Cabinet, Tuesday 29 September 2020 at 5.00pm

Procurement of Housing New Build Contractor

Approved Executive 1 paper

Cabinet approved this item on Tuesday 29 September 2020. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

RESOLVED THAT: (1) Cabinet approves the procurement of (a) construction contractor(s) for the duration of the current 3 year proposed new build programme; (2) Authority be delegated to the Strategic Director of Housing and Customer Services in consultation with the Section 151 Officer and relevant portfolio holder to select contractors, as necessary, to deliver the programme through legally compliant framework/dynamic purchasing systems. Reason for decision: To allow the Council to be compliant with the Procurement Rules within the Constitution.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet

Background

1.1On 10 November 2015 a report was taken to Cabinet providing an update on the new build work to date and seeking approval for 3 schemes to be included in the initial new build programme. 1.2 These schemes were described as:  Willesley Estate Sites x 2 (3 no. 1 bed units 4 no. 2 bed units)  Greenacres Colaville (4 no. 1 bed units and 6 no. 2 bed units)  The Brownfield Site, Coalville (4 no. 1 bed units 8 no. 2 bed units)

1.3A subsequent report was agreed by Cabinet on 17th January 2017 providing delegated authority for the Director of Housing to award the construction contract for the newbuild programme phase 1 and potentially phase 2 to Robert Woodhead (Woodheads) via Efficiency East Midlands (EEM.)

1.4This decision was made through a mini competition through the EEM framework and Woodheads were contracted for 24 units on Phase 1 and up to 20 units for a further phase with details to be determined. Phase 1 was built out as specified and phase 2 has recently been completed albeit in a reduced form with 8 units delivered on the former Cocked Hat site.

1.5Over the 3 1/2 years we have worked with our current contractor and have developed an effective partnership that has benefitted from continuity over time, and this is a feature we wish to secure in future arrangements. Working with a common contractor has assisted in progressing schemes quicker due to a closer and growing working relationship and has improved the overall delivery of housing sites within the HRA.

2. SCOPE OF FUTURE PHASES

2.1The housing service has been working up details for the next stage of the newbuild programme for some time and has now identified a number of sites with a combined capacity for approximately 30 units that it intends to build, as well as a number of others with varying degrees of potential. In addition, there is an ongoing programme of actively working with RP partners to identify development opportunities and seeking to directly acquire land for the construction of new Council housing. This new build programme is part of our wider approach to the supply of new affordable homes for rent as a landlord, which also includes acquiring Section 106 properties, buy back of former Right to Buy properties, and open market purchase of both new and existing homes in areas of housing need.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Housing New Build ContractorMinutes 480 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
RB
Councillor Richard BluntChair, present
RA
Councillor Robert AshmanDeputy Chair, present
RB
Councillor Roger BaylissCommittee Member, present
TG
Councillor Tony GillardCommittee Member, present
NR
Councillor Nicholas RushtonCommittee Member, present
AW
Councillor Andrew WoodmanCommittee Member, present
BS
Bev SmithOfficer, in attendance
JA
James ArnoldOfficer, in attendance
AB
Andy BartonOfficer, in attendance
TB
Tracy BinghamOfficer, in attendance
CC
Chris ColvinDemocratic Services Officer, in attendance
TD
Tom DelaneyDemocratic Services Officer, in attendance

All 16 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Procurement of Housing New Build ContractorThis decision
  2. Communal Cleaning Procurement for Housing SitesApproved
  3. Procurement of Housing New Build ContractorNoted

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies