meeting. A discussion was had which focused on Scotland’s Park Bowls Club. The Leisure Services Team Manager stated that the club would be in a better position to secure external funding to manage ongoing maintenance with a long-term lease if the lease would allow them to sublet. After it was asked whether any work was planned for the sports pavilion, the Leisure Services Team Manager replied that there are currently no plans to improve the existing pavilion, and members were advised that Section 106 funds could not be used for this purpose. Members commented that they had received concerns regarding the maintenance of the changing pavilion. It was replied by the Leisure Services Team Manager that inspections had since taken place, and that no issues had been identified, but that the area would continue to be monitored, as there was funding that had been allocated specifically for improving this pavilion. The discussion moved towards to Coalville Park Improvements during which members expressed their support for the trees and flower displays in Coalville Park. The Chair thanked members for their comments.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Report to Coalville Special Expenses Working Party
NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL
COALVILLE SPECIAL EXPENSES WORKING PARTY – TUESDAY, 7 OCTOBER 2025
Title of Report 2025/26 CAPITAL PROJECTS UPDATE
Presented by Jason Knight Leisure Services Team Manager
Background Papers None
Financial Implications All works are covered within existing budgets or through external funding sources.
Signed off by the Section 151 Officer: Yes
Legal Implications None
Signed off by the Deputy Monitoring Officer: Yes
Staffing and Corporate None Implications Signed off by the Head of Paid Service: Yes
Purpose of Report To update members with regards to capital projects within the Coalville Special Expenses Area.
Recommendations THAT THE WORKING PARTY:
NOTES THE PROGRESS UPDATE ON THE 2025/26 CAPITAL PROJECTS
1.02025/26 CAPITAL PROJECTS
1.1Coalville Special Expenses Assets The Asset Management Plan approved as part of the 2025/26 budget setting process is attached as Appendix A. All works budgeted for in 2025/26 will be delivered during the financial year.
Greenhill Recreation Ground Changing Pavilion - £9,000 This includes work to treat the walls, remove graffiti, decorate internally and externally, and the installation of a new extract fan. Work is being managed and delivered by the Property Services and quotes have been obtained which come in within budget. Consequently, the works will be delivered over winter.
Scotland Recreation Ground Drive Repairs - £1,903 This work has been completed, and this item will be removed from future reports.
London Road Cemetery Tree Works - £1,050 These works will be delivered during winter 2025/26. London Road Cemetery Footpath Repairs and Levelling - £10,000 This work is being managed and delivered by Property Services. Quotes have been obtained which come within budget and so subject to corporate approval being given for works to be undertaken, works will be completed prior to 31 March 2026.
Broomleys Cemetery Tree Works - £1,930 These works have commenced and will be completed during winter 2025/26.
Broomleys Cemetery Path Sealing - £13,105 Subject to being able to procure a contractor to deliver these works, they will be delivered prior to the end of March 2026.
Broomleys Cemetery Driveway and Path Repairs - £12,000 This work is being managed and delivered by Property Services. Quotes have been obtained which come within budget and so subject to corporate approval being given for works to be undertaken, works will be completed prior to 31 March 2026.
Play Area Painting - £5,400 Cropston Drive Play Area has been completed. All outstanding works will be delivered prior to the end of March 2026.
Stadium Close Play Area Equipment Replacement - £2,450 This work will be completed prior to the end of March 2026.
Staples Drive Play Area Entrance Gates - £3,000 This work has been completed, and this item will be removed from future reports.
1.2Trees in Coalville External funding has been obtained, and plans are being developed to plant trees at the following sites:
Cropston Drive Recreation Ground Stadium Close Play Area Western Avenue Recreation Ground
The funding covers the planting of the trees and the first three years of maintenance.
1.3Junior Parkrun Following support at the last meeting of the Coalville Special Expenses Working Party, preparations are ongoing to launch a Junior Parkrun at Coalville Park in spring 2026. There are currently 22 volunteers willing to support the weekly event.
1.4Coalville in Bloom The scheme for 2025 has been delivered. There have been concerns raised around the quality of the hanging baskets and these are being investigated by officers whilst also considering alternative options for 2026. The number of hanging baskets purchased by local businesses decreased from eleven in 2024 to six in 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Coalville Special Expenses Working Party at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingRESOLVED THAT: The minutes of the meeting held on 2 June 2026 be approved and signed by the Chair as an accurate reco...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.