RESOLVED THAT 1) Council be recommended to approve the 2021/22 capital strategy included in Appendix A, in line with the prudential code; 2) The forecast General Fund and HRA Capital Outturn for 2020/21 and planned financing be noted in Appendices B and C; 3) Council be recommended to approve the capital programmes in 2021/22 detailed in: · Appendix B – The General Fund Capital Programme · Appendix C – HRA Capital Schemes 4) Cabinet notes the proposed procurement routes in respect of vehicles, equipment and plant and delegates the authority to award these contracts and any associated agreements to the relevant Strategic Director in consultation with the relevant Portfolio Holder, subject to final approval of the capital programmes in February 2021. Reason for decision : To enable projects to be included in the Programmes for approval at Cabinet.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Title of Report 2021/22 CAPITAL STRATEGY AND 2021/22 - 2025/26 CAPITAL PROGRAMMES
Presented by Councillor Nicholas Rushton Corporate Portfolio Holder
Background Papers Corporate Scrutiny Public Report: Yes Minutes – 11 November 2020
Draft Capital Programme – Cabinet – 8 December Key Decision: Yes 2020
Draft Minutes – Corporate Scrutiny Committee - 6 January 2021 Financial Implications The General Fund Capital Programme for 2021/22 is £20.2 million. The main schemes are the new leisure centre in Coalville, Council Offices Refurbishment project, Coalville Regeneration and Marlborough Square.
The Housing Revenue Account Capital Programme for 2021/22 is £15.6 million. The main schemes are the Home Improvement Programme and the New Supply programme, which make up 77% (£12.0 million) of the programme.
Both programmes account for considerable slippage of funding from the 2020/21 financial year that is currently forecast for delivery in 2021/22. Signed off by the Section 151 Officer: Yes
Legal Implications None
Signed off by the Monitoring Officer: Yes
Staffing and Corporate None Implications Signed off by the Head of Paid Service: Yes
Purpose of Report To advise Members of the likely Capital Outturn and the relevant financing for 2020/21 for the General Fund and the Housing Revenue Account (HRA).
To seek approval to the General Fund and HRA Capital Programmes for 2021/22 and to note indications for future years and associated funding. Reason for Decision To enable projects to be included in the Programmes for approval at Cabinet.
Recommendations 1) THAT COUNCIL BE RECOMMENDED TO APPROVE THE 2021/22 CAPITAL STRATEGY INCLUDED IN APPENDIX A, IN LINE WITH THE PRUDENTIAL CODE.
2) THAT THE FORECAST GENERAL FUND AND HRA CAPITAL OUTTURN FOR 2020/21 AND PLANNED FINANCING BE NOTED IN APPENDICES B AND C.
3) THAT COUNCIL BE RECOMMENDED TO APPROVE THE CAPITAL PROGRAMMES IN 2021/22 DETAILED IN: APPENDIX B – THE GENERAL FUND CAPITAL PROGRAMME APPENDIX C – HRA CAPITAL SCHEMES
4) THAT CABINET NOTES THE PROPOSED PROCUREMENT ROUTES IN RESPECT OF VEHICLES, EQUIPMENT AND PLANT AND DELEGATES THE AUTHORITY TO AWARD THESE CONTRACTS AND ANY ASSOCIATED AGREEMENTS TO THE RELEVANT STRATEGIC DIRECTOR IN CONSULTATION WITH THE PORTFOLIO HOLDER, SUBJECT TO FINAL APPROVAL OF THE CAPITAL PROGRAMMES IN FEBRUARY 2021.
1 .0 INTRODUCTION
1.1Cabinet considered the draft capital programmes on 8 December 2020. This was followed up by a report to the Corporate Scrutiny Committee on 6 January 2021. A link to the draft minutes has been included as a background paper.
1.2By regulation, all local authorities are required to have regard to the Prudential Code when setting their Capital Programmes. The core objectives of the Code are to ensure that Capital schemes are ‘Affordable, Prudent and Sustainable’. This is reviewed in conjunction with both the Capital Strategy and the Treasury Management Strategy Statement (TMSS) which contains indicators that evidence compliance with the Code. These strategies will be presented to members at the same meeting as this report.
1.3As part of the process of effectively assessing property items for inclusion in the capital programme, the Council has collated a Planned Preventative Maintenance (PPM) Schedule that prioritises works based on a matrix scoring system. Items of a capital nature that are essential have been included in the capital programme in 2021/22.
1.4Appendix B shows the General Fund Programme estimated outturn for 2020/21 and the proposed Capital Programme for 2021/22 to 2025/26.
1.5There is no Special Expense capital expenditure estimated for 2020/21 and no proposed capital programme. 1.6 Appendix C shows the HRA Capital Programme estimated outturn for 2020/21 and the proposed Capital Programme for 2021/22 to 2025/26.
2.0CAPITAL STRATEGY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.