Capital Projects Update

Noted Committee 2 papers

Coalville Special Expenses Working Party noted this item on Tuesday 14 February 2023. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

RESOLVED THAT: The progress update on the 2022/23 Capital Projects be noted. Option 1 in relation to the Claremont Drive play area be recommended to Cabinet. The withdrawal of the Bardon Road verge improvement project be recommended to Cabinet. However an alternative project be drawn up, using the Bardon Community funding and a £1,000 contribution from Coalville Special Expenses.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Coalville Special Expenses Working Party

NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL

COALVILLE SPECIAL EXPENSES WORKING PARTY – TUESDAY, 14 FEBRUARY 2023

Title of Report CAPITAL PROJECTS UPDATE

Presented by Jason Knight Leisure Services Team Manager

Background Papers None

Financial Implications This report is providing the committee with an update on existing projects that already have approved budget or funding in place.

Due to the financial position of Coalville Special Expenses and the requirement to set a balanced budget for 2023/24, the report highlights several projects where the remaining budgets have been released back to balances. These are reflected within forecasts the 2022/23 Qtr 3 Finance Update Report.

There is also the potential to release a further £9,000 back to balances, which will improve the balances position further. These are detailed in paragraphs 1.5.1 and 1.7 and reflected in recommendations 2 and 3

Signed off by the Section 151 Officer: Yes

Legal Implications None identified

Signed off by the Deputy Monitoring Officer: Yes

Staffing and Corporate None identified Implications Signed off by the Head of Paid Service: Yes

Purpose of Report To update members with regards to capital projects within the Coalville Special Expenses Area and to seek approval on the recommendations within the report.

Recommendations THE WORKING PARTY: 1. NOTES THE PROGRESS UPDATE ON THE 2022/23 CAPITAL PROJECTS 2. MAKES A RECOMMENDATION TO CABINET ON PURSUING EITHER OPTION 1 OR 2 IN RELATION TO THE CLAREMONT DRIVE PLAY AREA 3. MAKES A RECOMMENDATION TO CABINET THAT THE BARDON ROAD VERGE IMPROVEMENT PROJECT BE WITHDRAWN TO EFFECT A SAVING OF £2,000 1.0 2022/23 CAPITAL PROJECTS

1.1Thringstone Miners Social Centre Training Pitch – £7,431 The football club have now undertaken their grading requirement work, but there has been no further progress with this project. In order to assist with the 2022/23 financial position, the £7,431 has been returned to balances and the trustees notified the funding is no longer available.

1.2Coalville Park Skate Park Graffiti Project – £600 The lack of response to a number of attempts to consult with and engage children and young people has led to the conclusion that there is no desire to progress this project. £600 has already been spent on engaging Graffwerks to develop designs, and the remaining £600 has been returned to balances to assist with the 2022/23 financial position.

1.3Lillehammer Drive - £4,223 The legal representatives of Barratt’s have executed and returned all the required legal documentation and the planning application for the change of use has been approved. Despite initially requesting further reassurances in writing from Barratt’s regarding the use of the land, LCC has now waived that request. Consequently, just confirmation from Barratt’s that they’re happy to complete the documentation is required, and when received the prepared lease will be signed and management of the area will be transferred to Belvoirdale School. Works will then be undertaken utilising the Barratt’s section 106 contribution earmarked for landscaping the area.

1.4Coalville in Bloom 2023 £5,000 A member of the Working Party has secured an in principle £5,000 contribution towards Coalville in Bloom 2023. As part of the budget setting process for 2023/24 and to try and ensure a balanced budget for Coalville Special Expenses, it has been proposed that the £5,000 revenue budget allocated to the scheme annually is removed and that the external £5,000 contribution is used to fund the scheme in 2023/24. Officers will work with members to develop a scheme within budget. If Coalville in Bloom is to be delivered beyond 2023/24 then external funding will need to be secured to cover the costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 367 KB Download
PDF
Capital Projects UpdateMinutes 366 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 18 attended
DE
Councillor David EverittChair, present
MW
Councillor Michael WyattDeputy Chair, present
EA
Councillor Elliott AllmanCommittee Member, present
AB
Councillor Alexander BridgenCommittee Member, absent
AB
Councillor Angela BlackCommittee Member, apologies
JG
Councillor John GearyCommittee Member, in attendance
JL
Councillor John LegrysCommittee Member, in attendance
JW
Councillor Jake WindramCommittee Member, in attendance
MF
Councillor Marie FrenchCommittee Member, present
AC
Anna CrouchOfficer, in attendance
JK
Jason KnightOfficer, in attendance
WM
Wendy MayOfficer, apologies

All 18 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Capital Projects UpdateThis decision
  2. Capital Projects Update 2025/26Agreed
  3. 2024/25 Capital Projects UpdateAgreed
  4. Capital Projects UpdateNoted
  5. Capital Projects UpdateNoted
  6. Capital Projects UpdateDecided

More from North West Leicestershire Coalville Special Expenses Working Party

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of the Previous MeetingRESOLVED THAT: The minutes of the meeting held on 2 June 2026 be approved and signed by the Chair as an accurate reco... Approved Open
2 Jun 2026 Appointment of ChairmanRESOLVED THAT: Councillor M Wyatt be appointed Chairman of the Coalville Special Expenses Working Party for 2026/27. Decided Open
2 Jun 2026 Appointment of Deputy ChairmanRESOLVED THAT: Councillor L Windram be appointed as Deputy Chairman of the Coalville Special Expenses Working Party f... Decided Open
2 Jun 2026 Minutes of the Previous MeetingRESOLVED THAT: The minutes of the meeting held on 11 February 2026 be confirmed as an accurate record of proceedings. Decided Open
11 Feb 2026 Minutes of the Previous MeetingRESOLVED THAT: The minutes of the meeting held on 2 December 2025 be confirmed as an accurate record of proceedings. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies