RESOLVED to note the outcomes of the consultation, outlined in Appendix 1 of the report, and approve the move to the next stage of consultation, the issuing of Statutory Notices. Reasons for decisions Following the positive responses to the consultation, moving to the next stage of consultation, issuing Statutory Notices, will enable the expansion of Heathfield Primary School to be completed for 1 September 2015. Other options considered No other options were considered as there is a demand for schools places in the area.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Subject: Proposed expansion of Heathfield Primary School, Basford
Corporate Alison Michalska, Corporate Director for Children and Adults Director(s)/ Director(s): Portfolio Holder(s): Councillor David Mellen, Portfolio Holder for Children’s Services Report author and Jennifer Shadbolt, Project Manager, School Organisation contact details: [email protected] 0115 87 65629 Key Decision Yes No Reasons: Expenditure Income Savings of £1,000,000 or Revenue Capital more taking account of the overall impact of the decision Significant in terms of its effects on communities living or working in Yes No an area consisting of two or more wards in the City Subject to call-in Yes No Total value of the decision: Nil Relevant Council Plan Strategic Priority: Wards affected: World Class Nottingham Basford and Bulwell Forest Work in Nottingham Safer Nottingham Neighbourhood Nottingham Date of consultation with Portfolio Family Nottingham Holder(s): Healthy Nottingham 11 September 2013 Leading Nottingham Summary of issues (including benefits to citizens/service users): On Monday 30 September 2013, a four week consultation with parents, carers, staff, governors and community members on the proposal to expand Heathfield Primary School commenced. 66% of responses to the consultation were in favour of the proposal. This report updates Executive Board on the outcomes of the consultation and seeks approval to move to the next stage of the consultation process. Recommendation(s): 1 Note the outcomes of the consultation, outlined in Appendix 1, and approve the move to the next stage of consultation, the issuing of Statutory Notices
1 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
1.1The recent increase in Nottingham’s population has put pressure on the availability of primary school places and the city, like many other major UK cities, is experiencing a shortage of places in primary schools.
1.2In April 2013, Central Government announced the Targeted Basic Need Programme, which is additional capital funding available to local authorities to help mitigate the pressure on primary places. Nottingham City Council submitted a bid for some of this funding and this bid was successful. Part of the criteria for applications was that land to be used for expansion had to be in the possession of the local authority and cleared for building work, so additional places could be provided for September 2015.
1.3Pupil projection data had already identified Basford as an area requiring additional primary school places and, as the former Henry Mellish site was available, a bid was submitted for funding to expand Heathfield Primary School. The proposal is for Heathfield to become a split site primary school when the new school building on the ex Henry Mellish site opens on 1 September 2015. 1.4 £3.8 million has been awarded to Nottingham City Council from the Targeted Basic Need Programme and early estimated costs indicate the expansion of Heathfield will cost £4.387 million. The remaining £587,000 will be funded from the Basic Need Grant.
1.5The Portfolio Holder for Children’s Services gave approval to start consultation on this proposal on 11 September 2013: http://open.nottinghamcity.gov.uk/comm/download2.asp?dltype=inline&filename=1 070/DD1007.pdf
1.6Heathfield will have 280 primary places at the Scotland Road site (the current school building) and a further 420 places at the new site, which will equate to 100 places per year group from years Reception to Year 6. The new school building will have 60 places per year group, which is two forms of entry, and a 52 full time equivalent (FTE) place nursery.
1.7Both the Scotland Road site and the new site will have a nursery and years Reception through to Year 6, so they will be run as mirror image primary schools retaining the primary school experience for children.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.