North West Leicestershire District Council
Cabinet, Tuesday 22 September 2026 at 5.00pm

Marlborough Centre Regeneration

Noted Executive 2 papers

AI summaryCabinet delegates authority to award Marlborough Centre enabling and fit out contracts to Lindum, so work can start before local government reorganisation limits spending.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedWithin agreed £6,464,627 budget envelope
Money£6,464,627 total budget£5,549,023 remaining; enabling works circa £500,000
What happens nextNew planning application September 2026Enabling works begin Autumn 2026
Who it affectsNot stated

What was decided

Cabinet delegated authority to the Strategic Director of Place, in consultation with the Leader, Monitoring Officer and S151 Officer, to award the enabling works contract and the fit out works contract and to agree all other costs, all within the agreed budget.

The delegation is needed so contracts can be awarded promptly and before a Section 24 Direction linked to Local Government Reorganisation limits the Council's ability to spend. Report 7.1, 7.2

Why

The project, which started in 2021 with a £4,464,627 budget later raised by £2,400,000, is nearing the end of its pre-construction stage and Lindum is expected to offer the best value price for the next stages. Report 1.1, 2.6, 2.7

Using the Pagabo framework is a compliant procurement route that has already tested suppliers, and the Council's cost consultants Gleeds advise it represents good value. Report 2.1, 2.10, 3.1

Completing the building will hand a finished asset rather than a liability to the new successor council under Local Government Reorganisation. Report 7.2

What happens next

A new planning application covering small design changes will be submitted in September 2026 and decided while enabling works proceed. Report 5.2

The enabling works package, covering fire escape replacement at Stafford House, demolition of the Owen Street infill building and car park access works, is due to start in Autumn 2026, with the main fit out and construction phase starting in Spring 2027 and lasting about 65 weeks. Report P24, P25, 4.2

The money

  • £4,464,627 Original business plan budget agreed August 2021 Report 1.1
  • £2,400,000 Additional budget approved by Council in February 2026 Report 1.1
  • £6,464,627 Total agreed project budget envelope Report 6.1
  • £1,315,603 Amount already spent, including the 2022 purchase price Report 6.1
  • £760,000 Acquisition price for the Marlborough Centre paid in 2022 Report 6.1
  • £146,440 Further sum committed to complete the PCSA with Lindum Report 6.1
  • £5,549,023 Budget remaining to complete the project Report 6.2
  • £500,000 Indicative order for the enabling works contract Report 2.9
  • £500,000 Latest estimate for the fit out works (expected November) Report 6.3
  • £1,000,000 Approximate gap between Lindum and the next cheapest contractor for the whole project Report 2.6

Options considered

  • Chosen: Award enabling and fit out contracts to Lindum via Pagabo framework under delegated authority. Lindum offered the most competitive overhead, profit and preliminary rates; framework use is procurement compliant and best value; needed to complete before Section 24 Direction takes effect Report 2.6, 2.10, 3.1, 7.1
  • Rejected: Wait for full Cabinet approval once final prices are known. Could delay the project past the start of Local Government Reorganisation restrictions Report 7.1, 7.2

Implications

  • Financial: Total project budget is £6,464,627, of which £5,549,023 remains, and Lindum's latest estimate suggests this is sufficient to complete the project. Report 6.1, 6.2, 6.3
  • Risk: The two named risks are contract costs exceeding the budget and changes to Council decision making processes arising from Local Government Reorganisation. Report P40
  • Legal: A further planning application is needed because small design changes identified during the PCSA go beyond the November 2024 consent. Report 5.1, 5.2
  • Equalities: Several of the new flats have been designed to be accessible. Report P40
  • Climate: Climate and zero carbon matters are being addressed through the planning permission and Building Regulations. Report P40
  • Other: The contractor is committed to delivering social benefits, with details still to be agreed. Report P40

Who and where

  • Residents and visitors to Coalville town centre, who will see a restored Marlborough Centre and improved Marlborough Square Report P40
  • Future occupants of the upper floor residential units Report 1.3, P25
  • Ground floor retail tenants, who may be offered shop front improvements Report 1.3
  • Lindum Group as the contractor across all three delivery stages Report 1.4, 2.4, 2.7
  • Gleeds, acting as cost consultant and project manager Report 2.1
  • The successor council created by Local Government Reorganisation Report 7.2

Timeline

  • August 2021: Business plan for the Marlborough Centre project approved with a budget of £4,464,627 Report 1.1
  • 2020: Project included in the Council's Future High Streets Fund application Report 7.2
  • February 2022: Council purchased the Marlborough Centre building for £760,000 Report 1.2, 6.1
  • 2023: Coalville Regeneration Framework published, listing the project as a key initiative Report 7.2
  • November 2024: Planning consent granted for the refurbishment (Ref: 22/01823/FULM) Report 5.1
  • 2025: Pre-Construction Services Agreement awarded to Lindum Group Report 1.4
  • 29 July 2025: Cabinet approved selection of Lindum for the Stage 1 PCSA contract Report 2.4
  • February 2026: Council increased the project budget by £2,400,000 Report 1.1
  • September 2026: New planning application covering PCSA design changes to be submitted Report 5.2
  • Autumn 2026: Enabling works package due to begin Report 4.2
  • 22 September 2026: Cabinet to be asked to note progress and delegate authority to award the next contracts Report 2.9
  • November 2026: Fit out works cost expected from Lindum Report 2.9
  • Spring 2027: Main construction phase due to start Report 4.2

Plain English for the jargon

  • PCSA: Pre-Construction Services Agreement, under which a contractor develops detailed design and costings before main works contracts are awarded
  • RIBA Stages 3 and 4: Royal Institute of British Architects work stages covering developed design and technical design
  • JCT Design and Build 2024: Standard UK contract published by the Joint Contracts Tribunal for design and build projects
  • Section 184 agreement: Highways Act provision allowing a vehicle crossing over a footway between private land and the highway
  • Section 24 Direction: Direction expected under Local Government Reorganisation that will restrict a council's ability to award higher value contracts
  • LGR: Local Government Reorganisation, the restructuring of councils in the area
  • Pagabo Alliance Framework: Pre-vetted construction framework used to compliantly appoint contractors
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item70

Resolved

RESOLVED THAT: 1) The progress of the Marlborough Centre Project be noted. 2) Authority be delegated to the Strategic Director of Place (in consultation with the Leader of the Council, Monitoring officer and S151 officer) to award the enabling works contract for the Marlborough Centre Project within agreed budget. 3) Authority be delegated to the Strategic Director of Place (in consultation with the Leader of the Council, Monitoring officer and S151 officer) to award the Fit Out Works contract for the Marlborough Centre Project subject to the cost being within agreed budget. 4) Authority be delegated to the Strategic Director of Place (in consultation with the Leader of the Council, Monitoring officer and S151 officer) to agree all other costs and payments required to deliver the Marlborough Centre Project up to the limit of the agreed budget. Reason for decision: The project has been running since 2021 and there is a strong desire to complete it prior to LGR which necessitates prompt award of contracts as soon as prices are known. The anticipated contract sums will be at a level where under the constitution a decision of Cabinet or delegated authority are required.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Marlborough Centre Regeneration Cabinet ReportReport Copy on its way
PDF
Marlborough Centre RegenerationMinutes 112 KB Download

At this meeting

Whole meeting

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open