RESOLVED THAT: 1) It be agreed to enter in to contract with a construction company for the design and build of six properties following a procurement exercise as detailed in the report up to a value of £1,600,000. 2) £1,600,000 be transferred from the development pool to the active pool in the Housing Revenue Account 2025/26 Capital Programme. 3) Authority be delegated to the Strategic Director responsible for housing to finalise and agree all necessary agreements and take appropriate procedural and process steps to deliver the above. Reason for decision: To provide high quality housing to the district
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
1.1Queens Street Measham is an internal development opportunity that has been under development since 2021.
1.2The planning authorisation was approved in early 2022 for the erection of six dwellings.
1.3Since then, due to resource constraints and the impacts of COVID, the development has experienced significant delays.
1.4In early 2025, a consultant was appointed to work with the Council to bring this site to fruition. The project is now at a stage where it can move forward to procure and appoint a contractor to undertake the build of this project.
1.5Subject to the successful award of a contract, the build could commence in late 2025/26 with completion later in 2026/27.
2.0TENDER PROCESS
2.1The proposed development consists of six properties comprised of a three- bedroom detached house, a one-bedroom bungalow and four two-bedroom semi-detached houses. This broadly aligns with the housing needs of applicants on the Council’s housing register.
2.2This report is seeking approval to enter into a contract upon completion of a tender process for the contractor to develop the Queens Street project.
2.3The Council will follow an open tender. The Housing Service will be supported by the Council’s procurement team. On this occasion, a framework provider will not be used as it is considered that this would limit opportunities for local businesses who had shown an interest in the development of this site at the informal pre- engagement stage of the project.
2.4The tender process will be open for a period of 6 weeks, and on receipt be evaluated on quality at 60% and price at 40% ensuring a quality tender is preferred over a cheaper option. This will be evaluated by the New Build Project Officer, the Asset Manager, and a third individual from our consultant Michael Dysons Associates to ensure no potential for tie. The successful bidder will be chosen based on their cost sum analysis breakdown along with a grading against their quality questions to provide a ranking of each tender return, the highest scoring tenderer will be chosen. The scores from the three evaluators will be averaged to create a single value which will make up the ranking.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.