Cabinet, Tuesday 10 January 2023 at 5.00pm

Kegworth Project

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 10 January 2023. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

RESOLVED THAT: 1. The £500,00 grant from LLEP business rates pool funding be accepted. 2. The available budget of £786,587 to be added to the Capital Programme Development Pool and agreed at Council in February 2023 as part of the budget be approved. 3. The Head of Property and Regeneration be delegated authority to spend the LLEP £500,000 grant on works and to enter into any necessary agreements to proceed with the project. Reason for decision: Acceptance of LLEP grant funding requires Cabinet approval.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet

NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL

CABINET – 10 JANUARY 2023

Title of Report KEGWORTH PUBLIC REALM PROEJCT Presented by Councillor Tony Gillard Business and Regeneration Portfolio Holder

PH Briefed

Background Papers Council February 2019 Public Report: Yes

Key Decision: Yes

Financial Implications The Council has been using monies set aside in an earmarked reserve to fund expenditure on this project to date. The Council has been successful in being allocated a £500,000 grant from the Leicester and Leicestershire Enterprise Partnership (LLEP) Business Rates Pool Fund. The report incorporates this additional grant funding into the project and includes a budget for the scheme into the Capital Programme. Signed off by the Section 151 Officer: Yes

Legal Implications Authority will be liable for delivery of outputs as per LLEP grant agreement.

Signed off by the Deputy Monitoring Officer: Yes

Staffing and Corporate Delivered within existing resources. Implications Signed off by the Head of Paid Service: Yes

Purpose of Report To update Cabinet with progress on the Kegworth Project and to seek approval to accept £500,000 grant from LLEP.

Reason for Decision Acceptance of LLEP grant funding requires Cabinet approval.

Recommendations THAT CABINET APPROVES ACCEPTANCE OF £500,000 GRANT FROM LLEP BUSINESS RATES POOL FUNDING

THAT CABINET APPROVES FOR THE AVAILABLE BUDGET OF £786,587 TO BE ADDED TO THE CAPITAL PROGRAMME DEVELOPMENT POOL AND AGREED AT COUNCIL IN FEBRUARY 2023 AS PART OF THE BUDGET

THAT CABINET DELGATES AUTHORITY TO HEAD OF PROPERTY AND REGENERATION TO SPEND THE LLEP £500,000 GRANT ON KEGWORTH PROJECT WORKS AND TO ENTER INTO ANY NECESSARY AGREEMENTS TO PROCEED WITH THE PROJECT 1.0 BACKGROUND

1.1As early as 2016, a project to improve Kegworth Market Place was mooted and in 2018 the opening of the Kegworth bypass presented opportunities to undertake a village improvement scheme.

1.2At Council on 26 February 2019, £450,000 was committed as match funding for village improvements in the north of the District. This commitment was used as the basis for a bid to the LLEPs Business Rates Pool fund for £500,000 for a public realm project in Kegworth which was submitted in September 2019 and announced as successful in July 2020. The Council has publicly committed to the project as part of the current Council delivery plan under the ‘Support for businesses and helping people into local jobs’ priority.

1.3The project as approved by the LLEP proposes to deliver four elements of work:

 Remodelling of the village Market Place as public realm to create a place for events and cultural activities.  Creation of new cycle routes to link the village centre to major employment areas.  Commencement of village traffic calming through the creation of entrance gateways.  Provision of a new public transport infrastructure (bus stop) within the Market Place.

1.4Preparatory works to deliver the village improvement scheme have been ongoing since the grant was confirmed in 2020. There have been a number of legal and technical challenges that have slowed progress, however, the majority of these have now been resolved and a reviewed timescale has been negotiated for delivery and expenditure with the LLEP. The deadline for spend is now March 2024.

1.5The project has successfully delivered two elements of the original proposal – the village gateways and revised bus waiting area (See Appendix 1). The amount expended to date is £43,067.82 to deliver the village gateways and £49,027.23 to deliver the bus waiting area works.

1.6Working with Kegworth Parish Council, it has been proposed that Leicestershire County Council (LCC) is appointed as the project delivery organisation. This makes practical sense as both the cycle route and the Market Place projects are being delivered on public Highways land.

1.7LCC has confirmed that both the timescales dictated by the LLEP funding agreement and available budgets are achievable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 3.2 MB Download
PDF
Appendix 2Appendix 2 598 KB Download
PDF
Appendix 3Appendix 3 698 KB Download
PDF
Kegworth ProjectMinutes 264 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
RB
Councillor Richard BluntChair, present
RA
Councillor Robert AshmanDeputy Chair, present
RB
Councillor Roger BaylissCommittee Member, present
TG
Councillor Tony GillardCommittee Member, apologies
KM
Councillor Keith Merrie MBECommittee Member, present
NR
Councillor Nicholas RushtonCommittee Member, present
AW
Councillor Andrew WoodmanCommittee Member, present
AT
Allison ThomasOfficer, in attendance
JA
James ArnoldOfficer, in attendance
AB
Andy BartonOfficer, in attendance
EW
Elizabeth WarhurstOfficer, in attendance
GH
Glenn HammonsOfficer, in attendance

All 16 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Kegworth ProjectThis decision
  2. Kegworth ProjectNoted

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies