RESOLVED THAT The progress against the Council Delivery Plan Actions and Performance Indicators for Quarter 3 of the financial year be noted by Cabinet. Reason for decision: That Cabinet notes the progress against the corporate objectives and performance indicators for Quarter 3
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Presented by Councillor Richard Blunt, Leader of the Council
PH Briefed x
Background Papers Council Delivery Plan Public Report: Yes Agenda for Council on Tuesday, 7 September 2021, 6.30pm-North West Key Decision: No Leicestershire District Council (nwleics.gov.uk)
Financial Implications The forecast financial position as at Quarter 3 for the financial year 2022/23 is set out in the report.
Signed off by the Section 151 Officer: Yes
Legal Implications There are no legal implications arising.
Signed off by the Monitoring Officer: Yes
Staffing and Corporate Implications Signed off by the Head of Paid Service: Yes
Purpose of Report The report provides members of Cabinet with information on the performance and progress made against the Council Delivery Plan actions and performance indicators for Quarter 3
Reason for Decision That Cabinet notes the progress against the corporate objectives and performance indicators for Quarter 3
Recommendations THAT CABINET NOTES THE PROGRESS AGAINST THE COUNCIL DELIVERY PLAN ACTIONS AND PERFORMANCE INDICATORS FOR QUARTER 3 OF THE FINANCIAL YEAR.
1. INTRODUCTION
1.1This report provides an update of the Councils key objectives and performance indicators for the third quarter of the financial year – the period October to December 2022. Performance is managed at a strategic, service, operational and individual level. This report provides information measured against the Council Delivery Plan agreed by full Council in September 2021. The detail of Quarter three performance is set out in Appendix 1 below. 1.2 The quarterly performance reports seek to recognise good performance, share best practice across the organisation and to identify ‘performance gaps’ highlighting if and where action is required to meet targets. Once these gaps are identified, intervention plans will be created or adapted to improve performance towards the target. This will be part of a continual cycle of review and action.
2. SUMMARY OF PERFORMANCE
2.1This report sets out the performance and progress against the Council Delivery Plan actions and key performance indicators.
2.2A report on the progress made against the Council Delivery Plan actions and indicators is included in the tables below at 3. Below. During the quarter twenty-seven of the thirty-five actions in the Council Delivery Plan were in progress and eight had been achieved. Looking at the forty-four performance indicators, at the end of Quarter 3, twenty-seven had been achieved, one was within 5% tolerance, five had not been achieved and eleven are reported annually (or where the data was not available at the time of writing this report).
Council Delivery Plan Actions Actual 2022/23
Number of actions achieved. 8
Number of actions in progress 27
TOTAL 35
Performance Indicators 2022/23 Actual RAG
Number of targets achieved. 27
Number of targets within 5% 1 variance of target (10% financial)
Number of targets Not achieved 5
Annual Measure / Not applicable 11
TOTAL 44
2.3The following notable achievements are some of the highlights of the quarter three report: -
2.4Supporting Coalville to be a more vibrant, family friendly town.
Footfall at the Coalville Newmarket has continued to increase by a third on the previous quarter despite the difficult economic and trading conditions in the retail sectors. The Council continues to promote the facility through targeted events designed to increase the footfall in the market and its immediate outdoor vicinity. Following preparatory work in quarter three, a marketing exercise to attract new leisure operators to Coalville is scheduled for the fourth quarter of the year. The Council is continuing to consider options for the former Hermitage Leisure Centre site, which will now be demolished during quarter four.
2.5Our communities are safe, healthy, and connected.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.