RESOLVED THAT: The Monitoring Report be considered and the elements making positive progress and those where there is a need for early intervention be highlighted. Reason for decision: to make Members aware of the early progress of the Council Delivery Plan.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
2.1The Council Delivery Plan contains four key priority areas – notably “A well run Council, Clean and Green, Housing and Communities and Planning and Regeneration.”
2.2There are 18 Key Performance Indicators (KPIs) in the Council Delivery Plan.
Six relate to Planning and Regeneration, Five to Housing and Community Services, four relate to Clean and Green and three relate to A Well-run Council.
The table below shows the performance in quarter 4 overall against each of the four priority areas.
The table shows the priorities that have been completed, those that were within a 5% variance of being completed, those that were not completed at all and those that were not applicable (usually due to no data being available, because they are scheduled for completion at a later stage of the plan.) Our Priorities
A well run council 33.33% 66.66%
Clean and Green 75% 25%
Housing and Communities 50% 16.66% 33.33%
Planning and Regeneration 33.33% 33.33% 33.33%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Complete 5% Variance Not Complete N/A
There are 18 KPIs in the Council Delivery Plan.
Six relate to Planning and Regeneration, two are on track, two are within a five percent variance and two are scheduled for completion at a later stage.
Five relate to Housing and Community Services - Three are on track, one within the five percent variance and two scheduled for completion at a later stage.
Four relate to Clean and Green - Three are not complete and one is scheduled for completion at a later stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.