RESOLVED THAT Cabinet delegates authority to award the Green Homes Improvement Programme Phase 1B Contracts to the Strategic Director of Housing and Customer Services in consultation with the Housing, Property and Customer Services Portfolio Holder and Section 151 Officer. Specifically for the direct award of contracts for: 1) Installation of Green Homes energy efficiency measures; 2) Domestic energy assessor services Reason for decision: The level of expenditure on the proposed contract exceeds the authority level in the Scheme of Delegation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
1.1In July 2020, the Chancellor announced £2 billion of support through the Green Homes Grant Scheme (GHG) to save households money; cut carbon emissions; and create green jobs. £500m of this support was allocated to English Local Authority (LA) delivery partners, through the Local Authority Delivery (LAD) scheme. To access grant funding, LAs had to submit competing bids with each bid having to satisfy strict criteria. Grant funding is being released in a series of phases, with tight delivery timetable attached to each one.
1.2The Department for Business, Energy and Industrial Strategy (BEIS) launched an initial competition (Phase 1A) in August 2020 with a delivery deadline of March 2021 for all proposed works projects and subject to a minimum bid of £500,000. The Council prepared a bid but were unable to submit it, as it didn’t meet the minimum threshold for value, and a suitable consortium approach could not be identified.
1.3In October 2020, following feedback on Phase 1A which was undersubscribed, BEIS announced a second round (Phase 1B) with LAs required to submit bids by 04 December 2020. Each bid had to be for a minimum of £250,000 of grant funding with its aim to raise the energy efficiency of low-income and low Energy Performance Certificate (EPC) rated homes. It focused on those households living in the worst quality off-gas grid homes, delivering progress towards: reducing fuel poverty, the phasing out of high carbon fossil fuel heating and the UK's commitment to net carbon zero by 2050.
1.4Delivery deadline for works projects benefitting from a Phase 1B bid is 30 September 2021 with all successful bidders to be notified in January 2021.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.