North West Leicestershire District Council
Cabinet, Tuesday 19 May 2026 at 5.00pm

MOIRA FURNACE VISITOR EXPERIENCE IMPROVEMENT PROGRAMME (PHASE TWO)

Approved Executive 1 paper

AI summaryNorth West Leicestershire Cabinet backs £2.455m plan for Moira Furnace visitor centre, operational building and improved access, to be funded from the Business Rates Reserve over 2026-2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase Two improvements at Moira Furnace
Money£2.455m from Business Rates ReserveSpent 2026 to 2028
What happens nextRecommend allocation to full CouncilProcure design team via Scape Framework
Who it affectsVisitors, Trust, local businessesHeart of the National Forest area

What was decided

Cabinet agreed to recommend allocation of £2.455m to the Council's Capital Programme, to be funded from the Business Rates Reserve. Report 4.1, P17

Cabinet approved using an appropriate procurement framework to commission the professional design team. Report 5.1

Authority delegated to the Director of Place, in consultation with the Portfolio Holder, to finalise the construction contract and related agreements within the budget.

Why

To progress Phase Two of the Moira Furnace Visitor Experience Programme, building on Phase One works that concluded in March 2026. Report 1.5, 1.6, 2.0, 2.1

To deliver a 2021 Options Appraisal recommendation and meet the Council's Contract Procedure Rules and procurement legislation. Report 2.1, 2.4

To increase visitor numbers, lengthen dwell time, improve facilities and support the Trust's financial sustainability. Report 1.7, 3.2, 6.2

What happens next

The £2.455m allocation will go to full Council for inclusion in the Capital Programme. Report 4.1

Design team to be procured via a call-off contract from the Scape Framework; construction procurement method to be determined later, likely mini-competition on a national framework. Report 5.1

A separate report on the uncosted Phase Three will be presented to Cabinet before any work proceeds. Report 2.3, 4.2

The money

  • £2,455,000 Total Phase Two allocation to the Capital Programme over 2026-2028 Report 4.1, P17
  • £446,000 Consultancy fees (RIBA 2-3, 4 and 5-7) Report P18
  • £204,650 RIBA 2-3 design fees Report P18
  • £102,280 RIBA 4 design fees (budget figure) Report P18
  • £139,000 RIBA 5-7 design fees (budget figure) Report P18
  • £2,009,000 Construction works total (including inflation and contingency) Report P19, P20
  • £465,000 Operational and storage facility for the Trust Report P19
  • £990,000 New visitor hub (cafe, interpretation, toilets) Report P19
  • £554,000 Improved site access, bridge loft, parking (with EV charging) and play facilities Report P19
  • £45,000 Annual Council grant to the Trust towards running costs Report 1.3
  • approximately £140,000 per annum Current annual operational costs of the site Report 1.3

Options considered

  • Chosen: Proceed with Phase Two improvements as set out. Supports 2021 Options Appraisal and aims to grow visitor numbers and Trust income Report 2.1, 2.2, 3.1
  • Rejected: Proceed with Phase Three (basement, monument interpretation and illumination). Currently uncosted; a full report will go to Cabinet before any work Report 2.3, 4.2
  • Chosen: Procure the design team via the Scape Framework call-off. Identified as the appropriate procurement route Report 5.1
  • Chosen: Mini-competition using a national framework of contractors for construction. Likely procurement route; final Cabinet approval will be required to appoint due to value

Implications

  • Financial: £2.455m is to come from the Business Rates Reserve, to be added to the Capital Programme. Report 4.1, P17
  • Legal: The Council must protect the scheduled monument, with Historic England overseeing compliance; all required consents for Phase One were obtained. Report 1.3, 1.4, 6.7, P62
  • Risk: Risks logged in the RAID register include materials availability, contractor pricing, required permissions, inflation and Local Government Reorganisation. Report 7.1
  • Risk: Tight delivery timetable is linked to LGR; delaying approval would significantly increase the risk of the project not proceeding. Report P63
  • Staffing: Phase Two will deliver a new on-site operational and storage facility for the Trust, supporting its site manager, site assistant and seasonal events coordinator. Report 2.2, 6.3
  • Equalities: Phase Two facilities are to be designed for all users, with safeguarding principles considered in design and planning. Report P47, P48
  • Climate: Plans include EV charging points and biodiversity improvements as part of the site access and parking upgrade. Report 2.2, P51
  • Other: Scrutiny members raised parking-charge concerns and asked for resident concessions and a balance between income and accessibility. Report P61

Who and where

  • Moira Furnace Museum Trust (charity number 702783), the site operator Report 1.3, 6.1, 6.4
  • Visitors to the museum and country park, including local residents Report 1.3, 2.2, 3.2
  • Seven active trustees and more than 80 registered volunteers Report 6.4
  • Associated businesses and tenants operating on the site Report 3.2, 9.2
  • Leicestershire County Council, the National Forest Company and adjoining private landowners Report 6.8
  • Historic England, as regulator for the scheduled monument Report 1.4, 6.7

Timeline

  • 16 April 2026: Phase One works launch event held after restoration concluded in March 2026 Report 1.5
  • 23 April 2026: Community Scrutiny Committee considered the Phase Two proposals Report 1.8, 10.1
  • May 2026: Museum accreditation renewal expected to be confirmed Report 6.6
  • 19 May 2026: Cabinet considered and recommended the Phase Two allocation Report P59
  • July 2026 to October 2026: RIBA 2-3 concept design and spatial coordination for the three Phase Two elements Report P37
  • October 2026 to February 2027: Planning consent sought for the three Phase Two elements Report P37
  • March 2027 to August 2027: RIBA 4 technical design and tendering for the three Phase Two elements Report P37
  • September 2027: Installation of the operational and storage facility Report P37
  • October 2027 to February 2028: RIBA 5, 6 and 7 progression of the visitor centre/café Report P37
  • February 2028 to May 2028: RIBA 5, 6 and 7 progression of site access, parking, bridge loft and play facilities Report P37

Plain English for the jargon

  • RIBA stages: Royal Institute of British Architects work stages: 2-3 concept design, 4 technical design and tendering, 5-7 construction to handover.
  • UKSPF: UK Shared Prosperity Fund, a government fund that part-financed Phase One works.
  • LGR: Local Government Reorganisation, flagged as a timing risk for project delivery.
  • Scape Framework: A procurement framework to be used to call off the professional design team.
  • RAID register: Risks, Assumptions, Issues and Dependencies register used to log project risks.
  • EV charging: Electric vehicle charging points included in the upgraded parking provision.
  • Scheduled monument: A building or site of national importance protected under law; Historic England oversees the Council's duties at Moira Furnace.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED THAT: 1) The comments and recommendations of the Community Scrutiny Committee on 23 April 2026 be considered. 2) The allocation of £2.455m to the Council’s Capital Programme be recommended to Council. 3) The use of an appropriate procurement framework to commission the professional design team be approved. 4) Authority be delegated to the Director of Place in consultation with the Portfolio Holder to: a) Negotiate, agree and finalise the terms of the construction contract within the budget. b) Complete such other agreements as shall be necessary to implement the project, within the approved budget. Reason for decision: Cabinet approval required to enable the progression of phase two Moira Furnace Visitor Experience Programme in compliance with the Council’s Contract Procedure Rules and procurement legislation.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet

Background

1.1The regeneration of sites within North West Leicestershire is a key priority within the Council Delivery Plan and the Moira Furnace project is one of the flagship schemes highlighted in the Districtwide Regeneration Framework 2024. 1.2 The continued development of Moira Furnace Museum and Country Park will contribute to the Council's long held ambition to transform the former coalfield area of Moira and Donisthorpe as part of the National Forest’s transformation of the Heart of the National Forest.

1.3Moira Furnace is owned by the Council and is listed as a scheduled monument dating back to 1806. It is considered one of the most well-preserved blast furnaces in the country. The Furnace and site are operated by the Moira Furnace Museum Trust (the “Trust”) on behalf of the Council, and the Trust receives an annual grant of £45,000 from the Council towards the running costs. The grant contributes towards operational staffing costs. All other day-to-day running costs and expenses (e.g. utility costs) are funded by the Trust, with annual operational costs currently being approximately £140,000 per annum.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MOIRA FURNACE VISITOR EXPERIENCE IMPROVEMENT PROGRAMME (PHASE TWO)Minutes 1.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 20 attended
RB
Councillor Richard BluntChair, present
MW
Councillor Michael WyattDeputy Chair, present
TG
Councillor Tony GillardCommittee Member, present
KM
Councillor Keith Merrie MBECommittee Member, present
NR
Councillor Nicholas RushtonCommittee Member, apologies
TS
Councillor Tony SaffellCommittee Member, present
AW
Councillor Andrew WoodmanCommittee Member, present
AT
Allison ThomasOfficer, in attendance
JA
James ArnoldOfficer, in attendance
AB
Andy BartonOfficer, in attendance
AC
Anna CrouchOfficer, apologies, sent representative
BL
Beth LeonardDemocratic Services Officer, in attendance

All 20 on the meeting page

On this subject at North West Leicestershire

Search all
  1. MOIRA FURNACE VISITOR EXPERIENCE IMPROVEMENT PROGRAMME (PHASE TWO)This decision
  2. Moira Furnace – Capital Works Programme UpdateApproved

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open